1 Sample Management Office
UCOR Oak Ridge Sample Management Office 2014 Site Status Report Presented by Phil Clark X

2 UCOR Scope of Work on the Oak Ridge Reservation

3 UCOR Scope of Work Perform D&D and remediation activities across the Oak Ridge Reservation (ORR) Manage the ORR Landfill and the Environmental Management Waste Management Facility (EMWMF) Manage the Water Resource Recovery Program (WRRP) Perform Environmental Compliance Monitoring Waste management and disposition Pre-Design Study for the Mercury Treatment Facility at Y-12

4 D&D Activities at ETTP Current ETTP D&D Activities K-25 Slab
K-27 (Entire Facility) K-31 (Entire Facility) Planned Activities Poplar Creek Facilities K-1037 Facility Centrifuge Facilities Central Neutralization Facility Toxic Substances Control Act (TSCA) Incinerator Balance of Facilities D & D Completed Property Transfer In Process .

5 D&D Sampling and Analysis
Analytical support for characterization of facility contents and construction debris K-25 slab, K-27, and K-31 are currently underway Other facilities are expected to be shifted to scope as these are completed 3000 analyses performed in FY14 Total cost for analytical services ~$600K

6 Landfill Operations Environmental Management Waste Management Facility (EMWMF) CERCLA waste associated with the ORR Must meet WAC requirements Oak Ridge Reservation (ORR) Landfill – (formerly the Y-12 Sanitary Landfill) Disposal of sanitary, industrial, construction, and demolition waste

7 EMWMF and ORR Landfill Sampling and Analysis
Sample Locations Monitoring wells Contact Water Leachate Air Sampling Number of analyses per year is relatively constant Weekly, Quarterly, Semi-annual, Rainfall event driven (EMWMF) Dynamic analytical suite for the EMWMF 8000 analyses performed in FY14 Total cost for analytical services $1.2M

8 Water Quality and Environmental Compliance

9 Water Quality and Environmental Compliance Sampling and Analysis
Samples Groundwater Surface Water Outfalls Runoff Air Monitoring Annual sampling for Water Quality is relatively constant Environmental Compliance varies some, but overall is constant 21,000 analyses performed in FY14 Total cost for analytical services $1.4M

10 Waste Management and Disposition
UCOR has taken a proactive and aggressive approach to waste management Waste is characterized and shipped as it is generated The majority of legacy waste has been dispositioned 1400 analyses performed on waste materials in FY14 Total cost for analytical services $175K

11 Y-12 Outfall 200 Treatability Study and Conceptual Design
Outfall 200 at right; Flow Augmentation at left

12 Mercury Treatment Facility at Outfall 200
UCOR has performed treatability studies in support of the conceptual design report. Pre-design studies are now underway. Anticipated construction beginning in 2017 Operations starting in 2020. The proposed facility can treat 1,500 gallons of water per minute. The treatment facility will be NPDES permitted

13 Site Remediation Expected increase in soil samples from the ETTP site
Driven by the Zone 1 and Zone 2 Records of Decision (RODs) Some will be associated with land transfers and footprint reduction Will require very low reporting levels in some cases depending on final disposition of parcel ~$10K spent on remediation in FY 2014

14 Bioassay and Industrial Hygiene
Bioassay Program 2500 analyses $250K Will see a decrease in FT 2015 due to changes in program requirements Industrial Hygiene Program 2600 analyses $225K Expected to remain relatively constant through 2015

15 DOECAP Laboratories ALS Laboratory Group, Cincinnati, OH
ALS Laboratory Group, Fort Collins, CO ALS Laboratory Group, Salt Lake City, UT ARS International, Inc., Port Allen, LA Brooks Rand, Seattle, WA CNS Y-12 Analytical Chemistry Organization, Oak Ridge, TN Eberline Services, Oak Ridge, TN GEL Laboratories LLC, Charleston, SC Materials and Chemistry Laboratory, Inc., Oak Ridge, TN Oak Ridge Institute for Science and Education, Oak Ridge, TN Southwest Research Institute, San Antonio, TX TestAmerica Missouri, St. Louis, MO TestAmerica Tennessee, Knoxville, TN

16 Specialty Laboratories
Assured Bio Labs, LLC, Oak Ridge, TN BCS Laboratories, Inc., Gainesville, FL CH2M Hill Applied Sciences Laboratory (ASL), Corvallis, OR Microbial Insights, Inc., Knoxville, TN Microseeps, Inc., Pittsburgh, PA Shaw Environmental Inc. (a CB&I Company), Knoxville, TN

17 Analytical Support Summary
Analytical laboratories performed over 38,000 analyses in support of UCOR projects in FY 2014 The total cost for analytical services in FY 2014 was ~$4M FY 2015 analytical support is expected to remain largely unchanged New D&D characterization projects are expected to be added to the current scope as K-27 and K-31 are completed Landfill, Water Quality, and Environmental Compliance Program needs are expected to remain constant Analytical needs for waste characterization associated with the Waste Disposition Program are expected to decrease about 15-20% Bioassay requirements are expected to decline approximately 50% Industrial Hygiene sampling is expected to remain constant

18 TSDFs

19 UCOR TSDF Usage Diversified Scientific Services, Inc., Kingston, TN
EnergySolutions, LLC, Oak Ridge, TN EnergySolutions, LLC, Clive, UT Materials and Energy Corporation, Oak Ridge, TN Perma-Fix Environmental Services of Florida, Gainesville, FL Perma-Fix Northwest, Inc., Richland, WA Waste Control Specialists LLC, Andrews, TX TCI of Alabama Veolia Environmental Services (Port Arthur, TX; Tallahassee, FL, Port Washington, WI)

20 TSDF Summary FY 2014 Over $3.0M spent on waste Disposition FY 2015 $2.5M Projected FY 2016 $2.0M Projected

21 DOECAP Qualified Auditors
Laboratory 1 Team Lead 3 Contractor TSDF 1 Team Lead 2 Contractor

22 K-25 Retrospective The “U” was the first stage of the K-25 Plant. It came online in 1945.

23 K-25 Retrospective The K-25 building was 4 stories high and almost a half mile long. The building enclosed some 2 million square feet of space, making it the largest building in the world at the time. The final stages of the plant did not come on line until mid-August 1945. Maximum enrichment during the war was about 20%. The eventual cost of the K-25 complex would be over $500 million. Even though the plant was fully automated, 9,000 employees working in three shifts were needed to operate the plant.

24 K-25 Retrospective Because the uranium hexafluoride gas which was pumped through the building attacked grease, new pump seals had to be developed that were both gas tight and greaseless. The new seal material developed came to be known after the war as Teflon. In April 1945, a second gaseous diffusion plant, K-27, was started. It would come on line in January 1946 and make all of the other uranium separation processes obsolete. After the war additional gaseous diffusion buildings were built to increase production of enriched uranium (K-29, K-31, K-33). The original K-25/K-27 facility was shut down in 1964 after operating without error for 20 years. The rest of the gaseous diffusion plant was shut down in 1987.

25 K-25 Retrospective The final wall of the K-25 Facility comes down…

26 K-25 Retrospective UCOR completed demolition of the K-25 facility in June 2014 6 months ahead of schedule DOE realized a cost savings of ~$225M from the early completion Slab characterization is underway

27 Any Questions