Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager.

Similar presentations


Presentation on theme: "Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager."— Presentation transcript:

1 Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager

2 Council policy - promote sustainable design and construction Design for energy efficiency -reducing C0 2 & fuel poverty Promote use of environmentally friendly materials -reducing pollution and environmental damage  Require sustainable accredited timber  -avoids deforestation / loss of biodiversity, etc

3 Ethelred tower blocks Ward, Brittany and Elkington Required major improvements Decent homes work needed

4 Ethelred’s problems Spalling concrete Ineffective heating and ventilation Generic heating and hot water charge for residents but high energy costs for Lambeth as landlord Socio-economic study May 2009: –53% of respondents suffered condensation –38% could not keep their homes comfortably warm due to draughty windows.

5 Funding Lambeth had prior experience of carbon reduction projects Positive track record on sustainability helped us secure additional funding –Government Office London £6.8m

6 Sustainable design and construction Holles house refurbishment- proven 50% energy use reduction via a range of sustainability measures

7 Sustainable legal timber Fairfax House – the first construction project in Britain to be independently certified by the Forest Stewardship Council for its use of sustainable timber.

8 Boatemah Walk

9 Before…

10 After!

11

12

13 Ethelred tower block refurbishment New double glazed windows Insulated external cladding 63KWp Solar PV New Communal boilers CHP plant (310KWe) New wet radiators with room thermostats and heating programmers

14 Green roofs Sedum roofs Promoting Biodiversity Reducing storm water run- off Improving air quality Insulation / cooling benefits

15 Challenges PV system output Cladding - delays

16 Challenges Working with residents in occupation

17 Successes Significantly improved conditions for residents 80% CO 2 reduction in landlords footprint Reduced energy costs for residents and Lambeth Blocks renewed to give a minimum 30 years of further life

18 The new look towers

19 Thank you


Download ppt "Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager."