Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Project Schedule and Budget

Similar presentations


Presentation on theme: "The Project Schedule and Budget"— Presentation transcript:

1 The Project Schedule and Budget
Chapter 7 Copyright 2012 John Wiley & Sons, Inc.

2 Learning Objectives Describe the Project Management Body of Knowledge (PMBOK®) area called project cost management. Develop a Gantt chart. Develop a project network diagram using the activity on the node (AON) technique. Identify a project’s critical path and explain why it must be controlled and managed. Develop a PERT diagram. Describe the concept of precedence diagramming and identify finish-to-start, start-to-start, finish-to-finish, and start-to-finish activity relationships

3 The Importance of Project Cost Management
IT projects have a poor track record for meeting budget goals A 2011 Harvard Business Review study reported an average cost overrun of 27 percent. The most important finding was the discovery of a large number of gigantic overages or “black swans”

4 Examples of how not to mange costs
The U.S. government (e.g. IRS) The United Kingdom’s National Health Service IT

5 Project Cost Management Processes
Process Group Cost Management Process Major Output Planning CP1: Planning Cost Mgmt Cost Management Plan CP2: Estimating Costs Activity Cost Estimates CP3: Determining the Budget Cost Performance Baseline Monitoring and Controlling MC1: Controlling Costs Work Perf. Measurements Budget Forecasts

6 What is Cost and Project Cost Management?

7 Project Cost Management Processes
Scope Baseline Schedule Baseline Estimate bases Project Funding Req. Determine Budget Control Costs Estimate Costs Activity Cost Estimates Cost Baseline

8 PMBOK® Project Cost Management
Estimate Costs Focuses on the processes to estimate the monetary resources needed to complete the project work or activities. Determine Budget Aggregating the individual cost for each of the project activities or work package components to determine the cost baseline or overall project budget. Control Costs Updating the project’s status while monitoring the project’s budget and managing any changes to the baseline plan.

9 The Project Planning Framework

10 Budget and Schedule Development

11 Developing the Project Schedule
Project Management Tools

12 Gantt Chart for Planning

13 Gantt Chart Reporting: Project’s Progress

14 Project Network Diagram: Activity Analysis for AON
Description Estimated Duration (Days) Predecessor A Evaluate current technology platform 2 None B Define user requirements 5 C Design Web page layouts 4 D Set-up Server 3 E Estimate Web traffic 1 F Test Web pages and links C,D G Move web pages to production environment D,E H Write announcement of intranet for corp. newsletter F,G I Train users J Write report to management H,I

15 Activity on the Node (AON) Network Diagram

16 Possible Activity Paths
Possible Paths Path Total Path 1 Path 2 Path 3 Path 4 Path 5

17 Critical Path

18 PERT

19 Activity Analysis for PERT
Predecessor Optimistic Estimates (Days) Most Likely Estimates (Days) Pessimistic Estimates (Days) Expected Duration A None 1 2 4 B 3 5 8 C D 6 E F C,D G D,E H F,G I 9 J H,I .5

20 Activity Analysis for PERT

21 Possible PERT Activity Paths
Possible Paths Path Total Path 1 Path 2 Path 3 Path 4 Path 5

22 Precedence Diagramming Method - PDM
Based on 4 fundamental relationships

23 Lead and Lag times Lead is starting the next task before the first task is complete Lag (or negative lead) is the adding of a buffer of time before the next task begins

24 Critical Path Analysis (with slack time)


Download ppt "The Project Schedule and Budget"

Similar presentations


Ads by Google