Download presentation
Presentation is loading. Please wait.
Published byAndrea Jordan Modified over 9 years ago
1
A tutorial on MS Project James Burns
2
Outline Setting up MS Project Defining Tasks (activity definition) Activity Subordination (WBS) Activity Sequencing (network chart) Determining durations Determining costs
3
Setting up MS Project Your first task should be a PROJECT meta-task Everything (every other task) should be subordinate to it
4
Must start with A list or tasks Or A Work Breakdown Structure
5
Defining Tasks This process is called Activity Definition Can do it by developing the WBS down to work packages Can do it by use of template Can do it by use of a list Or just off the top of your head
6
Bring up MS Project Start in the Gantt View Set start date in Project Information box Can do forward or backward scheduling Enter task detail in the entry table to the left Subordinate tasks appropriately Link Tasks as appropriate
7
Working from the WBS WBS’s utilize a standardized numbering scheme WBS Subordination is indicated to MS Project through indentation Use the indentation arrow
8
Click on Project and then Project Information Brings up this window
9
Can download add-ons from CriticalTools.Com To delineate (draw) the WBS To do PERT (Neither of which are available within MS Project)
10
Setting hard and fast task dates Normally, this is not a good idea Do this on the entry table
11
Adding resources Resource sheet
12
Determining cost and duration Must enter the hourly rates of the PROJECT PLAYERS into the RESOURCE SHEET
13
Tables
14
Reports
15
Microsoft Project Popular software package for project management and CPM/PERT analysis Relatively easy to use Copyright 2011 John Wiley & Sons, Inc.9-15
16
Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-16 Click on “Tasks” First step; Start Date
17
Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-17 Precedence relationships Click on “Format” then ”Timescale” to scale Gantt chart. Gantt chart; click on “View” to activate Create precedence relationships; click on predecessor activity, then holding “Ctrl” Key, click on successor activity.
18
Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-18 Click on “View” then Network Diagram Critical path in red
19
Microsoft Project – Zoom View Copyright 2011 John Wiley & Sons, Inc.9-19
20
Microsoft Project – Task Information Copyright 2011 John Wiley & Sons, Inc.9-20 Enter % completion
21
Microsoft Project – Degree of Completion Copyright 2011 John Wiley & Sons, Inc.9-21 Activities 1, 2 and 3 100% complete Black bars show degree of completion
22
PERT Analysis with Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-22 Click on PERT Entry Sheet to enter 3 time estimates Click on PERT calculator to compute activity duration
23
PERT Analysis with Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-23
24
PERT Analysis with Microsoft Project Copyright 2011 John Wiley & Sons, Inc.9-24
25
Project Crashing Crashing reducing project time by expending additional resources Crash time an amount of time an activity is reduced Crash cost cost of reducing activity time Goal reduce project duration at minimum cost Copyright 2011 John Wiley & Sons, Inc.9-25
26
Project Network – Building a House Copyright 2011 John Wiley & Sons, Inc.9-26 1 12 2 8 4 3 4 5 4 6 4 7 4
27
Normal Time and Cost vs. Crash Time and Cost Copyright 2011 John Wiley & Sons, Inc.9-27 $7,000 – $6,000 – $5,000 – $4,000 – $3,000 – $2,000 – $1,000 – – ||||||| 02468101214Weeks Normal activity Normal time Normal cost Crash time Crashed activity Crash cost Slope = crash cost per week
28
Project Crashing Copyright 2011 John Wiley & Sons, Inc.9-28 TOTAL NORMALCRASHALLOWABLECRASH TIMETIMENORMALCRASHCRASH TIMECOST PER ACTIVITY(WEEKS)(WEEKS)COSTCOST(WEEKS)WEEK 1127$3,000$5,0005$400 2852,0003,5003500 3434,0007,00013,000 412950,00071,00037,000 5415001,1003200 6415001,1003200 74315,00022,00017,000 $75,000$110,700
29
Copyright 2011 John Wiley & Sons, Inc.9-29 Project Duration: 36 weeks 1 12 2 8 3 4 5 4 6 4 7 4 $400 $500 $3000 $7000 $200 $7000 12 4 FROM … 1 7 2 8 3 4 5 4 6 4 7 4 $400 $500 $3000 $7000 $200 $7000 12 4 Project Duration: 31 weeks Additional Cost: $2000 TO…
30
Time-Cost Relationship Copyright 2011 John Wiley & Sons, Inc.9-30 Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs/day are less than indirect costs/day
31
Time-Cost Tradeoff Copyright 2011 John Wiley & Sons, Inc.9-31 Cost ($) Project duration CrashingTime Minimum cost = optimal project time Total project cost Indirect cost Direct cost
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.