Presentation is loading. Please wait.

Presentation is loading. Please wait.

Integrated Civil Engineering Design Project (Building Structure Design Example) CIVL 395 HKUST By : Ir. K.S. Kwan Date: 4/07.

Similar presentations


Presentation on theme: "Integrated Civil Engineering Design Project (Building Structure Design Example) CIVL 395 HKUST By : Ir. K.S. Kwan Date: 4/07."— Presentation transcript:

1 Integrated Civil Engineering Design Project (Building Structure Design Example) CIVL 395
HKUST By : Ir. K.S. Kwan Date: 4/07

2 Architectural Consideration
Limitation (plot ratio, height, public facilities, slope) View/light/Wind climate Flat size, Number of Blocks Podium (Other Facilities – Cube house/ Carpark/ Commercial complex) Budget estimation Other considerations

3 Structural Engineer Consideration
Any site construction difficulties Site Access Construction platform Foundation option Time for completion Tower Design To provide a cost-effective solution

4 Lack of flexibility by structural element
Case A : 45 storey Lack of flexibility by structural element End wall should be effectively used as shear wall to provide better stiffness

5 To enhance the stiffness of building by linking the walls as much as possible

6 Lack of flexibility by structural element
Too much wall No support for slab

7 Wall not allowed in front of stairs
Beam ahead bedroom Too much wall End wall should be effectively used as shear wall to provide better stiffness

8 Structural Framing Plan
Secondary Beam for gravity load only Aspect ratio = 45x3/19 =7.0 Lintel Beam For both wind load and gravity load

9 Case B: 15 storey

10 Aspect ratio = 15x3/60 =0.75 Column structure used

11 Case C: 57 storey

12 Aspect ratio = 57x3/24.3 =7.03

13 Podium Structure To confirm the column layout under transfer structure
To confirm the transfer plate/column layout To confirm the size of transfer structure (e.g. thickness of transfer plate) Evaluate the tower loading and estimate the size of transfer structure size

14

15 Tower Framing plan

16 Transfer Structure under tower

17 Supporting columns under transfer structure

18 Other beam/column structure below

19 Other beam/column structure below

20 Other beam/column structure below

21 Preliminary Computer Model
Use the effective members for first model Estimate the member size for model input based on gravity load first and provide some reserve for wind load (say 20 ~40% of wind load) Check top deflection < H/500

22 Minor wall not selected for preliminary modeling
Only analysis the critical wind direction Only use the effective members for modeling Minor wall not selected for preliminary modeling Width of building to calculate the wind load

23 For preliminary model, only typical floor is used to simulate the whole tower.
Building height should be maintained Tower model Podium model

24 Element Checking Check critical lintel beam force (e.g. check wind shear stress v=V/bd ) Check critical element force (e.g. wall element under high compression/tension)

25 Loading Schedule Checking
Check average gravity load (Total D+L/Gross Floor Area = 15~20 KN/m2 Total axial force = 0 Check total wind shear force = total wind force applied at the building

26 Q & A

27


Download ppt "Integrated Civil Engineering Design Project (Building Structure Design Example) CIVL 395 HKUST By : Ir. K.S. Kwan Date: 4/07."

Similar presentations


Ads by Google