1 Transelectrica SA Transelectrica’s Strategy
Two-tier-management company Transelectrica’s Strategy in line with European goals Romanian HydroPower Market Outlook and expected developments for 2014 Bucharest, Feb 2014

2 Romania at crossroads i ii iii
Between RGCE (ENTSO-E Continental Europe Regional Group) areas and non (or not yet) ENTSO-E areas (Moldova, Ukraine, Turkey) i Between different congestion management regions within ENTSO-E: - Central East Europe - South East Europe ii Between EU, and non-EU countries within ENTSO-E South-East Europe Regional Group (3rd EU legislative package not mandatory for all the members in the Regional Group) iii

3 Main challlenges faced by Transelectrica
Transelectrica’s challenges facing alignment requirements with 2030 policy framework for climate and energy Integrate renewable generation ( mainly wind) and new generation capacities Development of interconnection capacity to avoid internal/regional congestion Improving adequacy of the transmission grid (full compliance with ENTSO-E standards) High investment requirements

4 capex program ≈1,115 Investment needs 2014-2023 (Eur mill) ≈500
Fossil Fuel PP Wind PP OHL 400kV OHL 220kV OHL 400 kV operated at 220 kV First stage Second stage New lines (> 1000 km) Upgrade/ uprate Power Flows High penetration of wind plants NPP Cernavoda Interconn. capacity increase Investment needs (Eur mill) ≈1,115 Cross border ≈500 RES & Relief of associated congestions ≈265 Replacement and upgrade of aged network assets ≈350 new lines to strengthen the transmission capacity and interconnection capacity new facilities and technology change/updates facilitates the power exchanges in S-E Europe ~400 km, 800 MW, 500 kV consolidate the grid for all generation facilities in the area (renewables and nuclear)

5 Capex program Flagship projects (2014-2023) Cross-border ≈Eur 500 mill
Undersea Cable RO-TR Cross-border ≈Eur 500 mill New interconnector RO-RS (+1000 MW export) Eur 30 mill Reinforcement of internal south-western route* to enhance cross-border interconnectivity (HU and RS) Eur 115 mill New interconnectors RO-MD Eur 105 mill New interconnector (undersea cable) RO-TR Eur 260 mill *route linking Portile de Fier (RO-RS interconnection point) with Arad (RO-HU interconnection point) RES integration and congestion relief ≈Eur 265 mill Connection OHL Isaccea-Varna and OHL Isaccea-Dobrudja in 400 kV Medgidia Sud subtation Eur 28 mill OHL 400kV d.c. Cernavodă-Stâlpu and connection in Gura Ialomiţei Sbt Eur 50 mill OHL 400 kV d.c. Gutinas-Smardan Eur 60 mill OHL 400 kV s.c. Suceava-Gadalin Eur 95 mill Upgrade to 400 kV of OHL 220 kV Brazi Vest- Teleajen-Stalpu Eur 5 mill OHL 400 kV d.c. Medgidia Sud- Constanta Nord Eur 26 mill Replacement & upgrade of existing aged network assets ≈Eur 350 mill

6 Cross-border interconnectivity
Moldova (MD) Cross-border interconnectors (Moldova): OHL 400 kV Suceava (RO) – Balti (MD) EUR 65 mill: OHL total funding EUR 30 mill: OHL Romanian share EUR 40 mill: additional amount for back-to-back in Blati substation OHL 400 kV Straseni (MD) – Ungheni (MD) – Iasi (RO) EUR 100 mill: OHL total funding EUR 15 mill: OHL Romanian share EUR 40 mill: additional amount for back-to-back in Ungheni substation EUR 60 mill: additional amount for reinforcement of the Romania’s internal grid in the area OHL 400 kV Vulcanesti (MD) – Isaccea (RO) EUR 40 mill for back-to-back in Vulcanesti substation MD Suceava Balti Isaccea Vulcanesti Straseni Iasi Ungheni

7 Cross-border interconnectivity
Serbia (RS) Cross-border interconnector (Serbia): OHL 400 kV interconnector between Romania and Serbia Resita (RO) – Pancevo (SE) EUR 30 mill: Romanian share in total funding requirement RS Restita Pancevo Arad Reinforcement of internal south-western route* to enhance cross-border interconnectivity (HU and RS) Eur 115 mill *route linking Portile de Fier (RO-RS interconnection point) with Arad (RO-HU interconnection point) Portile de Fier

8 Cross-border interconnectivity
Turkey (TR) Cross-border interconnector (Turkey): HVDC 500 kV link between Romania and Turkey EUR 520 mill: total project funding requirement EUR 260: Romanian share TR Undersea Cable RO-TR Cost breakdown (EUR mill) Romania new 400 kV AC bay 2 Romania Conv Stn+link to Constanta Nord S/S 89 Romania DC Cable+OTHL+Cable Termination Stn 14 Sea HVDC cable 261 Tukey DC Cable+OTHL+Cable Termination Stn 20 Turkey Conv Stn+link to Alibeykoy S/S 81 Turkey new 400 kV AC bay Telecomunication, incl. cable Client Project Management 5 Contigencies (5%) 25

9 Backup slides

10 General EU Framework Romania’s priorities – in line with EU’s energy&climate goals The communication from the Commission entitled “Energy infrastructure priorities for 2020 and beyond — A Blueprint for an integrated European energy network”, followed by the Council conclusions of 28 February 2011 and the European Parliament resolution, called for a new energy infrastructure policy to optimize network development at European level for the period up to 2020 and beyond, in order to allow the Union to meet its core energy policy objectives of competitiveness, sustainability and security of supply. Regulation (EU) No 347/2013 of The European Parliament and Council of April 17, 2013, on guidelines for trans-European energy infrastructure defines, up to and beyond, about 12 trans-European corridors and thematic areas of priority covering the electricity and gas grids and the transmission infrastructure of oil and CO2 as well: corridors : electricity – 4 + gas – 4 + oil – 1 and 3 thematic areas :Smart grids deployment, Electricity Highways, Cross-border CO2 network

11 Electricity, gas, and oil routes
European energy infrastructure priorities Electricity, gas, and oil routes

12 ENTSO-E’s TYNDP Romanian projects included in EU’s 10-year Grid Masterplan

13 Projected power flow patterns
Romania’s electricity transmission projects bring a positive contribution towards the enhancement of transmission capabilities of the European electricity backbone

14 contact C.N.T.E.E. TRANSELECTRICA S.A. Fiscal Code: 13328043