Planning Processes/Permits “From Pre-application meeting to Board of Aldermen Approval.” “From Pre-application meeting to Board of Aldermen Approval.”

Similar presentations


Presentation on theme: "Planning Processes/Permits “From Pre-application meeting to Board of Aldermen Approval.” “From Pre-application meeting to Board of Aldermen Approval.”"— Presentation transcript:

1 Planning Processes/Permits “From Pre-application meeting to Board of Aldermen Approval.” “From Pre-application meeting to Board of Aldermen Approval.” But First,…… the ground work, 2007

2  Planning: A policy guide to development and land use within an area in relation to a long- range development plan  Zoning: Local law controlling use, building density and location and other development features  Subdivision: Local law governing the partitioning and development of land

3  Zoning and land use regulations must be adopted “in accordance with a comprehensive plan” §89.040 RSMo.  Consistent guide for development vs. ad-hoc “quickie” decisions  Opportunity to take stock of community preferences and set directions accordingly  Because just Zoning is not planning

4  Types of processes:  * Rezoning  * Conditional use permits  * Site Plans  * Preliminary Plats  * Record Plats  * Planned Developments  “All review and packet assembly processes accomplished in a 30 day window ”

5 Pre-Application Meeting Procedure: Applicant schedules Pre-app with City Planner; › Highlight ordinances & stipulations/access regulations › Address potential issues › Discuss potential solutions to technical, design & environmental review issues › Provide direction about process, i.e. submittal requirements, appropriate sequences of required plan review & processes › Assist in preparing plan which meets goals & objectives of Comprehensive Plan * Process for City Planner to add their application to a future agenda as applicable ; City Code §§ 405.073, Then what happens?

6 Public notice advertisement accomplished for Rezoning/CUP/Major plan amendments * (Published 15 days prior to scheduled Hearing per State/Local Ord.) (Public Hearing held at both the PZ and BOA levels/agenda’s) (Notification letters sent for 300 feet radius to all land owners and placed in newspaper); Notify and accept comments from Agency review authority’s (school district, Fire District, Modot, utility company’s); * Staff review and comment via Planning; engineering; building: administration (Comment Ltr sent ) Letter generated approximately 5-8 days after receipt of petition Revisions are required to address comments Comments related to Land Use and Subdivision regulations, Pre-app. Meeting discussion, special studies

7  Applicant provides revised documents: › Revisions re-reviewed by staff related to staff comments; › Results of process reported to the Commission/Board in Staff Recommendation. › Documents submitted by staff and packet generated in Minute Trac for Board and Commission

8  Planning Commission meeting held; › Commission makes a recommendation on agenda items to the BOA › Staff creates Board summary and amends MT documents as applicable › The “Action” and “reasoning” are forwarded to Board of Aldermen with Plan Action of Commission: › Approve › Deny › Approve with Conditions › Postponement

9 Board of Aldermen Meeting Held; › Board receives recommendation from Planning Commission; › Public hearing held for Rezoning/CUP/Major Plan amendments *Action of Board: › Approve › Deny › Approve with Conditions › Postponement

10  Effect of Approval/Denial › Approval  Applicant can receive building permits after Engineering Department review (staff review processes)  Denial › Applicant can resubmit the request with changes in response to reasons for denial