Presentation is loading. Please wait.

Presentation is loading. Please wait.

LSST Electronics Review BNL January 25-26, 20121 LSST Electronics Review BNL January 25-26, 2012 Electronics Development Plan and Vertical Slice Test (VST)

Similar presentations


Presentation on theme: "LSST Electronics Review BNL January 25-26, 20121 LSST Electronics Review BNL January 25-26, 2012 Electronics Development Plan and Vertical Slice Test (VST)"— Presentation transcript:

1 LSST Electronics Review BNL January 25-26, 20121 LSST Electronics Review BNL January 25-26, 2012 Electronics Development Plan and Vertical Slice Test (VST) R. Van Berg Electronics Mini-Review January 26 th, 2012

2 LSST Electronics Review BNL January 25-26, 20122 Outline – Development Plan Chips –ASPIC –CABAC Boards –FEB (Front End Board) –Video and Bias Cables –BEB (Back End Board) –Backplane –RCM (Raft Control Module) Firmware Software Testing –Bench testing [………..ongoing………………………………………………………..] –VST Phase I [now to end of 2012] –VST Phase II [late 2012 through 2013] –VST Phase III [late 2013 – mid 2014] Raft Control Crate (RCC) On FEB

3 LSST Electronics Review BNL January 25-26, 20123 Chip Development Plans ASPIC –Now at ASPIC2 – bench testing very advanced, satisfies essentially all requirements but some small tweaks to go –ASPIC3 with slightly modified bias scheme, more gain options, a bypass option and serial configuration (SPI) to be submitted May 2012 – expect this to be the final object but bench tests and VST to verify that conjecture. CABAC –Initial submission of process test chip in November 2011, expect submission of a full, nominally complete, chip in April/May 2012 – followed by extensive bench tests (including thermal lifetime tests) and VST –Second submission (if needed) early 2013 Bottom Line – packaged ASPIC3 and CABAC1 chips should be available to test by about September 2012 so FEB4 to take them needs to be ready ~ Oct. and RCC system should be ready for the FEB4 by the same time

4 LSST Electronics Review BNL January 25-26, 20124 Board Development Plans FEB – driven by chip schedule – present FEB3 uses ASPIC2 and SCC, FEB will use ASPIC3 + CABAC1 (also needs to be in tune with contamination testing – might want FEB4 in several different materials). Intent is to be as “final” as possible (e.g. include connections for RSA heaters and sensors). –FEB4 ready for assembly + test ~ Sept 2012 when chips are ready –Video and Bias cables same as present version except somewhat longer (45 cm) and with mesh GND plane – pin counts stay unchanged, pin assignments largely unchanged BEB + Backplane + RCM + Firmware + Software – unified design driven by VST and FEB4 –Working system needed by ~ Sept. 2012 to allow testing of FEB4 (VST Phase II) Need to freeze overall design ~ May-June to allow time for board layout and firmware/software development Firmware and Software development can advance significantly, if not completely, prior to availability of FEB4 –Design input from requirements/desiderata lists plus findings of VST

5 LSST Electronics Review BNL January 25-26, 20125 Testing – Multiple Facets Electrical bench testing to verify individual elements. We need to know that sub- elements of the design work properly (or well enough) before we assemble them into larger structures –Custom chips extensively tested before they are put on “final” boards –COTS devices tested as appropriate (e.g. low voltage regulators for use on the FEB must work properly at -100C) Contamination testing –Devices and elements must satisfy contamination constraints in a fully independent program so far looking at small samples, but some phase II boards are planned to be part of larger scale contamination testing) Environmental testing –In addition to operating at reduced temperatures, need to know that there is no significant long term degradation of devices at the expected operating conditions either through electronic effects (e.g. “hot carriers”) or mechanical effects (e.g. cracks in solder joints from differential CTE stress) Full scale system tests – the Vertical Slice Test (VST)

6 LSST Electronics Review BNL January 25-26, 20126 Vertical Slice Test A “complete” front to back test of the focal plane electronics chain. –Phased to build from center out FEB-BEB-RCM now in Phase I SDS enters in Phase I (March 2012) CCD emulator in March 2012 CCS-like control enters soon after SDS CCD readout in March-May 2012 time frame TCM (or TCM mockup) enters at Phase II Power system enters at Phase II or Phase III –Phases defined by hardware generations Phase I is present hardware (FEB3, BEB-RCM 1) Phase II is next generation hardware (FEB4, BEB-RCM 2) Phase III is “final” generation hardware – pre-production versions Overall goal is to verify that we have met (or exceeded) the design requirements or, via this process, improve the design until we can meet those requirements Actual list of “tests” in each phase or sub-phase is quite extensive and, in general, must be repeated in each later phase – see detail in talks to follow

7 LSST Electronics Review BNL January 25-26, 20127 VST – Phase I Data from single ASPIC, multiple channels Multiple copies of boards, evolving firmware and software Three parallel efforts: –Harvard –Penn –Paris

8 LSST Electronics Review BNL January 25-26, 20128 VST – Phase I - Harvard Initial focus on firmware development and digital testing –Firmware to cover all basic functions ASPIC timing CCD clock timing Voltage setting Data readout Firmware to facilitate other testing Firmware to integrate CDS Documentation –Temporary software to use USB readout (until CDS is integrated) –Digital testing Data integrity Full speed data transfers (50 MHz DDR on 18 bit backplane bus) Secondary focus on preparation for CCD readout in concert with BNL –Dewar preparation Initially cold CCD, warm electronics Eventually cold CCD, cold FEB, warm back end

9 LSST Electronics Review BNL January 25-26, 20129 VST – Phase I - Penn Focus on analog performance tests and preparation for CCD readout –Noise Channel by channel Power supply feedthrough Current source feedthrough –Dynamic range Matching input to ADC, use all (well, almost all) 17 available bits –Crosstalk – spatial (e.g. left – right) –Crosstalk – temporal (e.g. large pulse memory) –Timing variations Reset and clamp timings Placement of ramp up/down wrt input pulse Settling time at ADC –Assemble pieces for CCD readout Cables Adapters ???? –Operate with CCD emulator

10 LSST Electronics Review BNL January 25-26, 201210 VST – Phase I - Paris Primary focus on ASPIC and CABAC bench tests –Mostly dedicated chip test fixtures and software tools –Cold ASPIC test boards –Dedicated ADC board (same ADCs, different form factor) Secondary focus on VST hardware comparison with bench test system(s) –One RCM, full pair of BEBs, one FEB (more possible) –Extensive collection of CCD characterization tools available for use either with bench or VST hardware

11 LSST Electronics Review BNL January 25-26, 201211 VST – Phase 1.5 CCD Emulator being developed by BNL –Image pattern stored on emulator –16 bit DAC resolution –Extracted via proper clock pattern from Geary 4 channel controller –A good way to get ready for the real challenge 

12 LSST Electronics Review BNL January 25-26, 201212 VST – Phase I.7 Attach to CCD and read an image –Either at Harvard or BNL – TBD –Initially all warm electronics –Secondarily, cold FEB (to get to expected noise performance by avoiding extra cabling from CCD through cryostat wall) Needs significant mechanical effort Needs some level of image software – maybe Phase 1.5 level sufficient

13 LSST Electronics Review BNL January 25-26, 201213 VST Phase II New chip set (ASPIC3, CABAC1) New FEB New backend (BEB, backplane, RCM) At some point in phase II add in a TCM mockup Repeat all Phase I analog tests and digital tests –Need appropriate firmware –Need CCS compliant software Repeat emulator tests –Need image software Repeat CCD tests –Expand from simple schemes in 1.7 to LSST like schemes (e.g. full cold RTM assemblies even if only two FEBs are populated) Test monitoring and diagnostic modes Test full raft operation (look for any system issues) albeit with only a few CCDs into CDS Verify temperature cycling and temperature stress survival Test temperature measurement and control system Possibly bring in prototype power distribution system Produce one or more RTM assemblies for contamination testing

14 LSST Electronics Review BNL January 25-26, 201214 VST – Phase III Based on pre-production boards (presumably very similar to VST Phase II boards) Full electrical and CCD tests Near final (but still simplified) CCS code Multiple full RTMs Cold RTM and cold RCC Additional contamination studies Final temperature cycling and stress tests Test with pre-production TCM and PDS (Power Distribution System) Verify assembly and test procedures

15 End of Presentation


Download ppt "LSST Electronics Review BNL January 25-26, 20121 LSST Electronics Review BNL January 25-26, 2012 Electronics Development Plan and Vertical Slice Test (VST)"

Similar presentations


Ads by Google