Presentation is loading. Please wait.

Presentation is loading. Please wait.

H. Hayano, KEK, 10072014 New SRF Facility at Belgrade SRF-WG.

Similar presentations


Presentation on theme: "H. Hayano, KEK, 10072014 New SRF Facility at Belgrade SRF-WG."— Presentation transcript:

1 H. Hayano, KEK, 10072014 New SRF Facility at KEK @LCWS14 Belgrade SRF-WG

2 Outline of proposed Program 2012 supplementary budget, Industry-University cooperation, Center Of Innovetion (COI) program Targeting 10-20 years future social needs, innovative technology development center based on Industry-University cooperation is to be facilitated. KEK and industries proposed: (1) Pollution removal with electricity generation technology, (2) International electricity network, (3) New alternative resource material generation, (4) Ozone layer generator, In the futer. To make innovation to solve above subject, Seeds technologies are; (a) superconducting accelerator technologies (b) technologies of quantum-beam utilization (c) cryo-technologies Energy Environment Resource SC accelerator Industrialization of, compact sized of, SC accelerator = ILC

3 Earth CleanerInternational Energy Network Ozone layer generator Compact material analyzer for new resource material Laboratory university project Overall view of proposal

4 4 New SRF facility : promotion of superconducting accelerator utilization New building (80m x 30m) is under construction at North of STF SC cavity inspection & process, vertical test, cryomodule assembly, cryomodule test

5 Satellite View of new building location

6 Building location detail New SRF building STF building

7 Construction status of new building Construction compeletion will be end of Jan. 2015

8 List of new device to be installed (1) A large size clean room for ILC cryomodule assembly (2) EP facility to develop industrial EP (3) 4-cavities Vertical test stand (4) ILC Cryomodule assembly tools (5) Helium Cryogenics (6) Cryomodule test stand (to be installed later ) with (1) Center control room (2) KEK researcher room (3) Industry room (4) Small meeting room (5) Exhibition space

9 ISO-4, ISO-6 clean rooms, with dual cavity rail ISO4 & ISO6 Clean Rooms for ILC cryomodule assembly

10 Flat-floor Clean Room, ventilating to side wall For easy floor cleaning, easy rail dip cleaning Cavity outside wash room HPR

11 Block diagram of vertical EP system (VEP) HPR Scrubber Wast water tank EP system EP tank

12 Vertical EP (VEP) Cavity mount stage vertical horizontal Mounting at horizontal, Electrode insertion in vertical, EP at vertical. Cavity:fixed Electrode: rotation EP acid flow:vertical H2 gas flow:suction from top Motor driven

13 VEP Cavity vertical position during electrode insertion and EP Cavity horizontal position during cavity and EP header installation Use as a horizontal EP is also possible.

14 VEP Electrode Insertion HPR (Nozzle rotation type) VEP

15 HPR (High Pressure water Rinsing) Top view Side view Front view from EP floor Clean Room side Clean Room side EP floor Side(2F) Take-out To Clean room Mount From EP room HPR Cavity: no rotation, but up and down Water nozzle: rotation

16 DESY AMTF Under Building 4-cavity Vertical Test Stand, following DESY AMTF KEK new vertical test cryostat Vertical Test

17 Hanging 4 cavities with jacket and pipe Vertical Test TESLA cavity with jacket TESLA cavity w/o jacket

18 Cryomodule assembly tool Cryomodule Assembly tools, following to DESY/Saclay XFEL facility

19 Cryomodule assembly tool Cryomodule Assembly tools, following to DESY/Saclay XFEL facility

20

21 Experiment Hall South half-side 7t crane North half-side 15t crane View from control room View from east to west

22 Resident space 1 st floor, exhbition space and stairs, view from entrance 2nd floor, open space and control room

23 Plan of Start-up schedule JFY2013JFY2014JFY2015JFY2016 building facility Module Test facility COI project Design and construction Design and fabrication Kept in ATF Installation and commissioning Design and fabrication COI project start Organizing industry-university cooporation And project planning We are here Budget came here

24 End of Slide


Download ppt "H. Hayano, KEK, 10072014 New SRF Facility at Belgrade SRF-WG."

Similar presentations


Ads by Google