Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Similar presentations


Presentation on theme: "Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation."— Presentation transcript:

1 Project Planning Class 7

2 SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation Maintenance

3 Class today Project Planning in more depth Define the problem Define the objectives Project Feasibility Produce the Project Schedule

4 Defining the Problem Concentrate on current system Provide enough information to make it specific to your application.

5 Define Objectives Should match to most, if not all, problems Why might objectives not cover all problems? Can be both quantitative and qualitative

6 Assessing Project Feasibility Economic Organizational and Cultural (or Political) Technical Schedule Resource Operational Legal/contractual

7 Economic feasibility Identifying the financial benefits and costs associated with the project (CBA) At this point, probably do not know enough to complete in detail. What can be done: list tangible and intangible costs and benefits.

8 Tangible benefits Can be measured in dollars and with certainty. 1. 2. 3. 4.

9 Tangible Benefit Example Time spent finding invoices, receipts, and orders… Assume person spends 10% of time doing this Assume your new system will reduce the time to 1% This represents a 9% reduction in time If person’s salary is $25,000/yr, then savings is $2,250 ($25000 *.09)

10

11 Intangible benefits Difficult to assign dollar amount Customer-related, societal 1. 2. 3.

12 Costs Tangible One-time costs Recurring costs Intangible

13

14

15

16 Other Feasibility Analyses Organizational & Cultural (Political) Technical

17 Other feasibility analyses Schedule Resource

18 Other feasibility analyses Operational Legal / Contractual

19 Staff the Project Covered in earlier class

20 Representing and Scheduling Project Plans Gantt Chart: graphical representation of a project that shows each task activity as a horizontal bar. Pert chart: A diagram that depicts project activities and their inter-relationships. Critical path scheduling: a scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project.

21 Steps in Project Scheduling Identify phases/activities/tasks in project(use SDLC as guide) Estimate the size of the task Determine sequence for identified tasks Schedule tasks

22 Class Activity A project has been defined to contain the following list of activities and tasks along with their required times for completion:

23 ACTIVITY/task Time (weeks) Predecessors ANALYSIS: 1 – collect requirements 2 - 2 – analyze processes 3 1 3 – analyze data 3 2 DESIGN: 4 – design processes 7 2 5 – design data 6 2 6 – design screens 1 3,4 7 – design reports 5 4,5 IMPLEMENTATION: 8 – program 4 6,7 9 – test and document 8 7 10 – install 2 8,9

24 Lab Using Microsoft PM to create a project schedule (Gantt and PERT)


Download ppt "Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation."

Similar presentations


Ads by Google