Presentation is loading. Please wait.

Presentation is loading. Please wait.

Taylor Pavilion Design Review 2015. Pavilion Design Review Committee 2015 June 3, 2015 Belmar Mayor & Council form an advisory committee to review the.

Similar presentations


Presentation on theme: "Taylor Pavilion Design Review 2015. Pavilion Design Review Committee 2015 June 3, 2015 Belmar Mayor & Council form an advisory committee to review the."— Presentation transcript:

1 Taylor Pavilion Design Review 2015

2 Pavilion Design Review Committee 2015 June 3, 2015 Belmar Mayor & Council form an advisory committee to review the design of Taylor Pavilion for the express purpose of identifying areas where adjustments could be made to save costs of construction while not requiring significant redesign expenses. The committee met throughout the summer and arrived at the following presentation for Mayor & Council’s consideration.

3 Pavilion Design Review Committee 2015 Method of Review Building must stay within the existing footprint due to DEP & FEMA standards. Consideration of design alterations should maintain the integrity of the existing design purposes. Taylor Pavilion should remain as the replacement for what was destroyed. Any redesign recommendations must allow for the building to be permitted under NJDEP and remain inline with FEMA requirements so as not to jeopardize FEMA funding. Any redesign recommendations must survive a cost benefit analysis to ensure that savings exceed the cost of redesign. Carefully review designs to identify any changes from the destroyed structure and determine if those items can be eliminated or modified.

4 Pavilion Design Review Committee 2015 Review of Existing Design Taylor Pavilion Demolished by Sandy Rendering of New Taylor Pavilion Total Square footage - 7,000 SF Total Square Footage - 6,812 SF

5 Pavilion Design Review Committee 2015 Review of Existing Design Floor Plan of old Taylor Floor Plan of New Taylor Total Square footage - 7,000 SF Total Square Footage - 6,812 SF Concession SpaceBathrooms Beachfront OperationsKitchen & Storage General Space

6 Pavilion Design Review Committee 2015 Review of V-Zone Construction Standards Minimum Finished Floor Elevation (FFE) – Base Flood Elevation (BFE) +3’ results in FFE approximately 5 feet above the existing boardwalk. Open Foundation – Building must be pile supported with the lowest horizontal member above the BFE. All walls below the BFE must be breakaway. Impact loads – Must be able to survive impact from 1,000 lb object on critical members below the BFE. Wave loads – Every structural component below the BFE is subject to wave loading.

7 Pavilion Design Review Committee 2015 Review of Codes & Standard Requirements Building is an A-2/A-3 Mixed Use General Assembly building ADA access must be provided - ADA accessible ramps must be located at the main entrance Automatic Sprinkler System Bathrooms HVAC Requirements

8 Pavilion Design Review Committee 2015 Review of Taylor – Old V. New – What’s different? ItemWhy?Optional? Stronger Foundations*DEP V-Zone StandardsOnly if V-Zone is mitigated More BathroomsCodes & StandardsNo HVACCodes & StandardsNo Dedicated Beachfront Operations Space & SecuredRectifying Flaw of Old DesignYes Columns RemovedRectifying Flaw of Old DesignYes ( Columns limited general space usage.) Hallway AddedRectifying Flaw of Old DesignYes (Old design muddled beachfront operations and general usage.) *Redesign costs estimated at $25,000. Benefit of redesign would need to save more than $25,000 to be considered.

9 Pavilion Design Review Committee 2015 Design Consideration Alternate Foundation System The cost of the foundation is one of the largest components of the total project costs. Is a “cheaper” foundation possible? Alternatives must meet V-Zone requirements, current building codes, and any other structural requirements. The V-Zone requirements are the most difficult to design for. Must be able to withstand impact force of floating debris or have redundancy built in. Alternatives must be potentially permitted by DEP.

10 Pavilion Design Review Committee 2015 Design Consideration: Alternate Foundation System Option #1 - Take the building out of the V-Zone Build a steel sea wall and back fill to remove footprint from the V-Zone Build a traditional timber piling foundation. Concerns: Cost of sea wall Filling of beach may not be permitted by NJDEP

11 Pavilion Design Review Committee 2015 Design Consideration: Alternate Foundation System Costs Option #1 - Remove from V-Zone Cost $275k more than designed foundation + $25,000 in redesign = $300,000 Increase to Existing Design ItemUnit PriceUnitQuantityTotal Steel Bulkhead$1,400LF325$455,000 Fill$30.00CY5305$159,150 Piles$46.97LF3160$148,425 Timber Framing & Floor$7.51SF6812$51,158 $813,733

12 Pavilion Design Review Committee 2015 Design Consideration: Alternate Foundation System Option #2 – Leave in the V-Zone but Use a timber piling foundation (traditionally cheaper than steel and concrete) Impact loads in V-Zone requires redundancy of pilings; the structure must be designed for a damaged piling. Timber framing would be used for the foundation instead of concrete Concerns: Reduced service life and structural integrity compared to steel piles and concrete foundation Code standards require that more than double the number of piles would be needed if timber is used.

13 Pavilion Design Review Committee 2015 Design Consideration: Alternate Foundation System Costs Option #2 – Timber Piling Cost $158k more than designed foundation + $25,000 in redesign = $183,000 Increase to Existing Design ItemUnit PriceUnitQuantityTotal Piles$46.97LF12640$593,700.80 Timber Framing & Floor$15.02SF6821$102,451.42 $696,152.22

14 Pavilion Design Review Committee 2015 Design Consideration: Exhaust other “Reductions” Option #3 – Reduce Bathrooms:Not Permitted by Codes & Standards Remove HVAC:Not Permitted by Codes & Standards Return Beachfront Operations to Prior Would reintroduce flaw of old design. ConfigurationPotential savings is nominal and would not survive CBA. Put Columns Back In:Would reintroduce flaw of old design. Would add to the cost to put columns in where none are now. Would not survive CBA. Remove Hallway:Would reintroduce flaw of old design. Potential savings is nominal and would not survive CBA.

15 Pavilion Design Review Committee 2015 Committee Recommendation The Taylor Pavilion as designed adheres to codes and standards for V-Zone construction and is by far the most cost effective replacement of what was lost in Hurricane Sandy.

16 Taylor Pavilion Design Review 2015


Download ppt "Taylor Pavilion Design Review 2015. Pavilion Design Review Committee 2015 June 3, 2015 Belmar Mayor & Council form an advisory committee to review the."

Similar presentations


Ads by Google