Presentation is loading. Please wait.

Presentation is loading. Please wait.

Target Operation and Status Report Chris Booth for Target Team 13 th January 2009 Outline Current target performance Investigation of demonstrator failure.

Similar presentations


Presentation on theme: "Target Operation and Status Report Chris Booth for Target Team 13 th January 2009 Outline Current target performance Investigation of demonstrator failure."— Presentation transcript:

1 Target Operation and Status Report Chris Booth for Target Team 13 th January 2009 Outline Current target performance Investigation of demonstrator failure New mechanical design Control & monitoring issues Particle production vs. beam loss

2 Chris BoothUniversity of Sheffield 2 Current ISIS Target Target operation in ISIS for beam-line studies; >190K pulses by end December. Actuation & control have operated flawlessly – no target drops. Software (DAQ & monitoring) run well, allows remote monitoring. System operated by non-experts. Target behaviour stable and reproducible. 29 th November – target accidentally parked in beam –Interlock added to prevent parking with frame lowered 20 th December – target stopped actuating –Apparent mechanical failure. –No dust visible on inspection plate. –Removed 10 th January for examination. Awaiting news. –(Any connection with previous incident?)

3 Chris BoothUniversity of Sheffield 3 Possible Demonstrator failure causes Misalignment of bearings and shaft. (*) Partial demagnetisation of permanent magnets causing non-axial forces. (*) Distortion of coils causing non-axial forces. Dynamic distortion of shaft. Poorer quality DLC coatings on shaft and/or bearings. (*) Already eliminated at last CM. Above are addressed in the following slides. Several experts from RAL, Sheffield Materials and outside companies (as well as MICE) have been consulted and provided valuable expertise.

4 Chris BoothUniversity of Sheffield 4 Stator Field Measurements & Modelling Field measured (for DC current) by Craig MacWaters & Paul Smith. FEA modelling by Paul. See following slides. Small azimuthal variation seen. Equivalent to coil offsets ≤ 0.2 mm. This is also ~ the precision of the position reproducibility. Upper limit on coil misplacements is therefore 0.2 mm. Further FEA in progress to determine how this maps onto transverse force on the shuttle magnets.

5 Stator field measurements B Field measured for every 0.2mm axially over a distance of 120mm. Repeated at 30 deg increments.

6 FEA Modelling Repeated for AC Data – Similar Match

7 Chris BoothUniversity of Sheffield 7 Dynamic distortion of shaft Distortion of shaft ? Stephanie Yang/ Wing Lau modelled behaviour under acceleration. ~30 Hz mode found (c.f. 30 ms acceleration period in operation. High speed camera data also shows “wagging” motion at similar frequency. (No evidence from camera that Sheffield shock-absorbing mounting is significant.)

8 Chris BoothUniversity of Sheffield 8 Dynamic distortion of shaft Distortion of shaft ? Stephanie Yang/ Wing Lau modelled behaviour under acceleration. ~30 Hz mode found (c.f. 30 ms acceleration period in operation. High speed camera data also shows “wagging” motion at similar frequency. (No evidence from camera that Sheffield shock-absorbing mounting is significant.)

9 Chris BoothUniversity of Sheffield 9 Surface coating problems Poor Diamond-Like Carbon (DLC) coatings ? Sheffield & RAL team visited coating company (TecVac), who had examined failed parts. Likelihood of adhesive failure due to presence of cleaning or polishing materials, or oxidation due to wire erosion of bearings. Sharp edges give electropotential leading to uneven coatings. Surface quality pre-coating was also probably inadequate. (Recommend 0.1 to 0.02 Ra compared with current 1.6 Ra.) Adequate surface finish difficult to achieve with present machined cruciform shaft.

10 Chris BoothUniversity of Sheffield 10 New Mechanical Design Jason Tarrant producing revised mechanical design. –Discussed at weekly target phone meetings. –Details in Target Parallel this afternoon – only summary here. –Huge amount of work summarised in one slide! More rigid stator assembly. New flanges with bearings machined in situ. –Improved alignment, reduced tolerances. Radically different shaft design to improve rigidity, ease of construction, surface finish. –Tubular lower section (not cruciform) –~ same mass/length as at present –Flat on upper cylindrical section, with anti-rotation piece on bearing. Shorter shaft by reducing flange; revised bearing positions.

11 Chris BoothUniversity of Sheffield 11 Revised stator body

12 Upper Bearing Design l Alternative bearing design Wedge & dowel for full x,y,z location of clamp Anti rotation Feature (rounded or flat bearing face options) Single piece main body Wire cut from single piece for accurate wedge fit Full bearing merges into section for anti- rotation M/C with block in place to prevent tool wander Clearance for vane (potential risk if adding vane later otherwise simpler bearing)

13 Chris BoothUniversity of Sheffield 13 Conclusions of Target Workshop last week Timescale very tight. Drawing up documents for review. Key materials (Ti tube) should be ordered now. Baseline target is continued 6 mm tube –Other geometries/materials may have particle production advantages –Must not delay installation of next target Baseline coating is DLC –Other coatings (HIPIMS, WS2, WS2 over DLC) may have advantages. –Investigation will be left for subsequent targets. Informally, ISIS representatives are happy with design. Must have two drives ready for Demonstrator and installation in ISIS during April shutdown.

14 Chris BoothUniversity of Sheffield 14 Control Electronics Upgrade Present system stable, reliable but “expert” system, unfriendly to normal users! PIC processors at computational and I/O limits. Complete redesign planned with improved interfaces, PC configuration & control, flexibility, enhanced feedback, … FPGA-based system using USBDAQ board proposed. James Leaver (IC, FPGA experience) and Paul Smith (present target control designer) working together. 5 crates of electronics may come down to single FPGA plus few daughter cards (for A to D etc)! Requested input from MICE community over desired functionality. Major project – expected to take ~12 months. See talk this afternoon!

15 03/09/2015Imperial College 15 USBDAQ USB Mini- B 1.2V Regulator 2.5/3.3V Regulator Cypress SX2 USB Interface Differential / Single Ended User IO Single Ended User IO 1M Gate Spartan 3 FPGA 4Mb PROM

16 Chris BoothUniversity of Sheffield 16 DAQ & Monitoring Change to new DAQ card has led to driver problems. –Currently converting digital position to analogue! Unsatisfactory. DAQ code (James Leaver) – dumps data to individual pulse files. Target depth, beam intensity, bam losses (various), [frame status] recorded –Wish to include beam position, external delay Various monitoring codes (inc. EPICS based – see Pierrick’s talk this afternoon). Hardware & control upgrades will imply DAQ, monitoring & control software redesigns. Again, input & feedback requested from the community. For more details, see talk this afternoon!

17 Chris BoothUniversity of Sheffield 17 Beam-loss & Particle Production Adam Dobbs – ORBIT simulation of target & ISIS –Different target geometries & orientations. –Present orientation – losses mainly near target –90  rotation – losses near injection (see plots) –Other angles, geometries considered. Marco Apollonio – G4Beamline simulation of collection –Pion acceptance into Q1 largely unaffected by target shape or orientation. –Aluminium, Carbon, Beryllium also considered. –Detailed study required to optimise collected pion to beam loss ratio. –But must also consider mechanical and thermal properties! Aluminium could melt! For more details, see talk in beam-line session.

18 Chris BoothUniversity of Sheffield 18 Present orientation 90  rotated


Download ppt "Target Operation and Status Report Chris Booth for Target Team 13 th January 2009 Outline Current target performance Investigation of demonstrator failure."

Similar presentations


Ads by Google