Industry information day 21.05.2015 1 INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project Leader 21 st May 2015
2
Industry information day 21.05.2015 2 1.What is the BIPS scope and organization 2.Procurement status 3.Schedule 4.Status of the works 5.Status of the works in 2017 Summary
3
Industry information day 21.05.2015 Overview of the scope for Buildings Reinforced Concrete Buildings 250 000 m 3 of concrete (including 190 000 m 3 for Nuclear buildings) 21 000 m 2 footprint 750 000 m 3 building volume Steel Frame Buildings 29 000 m 2 footprint Power supplies (HV, MV, and LV distribution) Detailed design, installation and commissioning Procurement of the emergency generators, the cables, and 25% of the SSEN equipment Current arrangement: the remainder of the equipment are procured by other Domestic agencies (China and US) Site infrastructures (Galleries, trenches, roads, bridges fences) ITER : 180 ha with 39 buildings and areas on the 40 ha platform 3 Buildings program is 1.5 Billions of Investments
4
Industry information day 21.05.2015 4 Overview of the ITER Buildings
5
Industry information day 21.05.2015 5 Organization – Buildings contracts management BIPS PT IO/F4E Support to the Owner Energhia / Tiresia Internal and External Experts Health and Safety Coordination Legal Inspection Architect Engineer Tender Batch 04 Omega OWNER FIDIC Engineer IMPLEMENTATION Tender Batch 03 Vinci Ferrovial Razel Tender Batch 05. 06. 07 Ferrovial FIDIC Engineer 250 staff 270 staff -> 800 200 staff -> 800 50 staff -> 200
6
Industry information day 21.05.2015 PROCUREMENT STATUS 6
7
Industry information day 21.05.2015 7 1 B€ of construction contracts on-going TB07 Cooling Towers -15 M€ TB03 & TB04 Tokamak Complex & Assembly Hall TB03 : 300M€ TB04 : 500M€ TB02 Long Lead – Mechanical Handling: 32M€ TB05 Magnet Power Conversion & Reactive Power Control buildings - 25 M€ TB06 High Voltage Electrical Equipment - 38 M€
8
Industry information day 21.05.2015 8 Remaining procurement packages TB12 NB buildings TB16: Site infrastructures TB11: Completion works TB09 & TB10 Hot Cell complex TB13 Emergency Power Supplies
9
Industry information day 21.05.2015 9 Preparatory Phase: TB00 - Construction of the Tokamak Complex Seismic Isolation Pit, Supply and Installation of Anti- Seismic Bearings – Contracts signed TB01 - Site Adaptation – Contract signed Initial Phase: TBAlpha – Galleries and drainage works – Contract signed TB02 – Long Lead – Mechanical Handling – Contract signed TB03 – Main Civil & Finishing – Contract signed TB04 – Main M&E/Services – Contract signed TB05 – D&B Package – Contract signed TB06 – HV Electrical Equipment – Contract signed TB07 – D&B Package – Contract signed TB08 – Site Infrastructure Works – Contract terminated TB16 – Site Infrastructure Works (re-launch of part of the TB08 scope) – Call For Tender in June 2015 Subsequent Phase: TB09 – Hot Cells – Civil – Procurement strategy under preparation TB10 – Hot Cells – M&E Handling – Procurement strategy under preparation TB11 – Completion Works – Planned in 2015 TB12 – Buildings 24, 34 and 37– Planned in 2015 TB13 – Electrical equipment and Buildings – Call for Expressions of Interest under evaluation Overview of the Procurement Packages
10
Industry information day 21.05.2015 SCHEDULE 10
11
Industry information day 21.05.2015 11 Buildings Ready for Equipment (RFE dates) Earliest RFE (B61, Q4 2016) latest RFE (Hot Cell Facilities, Q1 2022) RFE 1A, Apr 2017 RFE 1B, Feb 2018 RFE 1C, Jul 2019
12
Industry information day 21.05.2015 WORKSITE STATUS 12
13
Industry information day 21.05.2015 13 CURRENT STATUS OF ITER worksite
14
Industry information day 21.05.2015 Reminder: TB 03 – Civil works Scope of Supply: 295M€ Tokamak Complex (buildings 11, 14 & 74) Assembly Hall (13), Cleaning Facility (17), RF Heating (15) Cryoplant Compressor (51-52), Resistors (75), Site Services (61), Control Building (71) Works duration Number of workers 2014 to 2019 ~ 800 14 11 13 71 61 14 74 17 75 15 51 52
15
Industry information day 21.05.2015 TB03 – Work progress Concrete pouring of the walls on the first level (B2) of the Tokamak 15 B14 – Tritium Building : -Walls execution is progressing. -The reinforcement for the last external wall is already in place.
16
Industry information day 21.05.2015 16 TB03 – Work progress Pouring of the pillars of the Diagnostic Building (B74) completed Reinforcement work for the bio-shield ongoing Reinforcement of columns started. First external wall ready to be poured
17
Industry information day 21.05.2015 17 TB03 – Work progress Mock-up
18
Industry information day 21.05.2015 TB03 – Work progress Assembly building 18 Objective: Ready for crane rails installation : 20 October 2015 The steel frame of the Assembly Hall building is starting to take shape with the fourth level sections of the massive columns being erected in the east facade and west facade has started the erection of the 2 nd level. Preparatory works for the assembly of the roof on the floor are ongoing. The roof will be lifted in one piece once assembled.
19
Industry information day 21.05.2015 19 TB03 – Work progress B61 – Sites services Building Objective: Building Water tight: 16 October 2015 Backfilling on going Earthwork foundation pilling until June Slab : Summer 2015 Steel structure : Until October
20
Industry information day 21.05.2015 TB04 – Tokamak Complex / HVAC – 3D views Design progress
21
Industry information day 21.05.2015 WORKSITE STATUS IN 2017 21
22
Industry information day 21.05.2015 22 Worksite status in 2017
23
Industry information day 21.05.2015 Thank you for your attention 23