Presentation is loading. Please wait.

Presentation is loading. Please wait.

Material Requirements Planning (MRP)

Similar presentations


Presentation on theme: "Material Requirements Planning (MRP)"— Presentation transcript:

1 Material Requirements Planning (MRP)
and ERP 14 PowerPoint presentation to accompany Heizer and Render Operations Management, Eleventh Edition Principles of Operations Management, Ninth Edition PowerPoint slides by Jeff Heyl © 2014 Pearson Education, Inc.

2 Outline Dependent Demand Dependent Inventory Model Requirements
MRP Structure Lot Size Techniques

3 Depend demand

4 Dependent Demand The demand for one item is related to the demand for another item Given a quantity for the end item, the demand for all parts and components can be calculated In general, used whenever a schedule can be established for an item MRP is the common technique

5 Independent demand is uncertain. Dependent demand is certain.
EOQ Independent Demand (final product) Product A Part B(4) Part C(2) Material D(2) Material E(1) Material D(3) Material F(2) Dependent Demand (Components) MRP Independent demand is uncertain. Dependent demand is certain.

6 Dependent inventory model requirements
MPS BOM Inventory Availability Phase Orders Outstanding Lead time

7 Dependent Inventory Model Requirements
Effective use of dependent demand inventory models requires the following Master production schedule (MPS) Specifications or bill of material (BOM) Inventory availability Purchase orders outstanding Lead times

8 Master Production Schedule (MPS)
Specifies what is to be made and when, not a forecast of demand MPS is established in terms of specific products The MPS is quite often fixed or frozen in the near term part of the plan TABLE 14.1 Master Production Schedule for Chef John’s Buffalo Chicken Mac & Cheese GROSS REQUIREMENTS FOR CHEF JOHN’S BUFFALO MAC & CHEESE Day 6 7 8 9 10 11 12 13 14 And so on Quantity 450 200 350 525 235 375

9 Bills of Material (BOM)
List of components, ingredients, and materials needed to make product Provides product structure Items above given level are called parents Items below given level are called components or children

10 BOM Example Question: If we want to produce 50 chairs, how many back supports do we need?

11 BOM Example Question: If we want to produce 50 chairs, how many cross bars do we need?

12 Accurate Inventory Records
Accurate inventory records are absolutely required for MRP Generally MRP systems require more than 99% accuracy

13 Accurate Inventory Records
Product A B (2) C (3) D (2) E D (4) F G (3) D Question: If we want to produce 10 A, how many D do we need?

14 Product A B (2) C (3) Question: we want to produce 10 A,
F G (3) D Question: we want to produce 10 A, Inventory of B is 3, Inventory of F is 10, how many D do we need?

15 Purchase Orders Outstanding
What is on order Outstanding purchase orders must accurately reflect quantities and scheduled receipts

16 Lead Times for Components
The time required to purchase, produce, or assemble an item For production – the sum of the move, setup, and assembly or run times For purchased items – the time between the recognition of a need and when its available for production

17 Must have D and E completed here so production can begin on B
Lead Time Product A B C D E(2) E(3) F G Must have D and E completed here so production can begin on B Start production of D | | | | | | | | Time in weeks 2 weeks 1 week D E 1 week 2 weeks to produce B C E 1 week A F 2 weeks 3 weeks 2 weeks D G 1 week

18 Lead Time Cumulative Lead Time: the longest lead time path in the BOM
1 week (A) + 2 weeks (B) + 3 weeks (F) = 6 weeks 1 week (A) + 1 weeks (C) = 2 weeks 1 week (A) + 3 weeks (D) + 2 weeks (E) = 6 weeks So, cumulative lead time is 6 weeks.

19 Discussion Question What is the cumulative lead time?

20 MPS structure

21 MRP Structure Figure 14.4 Data Files Output Reports BOM Master
Purchasing data BOM Lead times (Item master file) Inventory data Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reports Order early or late or not needed Order quantity too small or too large Master production schedule Material requirement planning programs (computer and software)

22 MRP Structure

23 MRP Structure Gross Requirements: total amount of an item that is required Net Requirements: amount needed in a time period Planned Order Receipt: amount of an item planned to arrive in a time period Planned Order Release: amount of an item planned to be ordered in time period Net Requirements = Gross _ Scheduled Receipts Available Inventory

24 Lot sizing techniques Lot-for-Lot EOQ

25 Lot-Sizing Techniques
Lot-sizing decision: how much to order Techniques to determine lot sizes Lot-for-lot techniques Economic order quantity (EOQ)

26 Lot-sizing Techniques
Process all BOM items level by level following a top-down approach. For each item at each level, compute the gross requirement for each period calculate the net requirement for each time period apply a lot-sizing technique to determine the order quantities offset each order for the lead time to yield a time-phased planned order release (POR). Net Requirements = Gross _ Scheduled Receipts Available Inventory

27 Lot-Sizing Techniques
Lot-for-lot techniques order just what is required for production based on net requirements May not always be feasible If setup costs are high, lot-for-lot can be expensive When frequent orders are economical and just-in-time (JIT) inventory techniques implemented, Lot-for-Lot can be very efficient

28 Lot-for-Lot (L4L) Example 14.1: Use L4L to fill out the following MRP table Item: X 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases (LT = 1 week) 35 30 40 10 40 30 30 55 30 40 10 55 30 40 10 55

29 Lot-for-Lot (L4L) Example 14.2: Use L4L to fill out the following MRP table Item: X 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts 90 Projected on hand Net requirements Planned order receipts Planned order releases (LT = 1 week) 35 50 50 40 30 20 30 55 30 20 55 30 20 55

30 Lot-for-Lot (L4L) Example 14.3:
Children's scissors are made from four items: two identical blades – two weeks lead time one screw – one week lead time one nut – one week lead time The assembly process for one gross of scissors takes one week. (1) Construct a product structure tree for the scissors. Screw Nut Blade(2) Level 1 Scissors Level 0

31 A order of 144 scissors in week 7
No inventory on hand Level 0 – Scissors: lead time (LT) = 1 week 1 2 3 4 5 6 7 8 9 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 144 432 144 432 144 432 144 432

32 Planned order release: 144 scissors @ week 6
Check the table for Scissor Same as the row “Planned order release” of the upper level table Level 1 – Blade: lead time (LT) = 2 weeks 1 2 3 4 5 6 7 8 9 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 288 864 72 360 – 288 = 72 360 792 864 – 72 = 792 360 360 360 360 360 72 Project on hand > Requirements, So, Net requirements =0 792 792

33 Planned order release: 144 scissors @ week 6
Check the table for Scissor Same as the row “Planned order release” of the upper level table Level 1 – Screw: lead time (LT) = 1 week 1 2 3 4 5 6 7 8 9 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 144 432 Project on hand > Requirements, So, Net requirements =0 600 600 600 600 600 600 456 600 – 144 = 456 456 456 – 432 = 24 24

34 Planned order release: 144 scissors @ week 6
Check the table for Scissor Level 1 – Nut: lead time (LT) = 1 week 1 2 3 4 5 6 7 8 9 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 144 432 100 100 100 100 100 100 44 432 44 432 44 432

35 EX 1 in class Inventory Availability Master Schedule Bill of Materials
Item Quantity in Inv. A 80 B 45 C 105 D E 650 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 Quantity 125 150 175 Develop the MRP tables for each items by using L4L rule. Bill of Materials LEVEL PART # ITEM QUANTITY LEAD TIME 11001 A 1 4 weeks 21001 B 3 weeks 21002 C 2 2 week 31001 D 1 week 31002 E

36 Lot-Sizing Techniques
Lot-sizing decision: how much to order Economic order quantity (EOQ) EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand

37 Economic Order Quantity (EOQ)
Example 14.4: Use EOQ=73 to fill out the following MRP table 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 43 73 – 30 = 43 3 43 – 40 = 3 26 66 – 40 =26 3 66 73 – 7 = 66 69 69 39 30 7 4 30 – 26 = 4 16 73 Net requirement in 2nd week is not zero, so, a planned order should be receipted. 73 73 73 73

38 EX 2 in class Develop the following MRP table by using EOQ = 57.
Beginning inventory = 40. Lead time = 1 week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 30 40 70 20 80 50 Scheduled receipts Projected on-hand Net requirements Planned order receipts planned order release

39 Example 14.5 Construct a product tree diagram and develop a material requirements plan (MRP) that will yield 400 units of product P at the start of week 7 Item Parent Quantity for 1 of Parent Currently On-Hand Scheduled Rcpt (in wk) Lead Time Order Quantity P - 1 lot-for-lot A 100 B Multiples of 450 C A,B 1,2 90 100 (wk 2) 2 Multiples of 600 D 50 80 (wk 2) P A (1) B (1) C (1) C (2) D (2) Level 0 Level 1 Level 2 Item P 1 2 3 4 5 6 7 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 400 400 400 400

40 Item Parent Quantity for 1 of Parent Currently On-Hand Scheduled Rcpt (in wk) Lead Time Order Quantity P - 1 lot-for-lot A 100 B Multiple of 450 C A,B 1,2 90 100 (wk 2) 2 Multiples of 600 D 50 80 (wk 2) P A (1) B (1) C (1) C (2) D (2) Level 0 Level 1 Level 2 Item A 1 2 3 4 5 6 7 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 400 100 100 100 100 100 100 300 300 300

41 Item B 400 50 400 450 450 1 2 3 4 5 6 7 Gross requirements
Parent Quantity for 1 of Parent Currently On-Hand Scheduled Rcpt (in wk) Lead Time Order Quantity P - 1 lot-for-lot A 100 B Multiples of 450 C A,B 1,2 90 100 (wk 2) 2 Multiples of 600 D 50 80 (wk 2) P A (1) B (1) C (1) C (2) D (2) Level 0 Level 1 Level 2 Item B 1 2 3 4 5 6 7 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 400 50 400 450 450

42 From the last row of table for item A: 300 @ week 5
Parent Quantity for 1 of Parent Currently On-Hand Scheduled Rcpt (in wk) Lead Time Order Quantity P - 1 lot-for-lot A 100 B Multiples of 450 C A,B 1,2 90 100 (wk 2) 2 Multiples of 600 D 50 80 (wk 2) P A (1) B (1) C (1) C (2) D (2) Level 0 Level 1 Level 2 From the last row of table for item A: week 5 From the last row of table for item B: 450*2 = week 5 450*2+300 = 1200 Item C 1 2 3 4 5 6 7 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 1200 100 90 90 190 190 190 190 1010 1200 1200 Since 1010 > 600, Planned order receipt = 600*2 = 1200

43 Item Parent Quantity for 1 of Parent Currently On-Hand Scheduled Rcpt (in wk) Lead Time Order Quantity P - 1 lot-for-lot A 100 B Multiples of 450 C A,B 1,2 90 100 (wk 2) 2 Multiples of 600 D 50 80 (wk 2) P A (1) B (1) C (1) C (2) D (2) Level 0 Level 1 Level 2 450*2 = 900 Item D 1 2 3 4 5 6 7 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 900 80 50 50 130 130 130 770 770 770

44 EX3 in class Develop a material requirements plan for end item P and its components. One hundred units of P are needed at the start of each of weeks 4 and 8 Item Lead Time Quantity on Hand Scheduled Receipts Order Quantity P 1 20 Lot-for-lot A 100 B C D F 200 week 1 400

45 Example 14.6 Develop a MRP for Item C by using L4L technique Item A
Inventory Availability Develop a MRP for Item C by using L4L technique Item On Hand Inventory Scheduled Receipts Lead Time A 100 week 2) 1 B 100 2 C 50 150 3) H J K 50 week 2) A H Master Schedule B C(2) J K(2) C Period 8 9 10 11 12 A 100 50 150 H C(2) 1st final product See “Master Schedule” See “Scheduled Receipts” Item A 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 100 50 150 100 100 100 100 100 100 100 50 150 50 150 50 150

46 Inventory Availability
H Item On Hand Inventory Scheduled Receipts Lead Time A 100 WK 2) 1 B 100 2 C 50 150 H J K 50 WK 2) B C(2) J K(2) C C(2) Master Schedule Period 8 9 10 11 12 A 100 50 150 H 2nd final product See “Master Schedule” Item H 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 100 50 100 50 100 50 100 50

47 Inventory Availability
H Item On Hand Inventory Scheduled Receipts Lead Time A 100 week 2) 1 B 100 2 C 50 150 3) H J K 50 week 2) B C(2) J K(2) C C(2) Master Schedule Period 8 9 10 11 12 A 100 50 150 H See “Planned order release” in upper level item “H” & Quantity relationship = 1:2 See “Inventory Availability” Item K 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 200 100 50 100 100 150 150 150 150 150 150 50 100 50 100 50 100

48 Inventory Availability
H Item On Hand Inventory Scheduled Receipts Lead Time A 100 wk 2) 1 B 100 2 C 50 150 3) H J K 50 wk 2) B C(2) J K(2) C C(2) Path A – C (2): see last row of Item “A” 50*2 = Week 9 150*2 = Week 11 Path H – K(2) – C(2 ): see last row of Item “K” 50*2 = Week 6 100*2 = Week 8 Master Schedule Period 8 9 10 11 12 A 100 50 150 H Path H – C: see last row of Item “H” Week 8 Week 10 See “Inventory Availability” Item C 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Schedule receipts Projected on hand Net requirements Planned order receipt Planned order release 100 100 50 300 150 50 50 50 200 200 200 100 100 200 100 50 300 200 100 50 300 200 100 50 300

49 EX 4 in class Construct a material requirements plan which will result in 100 units of P1 at week 6, and 200 units of P2 at week 8 P1 P2 A B(2) A(2) B C(3) C(4) C(3) C(4) Item Lead Time Quantity on Hand Scheduled Receipts Order Quantity P1 1 L4L P2 A 70 500 B 3 50 250 C 2 1000 WK 2 2000

50 Lot-Sizing Summary In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change Lot-for-lot should be used when low-cost setups can be achieved When setup costs are significant and demand is reasonably smooth, EOQ should give reasonable results Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM


Download ppt "Material Requirements Planning (MRP)"

Similar presentations


Ads by Google