SERVICING MISSION OBSERVATORY VERIFICATION (SMOV) SMOV PLANNING Carl Biagetti COS Science Team Meeting 26 Oct. 2007.

Similar presentations


Presentation on theme: "SERVICING MISSION OBSERVATORY VERIFICATION (SMOV) SMOV PLANNING Carl Biagetti COS Science Team Meeting 26 Oct. 2007."— Presentation transcript:

1 SERVICING MISSION OBSERVATORY VERIFICATION (SMOV) SMOV PLANNING Carl Biagetti COS Science Team Meeting 26 Oct. 2007

2 COS Science Team Meeting2 GENERIC SMOV PROGRAM A SMOV program is associated with each servicing mission (viz. www.stsci.edu/smov) Generic SMOV goals –Timely recommissioning of the Observatory for science operations Commission newly installed science instruments Recommission existing science instruments –Recommission Observatory subsystems for normal operations –Validation of other on-orbit replacements & installations –Early Release Observations Demonstrate upgraded science capabilities to astronomical community and general public

3 26 Oct. 2007COS Science Team Meeting3 SMOV Policies, Oversight, ERO NASA H/Q STScIHST PROJECT SMOV MGMT TEAM 441 Burley STScI - Biagetti STScI SMOV PLANNING TEAM Lead – Biagetti ACS – LSmith COS – Keyes OTA/FGS – Lallo, Nelan NICMOS/NCS – Wiklind/Wheeler STIS – Proffitt WFC3 – MacKenty, Turnbull Eng. Spt. – Wheeler, Long ERO – Noll, OPO Planning & Scheduling - Reinhart, Chapman, Periello, et al. OED Ops – Ellis, et al. Archive – TBD IT - TBD SMOV Policies, Oversight, ERO PROJECT SMOV PLANNING TEAM 441 – Burley STScI SMOV PLANNING TEAM CHAMP/MOSES IPT, IDT, BASD SMOV OPS TEAM HST Ops, STScI P&S, SI Teams, OED, OPO,441, 442 SMOV TTRB DO, HST MO, INS, OED, OPO, 441 PROPOSAL IMPLEMENTATION TEAM SMOV Policies, Oversight, ERO PROJECT CONTAMINATION WORKING GROUP (CWG) P&S,SI/IDT Teams, OED, OPO, 441, SMOV PIs SMOV4 PLANNING TEAMS & INTERFACES PROJECT CONTAMINATION WORKING GROUP (CWG) SERVICING MISSION OPS WG (SMOWG) 441,442, STScI/IDT SI Teams OBSERVATORY SUBSYSTEMS WORKING GROUPS 441, 442, STScI SI Teams PROJECT CONTAMINATION WORKING GROUP (CWG) Management/direction flow down Information/reporting flow up.

4 26 Oct. 2007COS Science Team Meeting4 SMOV4 PLANNING PROCESS FLOW SMOV CONCEPT STATEMENT REQUIREMENTS DEFINITION BASELINE PLAN STSCI, SMOV Mgmt Team STScI SMOV Team, 441 SMOV Planning Team PROPOSAL SUBMISSION PROPOSAL IMPLEMENTATION OPERATIONS PLANNING STScI Proposal Implementation Team SMOV Ops Working Group, 441 SMOV Planning Team SMOV OPERATIONS SMOV Ops Team, SMOV TTRB (& SMOV CLOSURE) STScI SMOV Team, 441 SMOV Planning Team

5 26 Oct. 2007COS Science Team Meeting5 SMOV4 Planning Schedule for Aug 2008 Launch Start End Activity ====== ====== ========== ============================ Oct06 Mar07 Requirements Update 21Mar07 SMOV Requirements Review Mar07 Oct07 SMOV Planning - Activity Summaries - Special Commanding Development - Integrated plan 12Oct07 SMOV Project Review Oct07 Aug08 SMOV Implementation Phase - Proposal generation/iteration - ERO program - Operations planning Jun08 Aug08 Test Calendar/SMS generation Jul08GSFC Launch Readiness (FRR) Jul08 STScI SM4/SMOV Readiness Review 07Aug08 SM4 Launch 15Aug08 ~Dec08 SMOV4 Feb09 SMOV4 Closure Review

6 26 Oct. 2007COS Science Team Meeting6 SMOV4 INITIAL CONDITIONS New gyros New batteries Two new Science Instruments (SIs) –COS in place of COSTAR –WFC3 in place of WFPC2 2 Restored SIs –STIS –ACS Refurbished FGS –FGS2R2 in place of FGS2R Other effects –NICMOS “warming up” for 8-10 days

7 26 Oct. 2007COS Science Team Meeting7 SMOV4 -BASIC APPROACH- Proceed with commissioning of existing SIs while new ones outgass Avoid “bright earth” occultations (BEA) for 21 days following Release –Use bright earth “allowances” during the BEA period Perform the “long” VDT early in BEA period FGS2R2 – Start commissioning prerequisites early using BEA-compatible targets and BEA allowances –Allows relief to FGS3 guiding asap STIS – Use BEA-compatible targets for early commissioning activities Start NCS early for NICMOS cool-down –2-week cooldown assumed for planning purposes SMOV SI commissionings proceed pretty much independently of each other. –Each SI undergoes a set of engineering activation activities, optical alignment/focus activities, and science calibrations –EROs and GO science are enable asap on a per channel basis. * BEA = Bright Earth Avoidance (period)

8 26 Oct. 2007COS Science Team Meeting8 SMOV EXTERNAL ORBITS BY SI/SS PRELIMINARY ESTIMATES AS 0F 15OCT07 POST-BEA EXTERNAL ORBITS PCS 10 (VDT) WFC3132* COS145* STIS 20* ACS 30* NICMOS 56* FGS 6 399 TOTAL * Does not include ERO orbits BEA EXTERNAL ORBITS PCS VDT 5 orbits after 36 Hrs @ +V3 ACS 2 orbits -- BEA WINDOW FGS 6 orbits -- BEA WINDOW 20 orbits -- BEA COMPLIANT STIS 8 orbits -- BEA COMPLIANT

9 26 Oct. 2007COS Science Team Meeting9 SMOV4 EXTERNAL ORBIT ESTIMATES BY WEEK (post-BEA, as of 12Oct007)

10 26 Oct. 2007COS Science Team Meeting10 SMOV4 SCHEDULE as of 12 Oct. 2007

11 26 Oct. 2007COS Science Team Meeting11 SMOV PROJECT REVIEW COS-RELATED ITEMS Need to study possibility of shortening the COS commissioning period. –Preliminary discussions have succeeded in shortening it by 2-3 weeks. FUV Door Opening – How many HST high voltages must be off for this operation?

12 26 Oct. 2007COS Science Team Meeting12 SM4 SIMS/JIS & SMGT HST Project conducts a series of operational simulations (Sims) and Joint Operational Simulations (JIS) –To simulate various portions of SM4 –Familiarize participants with Operational procedures, interfaces, and protocols –Certify participants for SM4 support SIM 4 (EVA 3) COS, ACS Repair –10/11/2007 - complete SIM 7-8 (EVA 3-4) COS, ACS Repair, STIS Repair, NOBL8 –11/28-29/2007 JIS 1 (EVA 3) COS, ACS Repair –03/18/2008 Servicing Mission Ground Tests (SMGT) –Test ability of ground system to support selected SM4 and SMOV4 activities Special commanding is tested

13 26 Oct. 2007COS Science Team Meeting13 EARLY RELEASE OBSERVATION (ERO) PLANNING - SM4 EROs will be planned for each of the HST Science Instruments. - Keith Noll is ERO lead at STScI. - ERO planning teams are in place for each instrument. - Planning for COS and WFC3 is well developed. - Multiple targets have been identified and are being prioritized. -Recommendations to NASA HQ (Alan Stern) in February-March 2008; selection of final targets by ~April 2008. - Phase 2s for final targets to STScI PIT by 15 May 2008. I-band DSS image from 1989 (blue) and J-band 2MASS image from 1999 (red). Motion object is marked. ACS EROs from SM3B.

14 26 Oct. 2007COS Science Team Meeting14 ERO: Who’s Involved Instrument-specific teams: WFC3 SOC, COS IDT, ACS,STIS,NICMOS Instrument Science Teams + community consultation GSFC: Leckrone, Niedner HQ: Stern, Morse, Mather, Hayes WFPC2 ERO from SM1. STScI: Noll, Reid, Sembach, Biagetti,Mountain OPO: Livio, Villard, Gundy, Estacion, Levay, Frattare

15 26 Oct. 2007COS Science Team Meeting15 ERO: Schedule Presentation to HQ: ~ February 2008 (TBD) Execution on Spacecraft ( all dates approximate, assume early Aug launch ): Instrument dependent ~mid September~early October, possibly later for COS ERO Press release: ~ mid-late October 2008 (TBD) Avoid US presidential election news cycle! May need a later one for COS (TBD) AAS Long Beach, CA 7-10 January 2009 Pasadena, CA 7-11 June 2009 IAU General Assembly Rio de Janeiro, Brazil 3-14 August 2009 International Year of Astronomy 2009 WFPC2 ERO from SM3A.

16 26 Oct. 2007COS Science Team Meeting16 SMOV Office Space STScI has begun discussion of office space needs with COS IDT and WFC3 IPT –Initial plan is to be able to accommodate up to 4 short term visitors and 1 long term visitor in the post-SM4 period –Duration and timing of visits will depend on final schedule of SMOV activities –Visitors will assist in SMOV analyses and work closely with Institute instrument teams –No present plans to host ACS or STIS visitors, but this can be revisited (or even accommodated in current plan) if the need arises Office space for external visitors will be worked into master office space plan for the coming year

17 26 Oct. 2007COS Science Team Meeting17 SMOV OPERATIONS SMOV Ops begins at Release (Aug. 15, 2008) Daily SMOV Status & Planning Meetings –“Morning Meeting” –Reps from all SI/Subsystems, STScI P&S, STScI & Project Ops Some operations require realtime support from STScI/EDT team –To be discussed During ops-related meetings next year Reviewed at STScI Readiness Review next July SMOV Closure Review