EURO - Welcome and Introduction EURO - Welcome and Introduction Welcome Status of EUROnu Annual report Milestones and deliverables Publications Technical.

Similar presentations


Presentation on theme: "EURO - Welcome and Introduction EURO - Welcome and Introduction Welcome Status of EUROnu Annual report Milestones and deliverables Publications Technical."— Presentation transcript:

1 EURO - Welcome and Introduction EURO - Welcome and Introduction Welcome Status of EUROnu Annual report Milestones and deliverables Publications Technical review This meeting

2 Safety Information for use at RAL Fire bells... Please leave the building by the closest route and go to the fire assembly point. Klaxon... Please stay inside the building and close any doors or windows having external access. Emergency Number for FIRE, AMBULANCE or FIRST AID. short code from any internal phone 2222 or from a mobile phone 01235 778888 Additionally... Please take a few moments to check that any equipment that may be plugged into the mains supply has undamaged leads, no exposed cables, a secure plug and that you have not created a trip hazard especially if you are on an escape route!

3 Some History Some History 1 st January 1946:Atomic Energy Research Establishment formed on RAF Harwell by John Cockcroft Flight from Harwell Operation Market Garden Sep 1944 1957:National Institute for Research in Nuclear Science (NIRNS) formed to operate the Rutherford High Energy Laboratory. 600 MeV proton linac transferred to RHEL 1964:Nimrod (weak focussing) 7 GeV proton synchrotron starts operation

4 Some History Some History

5 1967:NINA – 6 GeV electron synchrotron - started operation at Daresbury Daresbury 1964

6 Some History Some History 1975:Merged with Atlas Computer Laboratory to form Rutherford Laboratory 1977/78:NINA and Nimrod both closed 1974:Design study for EPIC: 14 GeV e+e- collider – PETRA built instead 1979:Merged with Appleton Laboratory to form Rutherford Appleton Laboratory 1980:SRS starts at DL: first dedicated light source 1985:ISIS starts at RAL

7 Some History Some History

8 2007: Official opening of Diamond 2008:Official closing of SRS

9 Some History Some History During its history, RHEL/RL/RAL has been run by: - NIRNS - SRC - SERC - DRAL - CCLRC - STFC -........

10 Some Logistics Some Logistics All speakers should be able to upload to Indico Please do so! Plenary today and tomorrow: here Friday : CR12 & 13 Coffee : R22 or CR12 Lunch : R22 cafeteria Dinner on Thursday – bus departs from Ridgeway House at 18:45 Don’t be late! Return at 10:15 If you haven’t paid your registration/dinner fee, please do so!

11 Dinner Dinner Drinks in Museum of the History of Science, Oxford Dinner in Exeter College, Oxford: - Established 1314 - 4 th oldest in Oxford

12 Status of EUROnu Status of EUROnu 29/48 th finished! Converging on baselines Important as we need to worry about  costing  safety  technical risks How to do this (i.e. resources) is still to be solved Bottom line: EUROnu is going well!

13 Annual Report #2 Annual Report #2 A lot was learnt from #1! #2 has gone much more smoothly:  Technical information completed on time  some WP too short, some too long  result is a bit uneven  Financial information:  most on time, last few ~2 weeks late  last Form C only arrived yesterday Technical review delayed

14 Deliverables T ABLE 1. D ELIVERABLES Del. no. Deliverable nameVersionWP no.Lead beneficiaryNature Disseminati on level Delivery date from Annex I (proj month) Actual / Forecast delivery date Dd/mm/y yyy Status No submitted/ Submitted Contractual Yes/No Comments D1Requirements for proton driver 122RPU69SubmittedNoSee reportreport D3Review detector performance of baseline scenarios 154RPU1214SubmittedNoSee reportreport D4Review physics of baseline scenarios and optimisation 166RPU1215SubmittedNoSee reportreport D5Review of baseline muon front end 133RPU1526SubmittedNoSee EUROnu- WP3-02 D6Review of baseline large aperture acceleration 135RPU1827SubmittedNoSee EUROnu- WP3-03 D7Comparison criteria211RPU1820SubmittedNoSee reportreport D8Collection device construction 1415PPU18 SubmittedNoSee EUROnu- WP4-15

15 Deliverables

16 Milestones

17 Milestones

18 Publications Publications Reminders  All EUROnu pubs should be on or linked to EUROnu website  All should have a EUROnu number – see website  All should have EC acknowledgement – see website  When submitted to website, email me  Some are protected – you need to login to see them  If you need a login, email me

19 Publications Publications Work PackageNumber of publications General12 WP12 WP26 WP34 WP424 WP53 WP622 Total73

20 Meetings Meetings All meetings should be on the web “Meeting” means anything: - involving discussions between >1 people - uses EUROnu travel funds (EC or matching) Meetings are included in finance reports Better that they can be found on website They also must be listed in annual report

21 Technical Review Technical Review

22 This Meeting This Meeting Very important! Review of progress Discussion of baselines Start preparation for CERN strategy review First thoughts about what comes after EUROnu Welcome to the 3rd annual EUROnu meeting!