TS2-SPS & TS1-LHC. TS2-SPS (On Monday 15th of June for 24hrs) SPS – HW: Replacement of HV Switch PFN 7 MKP (Impact 65420) SW: « Smooth » upgrade in accordance.

Similar presentations


Presentation on theme: "TS2-SPS & TS1-LHC. TS2-SPS (On Monday 15th of June for 24hrs) SPS – HW: Replacement of HV Switch PFN 7 MKP (Impact 65420) SW: « Smooth » upgrade in accordance."— Presentation transcript:

1 TS2-SPS & TS1-LHC

2 TS2-SPS (On Monday 15th of June for 24hrs) SPS – HW: Replacement of HV Switch PFN 7 MKP (Impact 65420) SW: « Smooth » upgrade in accordance with BE/CO

3 TS1-LHC Week 25, 5 days LHC – SW: FESA Software release in accordance with BE/CO – MKI Point 2 and Point 8 No request of consignation from the coordination (to confirm) Improvement of the rise time : – Adjustement front cell on PFN 2d/point (Impact - 64460 & 64461) Replacement FIB AGK 0.5 d/point (Impact to launch) Update class LhcMKIstate with TDR measurements Update BETS TDI table 3

4 TS1-LHC Week 25, 5 days LHC Point 4 MKQA – Checking the tightening of the capa bank on AC dip Generator (Impact to launch) LHC point 6 LIU-TCDI – Floor Levelling - Impact 64913 – Check BEC 4

5 TS1-LHC Week 25, 5 days LHC – LBDS Point 6 – Consignation for EN: From On monday up to Wednesday morning – Inspection inside of some MKD generators HV (Impact 65125) – Cleaning up MKB generators H and may be V (Impact 65125) – Pre-tests (Planning ? Impact to launch) – Noise measurement on IPCO1 at low energy pulsed (Impact to launch) – Cleaning of cabling in GP rack (Impact to launch) – Check UPS powering in UA 63 and ABDT signal on TSU-A in UA67 – Put into place of 2 racks in the storage area for electronic spares storage 5