1 WECC TEPPC Meeting SWAT Update
Western Electricity Coordinating Council Transmission Expansion Planning Policy Committee WECC TEPPC Meeting SWAT Update Robert Kondziolka Salt River Project March 25, 2010 Salt Lake City, Utah TEPPC SWAT Summary - R. Kondziolka

2 SWAT Footprint One of the WestConnect Sub-Regional Planning Groups
SWAT Footprint One of the WestConnect Sub-Regional Planning Groups SWAT Southwest Area Transmission TEPPC SWAT Summary - R. Kondziolka

3 Transmission Projects in WECC Regional Planning, Path Rating Process, or Development
Chinook Zephyr TransWest Express SWIP High Plain Express Pinal West to Pinal Central Pinal Central to Browning Pinal Central to Tortolita Morgan to Pinnacle Peak Palo Verde to Sun Valley Sun Valley to Morgan SPPR Navajo Transmission Project Segment 1 Palo Verde–Devers II California Portion Tres Amigas Santa Fe Palo Verde-North Gila II SunZia South Line TEPPC SWAT Summary - R. Kondziolka

4 EHV Transmission Upgrades In Development
Nevada 2009 625MW Energized To Intermountain Utah To Celilo Harry Allen Crystal California Marketplace Mead McCullough Navajo 2009 625MW Energized Eldorado 2010 600MW Four To Midway Corners Mohave Yavapai Adelanto Moenkopi Victorville Sylmar Vincent Peacock Lugo Cholla Rinaldi Toluca Mira Loma Arizona Coronado Serrano Devers 2010 400MW Energized Valley Perkins Westwing DPV2 Project Palo Verde Rudd Miguel Imperial Valley Harquahala Liberty North Gila Kyrene Silver Jojoba King Saguaro +/- 500 kV DC line 500 kV line 345 kV line Major Substation Major Power Plants 500kV Line Upgrade TEPPC SWAT Summary - R. Kondziolka

5 Status of Major New Transmission Projects
Project Name Voltage Capacity Proposed In-Service Sponsor Status Pinal Central to Browning 500kV 1400MW nd Qtr SRP In Construction Pinal West to Pinal Central nd Qtr In Design & ROW Acquisition Palo Verde to Sun Valley 650MW APS Sun Valley to Morgan 1200MW nd Qtr Morgan to Pinnacle Peak 1000MW 2010 – 4th Qtr Arizona Gateway South (Double Circuit) 345kV 2000MW 2014 TEP In Perpetual Federal Permitting Navajo Transmission Project 1500MW 2012 DPA In Path Rating Study Process Palo Verde to North Gila II 1250MW Palo Verde to Devers II (California Only) 2012 – 4th Qtr SCE In Siting & Permitting TransWest Express (Bi-Pole DC) 600kV 3000MW 2015 Anschutz In Siting & Permitting & Path Rating Chinook and Zephyr (Bi-Pole DC) 6000MW TransCan Pinal Central to Tortolita ON-Line … Consolidated into SWIP th Qtr NVEnergy SWIP – Southwest Intertie Project (South) Phase I 2012 LS Power Project kV MW 20XX ID I SunZia Southwest Trans Project (2 Circuits) SW Power In Path Rating Process & Permitting High Plains Express Initiative (2 Circuits) 3500MW 2017+ Xcel Feasibility Studies TEPPC SWAT Summary - R. Kondziolka

6 Western Area Power Administration Transmission Infrastructure Program
Sonoran-Mohave Renewable Transmission (SMRT) Project A—Palo Verde-North Gila 500-kV, 100 miles B—Palo Verde-Blythe 500-kV, 110 miles C—North of Parker Potential double circuit, /500-kV, 190 miles C—South of Parker Potential double circuit, 230/500-kV, 330 miles D−Imperial Valley Potential 500-kV network addition to the Southern California grid in Imperial County, California, miles TBD TEPPC SWAT Summary - R. Kondziolka

7 SWAT Summary - R. Kondziolka
SWAT 2010 Progress CRT Subcommittee RMR Studies for Yuma and Mohave counties Yuma 230kV Ring and Western TIP SMRT SATS Subcommittee 2009 study work approved and filed Alternative evaluation and VAR Margin study Short Circuit Work Group Expanding area to include southern California Retained consultant for CAPE, ASPEN, PSS/E NM Subcommittee Wind collector and integration system, include pass through SWAT Renewable Transmission Task Force Coordination with TEPPC studies TEPPC SWAT Summary - R. Kondziolka

8 SWAT Summary - R. Kondziolka
SWAT 2010 Progress CATS Subcommittee Development of WestConnect Base Cases Joint MOD-029 Studies Transmission Corridor Planning Committee WGA Roadmap/Primer for Transmission Development BLM Arizona Restoration Design Energy Projects Western’s Transmission Infrastructure Program (SMRT) Arizona Corporation Commission Biennial Transmission Assessment 4th Qtr Utilities filed reports identifying top 3 renewable transmission projects and workshop to address filings Initiating 6th BTA TEPPC SWAT Summary - R. Kondziolka

9 Arizona Renewable Generation Interconnection Requests
250MW 500MW 250MW 500MW 500MW 500MW APS Solar Wind SRP TEP WAPA CAISO Interconnection Queue Listing As of 2/8/10 340MW 260MW 8102MW 200MW 1000MW 100MW 3244MW 600MW 500MW 390MW 300MW 500MW 200MW 150MW 700MW 2095MW 150MW 300MW 50MW 18.9MW 800MW 1400MW 110MW 50MW 400MW 50MW 900MW 125MW 150MW 700MW 300MW 125MW 700MW 2950MW 180MW 250MW 700MW 20MW 180MW 100MW 700MW 20MW 180MW 125MW 70MW 150MW 20MW 1275MW 180MW 125MW 125MW 1600MW 80MW 297MW 500MW 500MW 99MW 400MW 480MW 250MW 2000MW 99MW 150MW 10MW 150MW 40MW 20MW 600MW 280MW 750MW 300MW 87MW 20MW 45MW 290MW 480MW 200MW 20MW 20MW TEPPC SWAT Summary - R. Kondziolka 960MW 20MW 5MW 20MW

10 SWAT Summary - R. Kondziolka
TEPPC SWAT Summary - R. Kondziolka

11 SWAT Summary - R. Kondziolka
TEPPC SWAT Summary - R. Kondziolka

12 SWAT Summary - R. Kondziolka
TEPPC SWAT Summary - R. Kondziolka

13 SWAT Summary - R. Kondziolka
TEPPC SWAT Summary - R. Kondziolka

14 SWAT Summary - R. Kondziolka
Morgan 500/230kV Substation TEPPC SWAT Summary - R. Kondziolka

15 SWAT Summary - R. Kondziolka
Morgan 500/230kV Substation TEPPC SWAT Summary - R. Kondziolka

16 Morgan to Pinnacle Peak 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

17 Pinnacle Peak 500/230kV Substation
TEPPC SWAT Summary - R. Kondziolka

18 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

19 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

20 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

21 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

22 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

23 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

24 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

25 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

26 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

27 Pinal Central to Abel to Browning 500/230kV Transmission Line
TEPPC SWAT Summary - R. Kondziolka

28 Western Electricity Coordinating Council
Transmission Expansion Planning Policy Committee Questions? Details Contact Information Robert E. Kondziolka (602) TEPPC SWAT Summary - R. Kondziolka


Download ppt "WECC TEPPC Meeting SWAT Update"

Similar presentations


Ads by Google