Presentation is loading. Please wait.

Presentation is loading. Please wait.

Announcements Be reading Chapter 7

Similar presentations


Presentation on theme: "Announcements Be reading Chapter 7"— Presentation transcript:

0 ECE 476 POWER SYSTEM ANALYSIS
Lecture 17 Economic Dispatch, OPF, Markets Professor Tom Overbye Department of Electrical and Computer Engineering

1 Announcements Be reading Chapter 7
HW 7 is 12.26, 12.28, 12.29, 7.1 due October 27 in class. US citizens and permanent residents should consider applying for a Grainger Power Engineering Awards. Due Nov 1. See for details. The Design Project, which is worth three regular homeworks, is assigned today; it is due on Nov 17 in class. It is Design Project 2 from Chapter 6 (fifth edition of course). For tower configuration assume a symmetric conductor spacing, with the distance in feet given by the following formula: (Last two digits of your UIN+50)/9. Example student A has an EIN of xxx65. Then his/her spacing is (65+50)/9 = ft.

2 Inclusion of Transmission Losses
The losses on the transmission system are a function of the generation dispatch. In general, using generators closer to the load results in lower losses This impact on losses should be included when doing the economic dispatch Losses can be included by slightly rewriting the Lagrangian:

3 Impact of Transmission Losses

4 Impact of Transmission Losses
The penalty factor at the slack bus is always unity!

5 Impact of Transmission Losses

6 Calculation of Penalty Factors

7 Two Bus Penalty Factor Example

8 Thirty Bus ED Example Because of the penalty factors the generator incremental costs are no longer identical.

9 Area Supply Curve The area supply curve shows the cost to produce the
next MW of electricity, assuming area is economically dispatched Supply curve for thirty bus system

10 Economic Dispatch - Summary
Economic dispatch determines the best way to minimize the current generator operating costs The lambda-iteration method is a good approach for solving the economic dispatch problem generator limits are easily handled penalty factors are used to consider the impact of losses Economic dispatch is not concerned with determining which units to turn on/off (this is the unit commitment problem) Economic dispatch ignores the transmission system limitations

11 Thirty Bus ED Example Case is economically dispatched without considering the incremental impact of the system losses

12 Optimal Power Flow The goal of an optimal power flow (OPF) is to determine the “best” way to instantaneously operate a power system. Usually “best” = minimizing operating cost. OPF considers the impact of the transmission system OPF is used as basis for real-time pricing in major US electricity markets such as MISO and PJM. ECE 476 introduces the OPF problem and provides some demonstrations.

13 Electricity Markets Over last ten years electricity markets have moved from bilateral contracts between utilities to also include spot markets (day ahead and real-time). Electricity (MWh) is now being treated as a commodity (like corn, coffee, natural gas) with the size of the market transmission system dependent. Tools of commodity trading are being widely adopted (options, forwards, hedges, swaps).

14 Electricity Futures Example
Source: Wall Street Journal Online, 10/19/11

15 Historical Variation in Oct 11 Price
Price has dropped, following the drop in natural gas prices Source: Wall Street Journal Online, 10/19/11

16 “Ideal” Power Market Ideal power market is analogous to a lake. Generators supply energy to lake and loads remove energy. Ideal power market has no transmission constraints Single marginal cost associated with enforcing constraint that supply = demand buy from the least cost unit that is not at a limit this price is the marginal cost This solution is identical to the economic dispatch problem solution

17 Two Bus ED Example

18 Market Marginal (Incremental) Cost
Below are some graphs associated with this two bus system. The graph on left shows the marginal cost for each of the generators. The graph on the right shows the system supply curve, assuming the system is optimally dispatched. Current generator operating point

19 Real Power Markets Different operating regions impose constraints -- total demand in region must equal total supply Transmission system imposes constraints on the market Marginal costs become localized Requires solution by an optimal power flow

20 Optimal Power Flow (OPF)
OPF functionally combines the power flow with economic dispatch Minimize cost function, such as operating cost, taking into account realistic equality and inequality constraints Equality constraints bus real and reactive power balance generator voltage setpoints area MW interchange

21 OPF, cont’d Inequality constraints Available Controls
transmission line/transformer/interface flow limits generator MW limits generator reactive power capability curves bus voltage magnitudes (not yet implemented in Simulator OPF) Available Controls generator MW outputs transformer taps and phase angles

22 OPF Solution Methods Non-linear approach using Newton’s method
handles marginal losses well, but is relatively slow and has problems determining binding constraints Linear Programming fast and efficient in determining binding constraints, but can have difficulty with marginal losses. used in PowerWorld Simulator

23 LP OPF Solution Method Solution iterates between
solving a full ac power flow solution enforces real/reactive power balance at each bus enforces generator reactive limits system controls are assumed fixed takes into account non-linearities solving a primal LP changes system controls to enforce linearized constraints while minimizing cost

24 Two Bus with Unconstrained Line
With no overloads the OPF matches the economic dispatch Transmission line is not overloaded Marginal cost of supplying power to each bus (locational marginal costs)

25 Two Bus with Constrained Line
With the line loaded to its limit, additional load at Bus A must be supplied locally, causing the marginal costs to diverge.

26 Three Bus (B3) Example Consider a three bus case (bus 1 is system slack), with all buses connected through 0.1 pu reactance lines, each with a 100 MVA limit Let the generator marginal costs be Bus 1: 10 $ / MWhr; Range = 0 to 400 MW Bus 2: 12 $ / MWhr; Range = 0 to 400 MW Bus 3: 20 $ / MWhr; Range = 0 to 400 MW Assume a single 180 MW load at bus 2

27 B3 with Line Limits NOT Enforced
Line from Bus 1 to Bus 3 is over- loaded; all buses have same marginal cost

28 B3 with Line Limits Enforced
LP OPF redispatches to remove violation. Bus marginal costs are now different.

29 Verify Bus 3 Marginal Cost
One additional MW of load at bus 3 raised total cost by 14 $/hr, as G2 went up by 2 MW and G1 went down by 1MW

30 Why is bus 3 LMP = $14 /MWh All lines have equal impedance. Power flow in a simple network distributes inversely to impedance of path. For bus 1 to supply 1 MW to bus 3, 2/3 MW would take direct path from 1 to 3, while 1/3 MW would “loop around” from 1 to 2 to 3. Likewise, for bus 2 to supply 1 MW to bus 3, 2/3MW would go from 2 to 3, while 1/3 MW would go from 2 to 1to 3.

31 Why is bus 3 LMP $ 14 / MWh, cont’d
With the line from 1 to 3 limited, no additional power flows are allowed on it. To supply 1 more MW to bus 3 we need Pg1 + Pg2 = 1 MW 2/3 Pg1 + 1/3 Pg2 = 0; (no more flow on 1-3) Solving requires we up Pg2 by 2 MW and drop Pg1 by 1 MW -- a net increase of $14.

32 Both lines into Bus 3 Congested
For bus 3 loads above 200 MW, the load must be supplied locally. Then what if the bus 3 generator opens?

33 Profit Maximization: 30 Bus Example

34 Typical Electricity Markets
Electricity markets trade a number of different commodities, with MWh being the most important A typical market has two settlement periods: day ahead and real-time Day Ahead: Generators (and possibly loads) submit offers for the next day; OPF is used to determine who gets dispatched based upon forecasted conditions. Results are financially binding Real-time: Modifies the day ahead market based upon real-time conditions.

35 Payment Generators are not paid their offer, rather they are paid the LMP at their bus, the loads pay the LMP. At the residential/commercial level the LMP costs are usually not passed on directly to the end consumer. Rather, they these consumers typically pay a fixed rate. LMPs may differ across a system due to transmission system “congestion.”

36 MISO and PJM Joint LMP Contour

37 Why not pay as bid? Two options for paying market participants
Pay last accepted offer What would be potential advantages/disadvantages of both? Talk about supply and demand curves, scarcity, withholding, market power

38 Market Experiments


Download ppt "Announcements Be reading Chapter 7"

Similar presentations


Ads by Google