Summary of the AWAKE Technical Board Meeting September 2014 – March 2015
2
Technical Board Meetings 5 th TB: 24 September 2014 (Greifswald) – Vacuum design status and issues, Plasma cell status, Proposal of TRIUMF contribution TRIUMF joins AWAKE Collaboration Issues for vacuum: vacuum specifications, vacuum separation window Start of discussions with plasma cell company (GRANT): e.g. clean plasma cell delivered in Feb 2015 2
3
Technical Board Meetings 6 th TB: 6 November 2014 – New vacuum separation window, impact on RP, impact on spectrometer, Layout of common proton and electron beam-line, plasma cell integration, planning Vacuum requirement specification decision on vacuum window: 0.2mm Al. Factor 20 lower background. No absorber downstream the window. Definition of plasma cell: 12m (10+2m), move plasma cell by 2m. integration of plasma cell and common proton and electron beam-line 3
4
Technical Board Meetings 7 th TB: 12 December 2014 – Vacuum simulation results, electron spectrometer magnet, proton beam line optics, updated layout of the AWAKE area, RF synchronization update, plasma cell alignment. HB4 magnet will be used as electron spectrometer streak camera optical line to be defined layout downstream the plasma cell first ideas on the plasma cell support 4
5
Technical Board Meetings 8 th TB: 12 February 2015 – Status of e-beam magnets, update on e-spectrometer, update on RF synchronization, plasma cell measurements, RP maps, planning Strategy for laser dump design/production/payment plasma cell support responsibilities defined Updated realistic planning for plasma cell: clean plasma cell delivered in July 2015. layout of RF signal generation and distribution for AWAKE electron line magnet design RF signal requirements Triumf magnets for electron line compressor design Electron spectrometer vacuum window Shielding for AWAKE experimental area BI planning 5
6
Technical Board Meetings 9 th TB: 11 March 2015 – CSR preparation, BTVs and light transmission, TRIUMF status, Update on integration, electron source performance, laser dump, Safety files Compressor design defined RF signal requirements TRIUMF: BPM design for 40mm completed, approved in February. 60mm design underway Cockcroft contributions to emittance diagnostics 80% of the descriptive part of the safety file is done demonstrative part by October 2015 Streak camera position to define e-spectrometer optical line, proton beam halo measurements. 6
7
Technical Board Meetings 5 th TB: 24 September 2014 (Greifswald) – Vacuum design status and issues, Plasma cell status, Proposal of TRIUMF contribution Issues for vacuum: vacuum specifications, vacuum separation window Start of discussions with plasma cell company (GRANT): e.g. clean plasma cell delivered in Feb 2015 TRIUMF joins AWAKE Collaboration 6 th TB: 6 November 2014 – New vacuum separation window, impact on RP, impact on spectrometer, Layout of common proton and electron beam-line, plasma cell integration, planning Vacuum requirement specification decision on vacuum window: 0.2mm Al. No absorber downstream the window. Definition of plasma cell: 12m (10+2m), move plasma cell by 2m. integration of plasma cell and common proton and electron beam-line 7 th TB: 12 December 2014 – Vacuum simulation results, electron spectrometer magnet, proton beam line optics, updated layout of the AWAKE area, RF synchronization update, plasma cell alignment. HB4 magnet will be used as electron spectrometer streak camera optical line to be defined layout downstream the plasma cell first ideas on the plasma cell support 8 th TB: 12 February 2015 – Status of e-beam magnets, update on e-spectrometer, update on RF synchronization, plasma cell measurements, RP maps, planning Strategy for laser dump design/production/payment plasma cell support responsibilities defined Updated realistic planning for plasma cell: clean plasma cell delivered in July 2015. layout of RF signal generation and distribution for AWAKE RF signal requirements Triumf magnets for electron line ompressor design Electron spectrometer vacuum window Shielding for AWAKE experimental area BI planning! 9 th TB: 11 March 2015 – CSR preparation, BTVs and light transmission, TRIUMF status, Update on integration, electron source performance, laser dump, Safety files Compressor design defined RF signal requirements TRIUMF: BPM design for 40mm completed, approved in February. 60mm design underway Cockcroft contributions to emittance diagnostics 80% of the descriptive part of the safety file is done demonstrative part by October 2015 Streak camera position to define e-spectrometer optical line, proton beam halo measurements. 7
8
AWAKE Technical Board Issues are well followed up Collaboration between the different work packages has strongly improved – Still room for more involvement Many iterative meetings in between the TB leads to conclusions in TB Minutes are an extremely useful tool to track actions and decisions. – Read them carefully! Planning is updated and available 8