Download presentation
1
TUNNELS
2
TERMINOLOGY for UNDERGROUND STRUCTURES
Adit galeri Tunnel tünel Subway metro Shaft baca Chamber oda Portal ana giriş veya çıkış Pilot adit yan galeri, pilot galerisi Centre merkez, eksen Face ayna Wall ~ site yan, kenar, duvar Floor taban Roof tavan
3
Overbreak.............................aşırı sökülme
Excavated profile kazı profili Natural archling doğal kemerlenme Load yük Support destek, iksa Failure yenilme, çökme Gentle failure yavaş yenilme Rock burst kaya patlaması Squeezing ground sıkışan zemin Swelling ground şişen zemin Clay-filled joint kil dolgulu eklem Long term stability uzun süreli duraylılık Ground treatment zemin iyileştirmesi Support before excavation....kazı öncesi destekleme
4
Jet grouted roof cover..............jet grouting ile iyileştirilmiş tavan örtüsü
Shotcrete initial lining püskürtme beton başlangıç çizgisi Jet grouted floor cover jet grouting ile iyileştirilmiş döşeme Top heading kalot (Crown) Invert stros (Bottom excavation) Bench üzengi çizgisi Final concrete lining sonuncu beton kaplama (nihai beton kaplama çizgisi) SHIELD tunnelling method KALKAN Yöntemi CUT & COVER tunnelling method....AÇ-KAPA Yöntemi TBM (Full face ~ Total Boring Machine).....TÜM KESİT KAZI MAKİNASI
5
TERMINOLOGY for EXCAVATIONS of ROCKS & SOILS
DRILLING Sondalama Hardness Sertlik Toughness Dayanım – direnç Abrasiveness Aşındırıcılık Structure Jeolojik yapı Drilkling fluids Sondaj sıvısı AUGERING Burgulama MACHINE BORING.....Mekanize tünel açma Total Boring Machine (TBM) Full face excavation BLASTING Patlatma
6
SCRAPING...................Kazıma (makinayla)
RIPPING Kırarak kazıma DIGGING Kazma GROUND WATER yeraltısuyu Control of groundwater Groundwater flow Rate of flow Volume of flow Boundaries
7
TUNNEL DESCRIPTION Made into natural material (rocks) Empty inside
Carry the loads itself Both ends are open to atmosphere Generally horizontal Thick walled structure looks like cylinder
9
1- Kilit (anahtar) taşı........................Key stone
2- Kemer Arch 3- Ayak (duvar) Wall 4- Taban Floor 5- Üzengi Bench 6- Üzengi çizgisi (düzeyi) Bench line or plane 7- Kalot Top heading 8- Stros Invert 9- Ano Ano (unit)
10
Tunnel Section for Swelling Ground
1- Digging section 2- Support 3- Swelling section 4- Pressurized area 5- Flow direction of water
11
SURFACE EXCAVATIONS Deformation & failure
12
UNDERGROUND EXCAVATIONS
In Rock In Sediment Stability & Arching Water Dry tunnel above water table Wet tunnel below water table Gases Carbon dioxide (CO2) Carbon monoxide (CO) Methane (CH4) Hydrogen sulphide (H2S) Other gases
13
Gas bursts......................gaz patlaması
Rock falls kaya düşmesi Rock bursts kaya fırlaması Squeezing ground şişen – kabaran zemin Temperature Subsidence
14
EXPLORATION & INVESTIGATIONS RELATED of SLOPE STABILITY
Geomorphologic maping and preparation of longitudinal & cross sections Geological maping & surveyings (aerial photographs) Geophysical surveyings Underground explorations, boreholes Ground water surveyings Laboratory tests Model studies
15
SURFACE EXCAVATIONS Permanent Short term excavations
16
SUBSURFACE EXCAVATIONS
GEOLOGY Soil profile or hard rock geology Structure Ground water (hydrogeology) Stability
17
INVESTIGATIONS Mapping (Topographic, geologic, etc...)
Geophysical surveying (especially seismic velocity of rocks) Trial pits & boreholes General and local stability analysis Decide to excavation method
19
UNDERGROUND EXCAVATIONS
Adit, shaft, incline, large chamber Tunnel Subway ~ metro Underpass Shelter Power house Ware house, store, mining ...etc
20
GASES (can be lethal or burst)
Carbon monoxide (CO) of air Carbon dioxide (CO2) of air Methane (CH4) of air (Highly explosive with air) marsh gas Hydrogene sulphide (H2S) 1.19 of air (Highly toxic and explosive) Sulphur dioxide (SO2)
21
ROCK FALL SQUEEZING GROUND (sand, silt, shale, clay) ROCK BURST BULKING (Increase in volume, 10-40%)
22
FACTORS EFFECTING EXCAVATION of ROCKS
Mineralogical composition of rocks Texture & fabric Petrographic features Structure Rock mass Strike & dip of beds in relation to face of excavation Intensity of tectonic disturbances Degreee of weathering
23
RESISTANCE of ROCKS to EXCAVATION
Loose soils Soil easy to spade (bel ile kazmak) Soil easy to dig Crumbling weak rocks (ufalamak) Rocks easy to blast Rocks difficult to blast Rocks very difficult to blast
24
TUNNELLING METHODS
25
SHIELD TUNNELLING METHOD
This method involves the use of shield machine to drive the tunnels below the ground. After completion of a work shaft, the shield machine is lowered into the shaft and assembled there before excavation and construction of the tunnels using precast concrete lining segments of about 1.2 meter width. This construction method causes minimal disruption to traffic and the environment because all the work takes place below ground and the ground level environment is unaffected.
27
CUT and COVER TUNNELLING METHOD
This construction method, whereby the site is fully excavated, the structure built and then covered over, uses diaphragm walls as temporary retaining walls within the site area. Step one :Construction of diaphragm walls, pin piles, and decking. Step two :Excavation within the diaphragm walls, installing struts as work progresses. Step three :Construction of permanent floor slabs and walls. Step four : Fitting out the internal structures, backfilling, and reinstating the surface structures.
29
TBM (Tunnel Boring Machine)
Mechanical-support TBM Compressed-air TBM Slurry shield TBM Earth pressure balance machine Mixed-face shield TBM
30
1- Mechanical Support TBM
A mechanical-support TBM has a full-face cutterhead which provides face support by constantly pushing the excavated material ahead of the cutterhead against the surrounding ground.
31
2- Compressed-Air TBM A compressed-air TBM can have either a full-face cutterhead or excavating arms. Confinement is achieved by pressurizing the air in the cutter chamber.
32
3- Slurry Shield TBM A slurry shield TBM has a full-face cutterhead. Confinement is achieved by pressurizing boring fluid inside the cutterhead chamber.
33
4- Earth Pressure Balance Machine
An earth pressure balance machine has a full-face cutterhead. Confinement is achieved by pressurizing the excavated material in the cutterhead chamber.
34
5- Mix-Face Shield TBM Mix-face shield TBMs have full-face cutterheads and can work inclosed or open mode and with different confinement techniques.
35
EFFECT of GEOLOGICAL STRUCTURES to TUNNEL EXCAVATION
Effect of soil layers: horizontal, vertical and inclined layers have different kinds of loading conditions for tunnels.
36
Effect of faults: the relation between the fault slope direction and the tunnel direction, width of the fault zone, type and thickness of the fill material and the hydrostatic pressures in both sides of the fault are some problems in the tunnelling. Relation between the fault zone and the tunnel
37
Tunnel excavations in the slopes: the discontinuities (layers, fissures) inclined inside or outside of the slope are very important regarding the stress and strength of the tunnel.
38
Effect of the folds: While tunnel is excavated in an area that contains folded rocks, different stresses and conditions may occur depending on the fold type. Fold axis and the tunnel direction is parallel Fold axis and the tunnel direction is vertical
39
CLASSIFICATION of ROCKS for TUNNELING PURPOSES
40
Classification of rocks for engineering purposes is needed in analyzing the project costs and to obtain an economic and reliable solution. The classification of the rocks, that the tunnel will be constructed in, is first done by Terzaghi. But, it is too general and gives qualitative results.
41
TUNNEL ROCK CLASSIFICATION by TERZAGHI
42
Laufer classified tunnel rocks to 7 groups according to stand-up time
43
Rock classification and determination of unsupported span
44
URFA IRRIGATION TUNNEL
46
ONE of the LONGEST IRRIGATION TUNNELS in the WORLD
47
Consist of two concrete lined tunnels each of which is 7
Consist of two concrete lined tunnels each of which is 7.62 m in diameter and 26.4 km in length discharging water from the reservoir of Atatürk Dam.
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.