 Target K. Long, 23 August 2009 Sunday 23Aug09 Water and power connections made Test water, check power Will plan soak test.

Similar presentations


Presentation on theme: " Target K. Long, 23 August 2009 Sunday 23Aug09 Water and power connections made Test water, check power Will plan soak test."— Presentation transcript:

1  Target K. Long, 23 August 2009 Sunday 23Aug09 Water and power connections made Test water, check power Will plan soak test

2 Status of build: Target 1: – Complete, 50 k actuations done OK Target 2: – Complete

3 Critical path: Issue: – Modified power supply: Charge/discharge time-constant differs between +ve and –ve capacitor banks S.Griffiths will investigate – Testing continues with power supply brought to RAL form Sheffield Installation planned ‘on schedule’: – Tuesday/Wednesday 25/26Aug09