1 FM 5S Project Housekeeping equipment storage
Spring 2014

2 FM 5S Projects Richard Smith provided overview training on April 9, 2014 All FM team leaders attended Sort, Set in order, Shine, Standardize and Sustain Reviewed the 8 Wastes Lack of Focus, Excess Inventory, Transportation, Motion, Waiting, Defects, Over Processing and Over Production

3 Charter Mission – To provide Berea College with clean dormitory and office areas in a highly efficient manner along with the highest level of customer service. Process Description – Housekeeping staff stores and retrieves equipment and supplies from a centrally located storage area. Problem Statement – Because the equipment and supplies are not organized systematically by type and because a large amount of obsolete or broken equipment is stored in this area there is not a logical or efficient way to retrieve the required equipment. Sponsor – Wayne Orr / Jeff Reed Process Owner – Teena Riddell Team Lead – Teena Riddell Facilitator – Richard Smith Team – Teena Riddell, Ronnie Vanhook, Matt Partain, Lindsey Mullins, Teresa Barrett, Jeff Reed, Terry Bingham, Richard Smith, and Jonathan Taylor IT solutions around the corner?

4 BEFORE AFTER

5 BEFORE AFTER

6 BEFORE AFTER

7 Sustain

8 Sustain

9 Close Out Notes Safer work area
Equipment retrieval time reduced from 30 minutes to 5 minutes. Recovered floor space for vacuum cleaner storage. Cost avoidance of $12,000.