Caltrain Modernization Program Update Palo Alto City Council Rail Committee August 10, 2012.

Similar presentations


Presentation on theme: "Caltrain Modernization Program Update Palo Alto City Council Rail Committee August 10, 2012."— Presentation transcript:

1 Caltrain Modernization Program Update Palo Alto City Council Rail Committee August 10, 2012

2 Presentation Topics 1.State Legislature Update 2.Next Steps for the Peninsula 3.Blended System Planning Analysis Update 4.Discussion

3 State Legislature Update

4 Green Light for HSR & Blended System Bay Area State Assembly and Senate support –Elaine Alquist, D-San Jose –Tom Ammiano, D- San Francisco –Jim Beall, D-San Jose –Nora Campos, D-San Jose –Paul Fong, D-Mountain View –Rich Gordon, D-Menlo Park –Jerry Hill, D-San Mateo –Mark Leno, D-San Francisco –Fiona Ma, D-San Francisco –Leland Yee, D-San Francisco

5 SB 1029 Appropriates $705 million for Caltrain Modernization –$600 million from Prop 1A (HSR) –$105 million from Prop 1A (Connectivity) Funds available for: –“blended system improvements consistent with the MOU” and –“shall not be used to expand the system to a dedicated four-track system” Bonds sold and allocated to project by State Controller

6 Next Steps for the Peninsula

7 Project Delivery Focus Early Investment (2019) –Define outreach/decision-making structure and process –Advanced Signal System  Advance design from “Critical” to “Final” –Electrification & Electric Vehicles  Update / Recirculate Caltrain EA/EIR  Define project delivery approach/team Blended System (2029) –Complete current planning studies –Schedule for completing planning process

8 Blended System Planning Update

9 Blended System Planning Process Decision-Making Matrix Blended System Alternatives Design & Environmental Review Infrastructure NeedRevenue / CostFleet Need Capacity Analysis Service Plan Options Grade Crossing & Traffic Analysis Service Plan / Operations Considerations

10 Blended System Service Plan/Operations Considerations Analysis

11 Purpose / Goals Consider service / operations variables not included in capacity analysis Requested by stakeholders Inform development of service plan options

12 Scope of Work 4 Track – Full & Short Midline – Evaluated in Capacity Analysis 4 Track - Northern 4 Track - Southern 3 Track Passing Track Options* Mid-Peninsula HSR Station Baby Bullet Service Longer Trains / Less Train Traffic Different Service Patterns DTX to TBT Dumbarton Rail Future ACE, Capitol Corridor, Amtrak service Future Freight Service Storage/Maintenance Facility 3 rd Party Future Plans

13 Passing Track Options OptionsLocations 4 Tracks – NorthernMilepost 5 to 15.2 (Bayshore to Millbrae stations) 4 Tracks - Full MidlineMilepost 18.1 to 27.2 (Hayward Park to Redwood City stations) 4 Tracks - Short MidlineMilepost 18.1 to 24.2 (Hayward Park to Whipple Ave.) 4 Tracks - SouthernMilepost 33.8 to 41.6 (San Antonio to Lawrence station) 3 Tracks Milepost 18.1 and 33.7 (Hayward Park to California Ave. )

14 Simulation Model Results 4 Track Options 3 Track Option –Model: high performance –Practice: further evaluation Operational Performance Ranking High:Full Midline Medium:Short Midline & Southern Low :Northern

15 Decision Matrix (work in progress) Passing Track Options Considerations OperationsE & CROWCostCity / County 4 Tracks - Northern 4 Tracks - Full Midline 4 Tracks - Short Midline 4 Tracks - Southern 3 Tracks

16 Blended System Grade Crossing & Traffic Analysis

17 40 at-grade crossings Identify relationship between: –Train service levels –Gate down time –Local traffic Analyze future scenarios (2035): –Impacts from Caltrain versus future growth –Difference between service plan options Improvement recommendations Study Purpose & Goals

18 Draft & Final Report Improvement Options Future Conditions Existing Conditions Inputs Key Tasks and Status

19 Discussion