1 Contracts for Difference
Implementation Update 21st January 2015

2 Welcome, Agenda and Safety

3 Agenda CfD Round 1 Progress and Timeline CfD Allocation Overview
Sealed Bids Rules & Form Demo Applicant Processes (Submit & Withdrawals) CfD Contract Signing Process CfD Contract Management LCCC Key Contacts Q&A & Close 121 discussions

4 Contracts for Difference
Round 1 Progress and Timeline John Perkins CfD Manager

5 Round Variation / Budget Revision Notices
5. Appeal 6. Valuation 7. Sealed Bids 8. Allocation & Independent Audit 9. Allocation Notification 1. Pre-Application Activities 2. Application 3. Qualification 4. Review Applicants Request Review Request Appeal Apply Round Variation / Budget Revision Notices Assess Eligibility Qualified Applicants Review RO Check Appeal

6 Round Variation / Budget Revision Notices
5. Appeal 6. Valuation 7. Sealed Bids 8. Allocation & Independent Audit 9. Allocation Notification 1. Pre-Application Activities 2. Application 3. Qualification 4. Review Applicants Submit Sealed bids if requested Round Variation / Budget Revision Notices Value qualified applicants Request sealed bids if required Allocation & Independent Audit

7 Applicant Options in a Bid Window
Defaults to single bid as per original application if none submitted Note: Potential NDD policy impacts Submit Sealed Bids Ability to submit new sealed bids Default as above Withdraw Sealed Bids Note: Impact on Eligibility for Renewables Obligation Withdraw Application

8 Allocation Reports Review
5. Appeal 6. Valuation 7. Sealed Bids 8. Allocation & Independent Audit 9. Allocation Notification 1. Pre-Application Activities 2. Application 3. Qualification 4. Review Applicants Contract Signature Allocation Reports Review CfD Notification Appeals Register Issue Contracts CfD Register

9 LCCC prepare Contracts
Expected Key Dates Process Step Date DB Notice to SOS 20-Jan SOS Budget Review 21-27 Jan Auction Notice 28-Jan Sealed Bid Submission 29 Jan - 4 Feb Allocation 5-20 Feb SOS review 23 & 24 Feb CFD Notification 26 Feb LCCC prepare Contracts 27 Feb - 12 Mar Contract Signature 13-27 Mar

10 National Grid Contact Details
' Phone: (calls recorded on this number) * website:

11 Contracts for Difference
Allocation Rules Yasharn Smith EMR Delivery Manager

12 CfD – Competitive Allocation Principles
Used to identify Successful applicants and Strike Prices Sealed bid process (includes bidder flexibility) Each delivery year has a separate clearing price Triggered by breach of Budget Minimum allocated first Allocation in ascending price order (across years) Years can close independently

13 When is an Auction Required Illustration only
NO AUCTION REQUIRED

14 Maximum amounts consumers would be expected to fund in each year
Budget Notice £m 11/12 prices 15/16 16/17 17/18 18/19 19/20 20/21 Pot 1 (established) 50 65 Pot 2 (less established) 155 235 Pot 3 (biomass) Total 220 300 Maximum amounts consumers would be expected to fund in each year Conversion factor to translate budget to 2012 prices :

15 CfD Allocation – General Principles
Budget Rule Pot /Budget (Cannot Be Exceeded Except for Pending Projects) Constraint Only competitive where binding constraint (E.g. MIN capacity/Pot Budget) Across Years All projects in same Pot will compete on strike price basis, regardless of delivery year. Years can close independently Bids/ Prices Projects will be awarded in order of lowest to highest strike price Sealed bid process (includes bidder flexibility) Pay as Cleared Clearing Price set by most expensive successful project in each year (subject to cap at the Technology Admin Strike price).

16 CfD Allocation – Flexible Bids
Close Year Project SP Bid Del Yr MW A2 115 16/17 43 K1 113 18/19 700 G3 112 5 C2 108 17/18 28 A1 105 15/16 47 C1 38 D6 97 42 D1 94 80 H4 93 35 B2 92 50 F2 90 E1 88 63 B7 85 A2 K1 Close Year Tiebreak with A1 & C1 G3 C 2 A1 C1 Flexible Bids- Increasing Price A1 uses budget best in final year Reject all other bids for 16/17 Strike Price Bids Next cheapest bid is for same project Close Year D6 D1 Budget would be exceeded in 16/17 H4 B2 Bids are assessed in order of strike price bid (cheapest first) . If they fit the budget profile after clearing consideration, they are accepted. Same Commissioning Year Flexibility If a bid is successful, remove from stack all other bids relating to same project F2 E1 B7 15/16 16/17 17/18 18/19

17 CfD Allocations – Tiebreaker Rules
Tie-breaker rules applies where 2 or more projects with the same strike price bid, both cannot be awarded a CfD without exceeding budget limits Confirm projects with same S.P would exceed budget Assess all combination of tied projects which exceeds budget Choose combination of projects which best uses budget For further ties – Random number generator is to be used Consider other flex bids for unsuccessful projects Remove other flex bids for successful projects

18 Contracts for Difference
Sealed Bids Giampaolo Panizio EMR CfD - Commercial Analyst

19 Sealed Bids – Relevant Material
Sealed Bid Submission User Guide is available on the Delivery Body Portal

20 Sealed Bids Submission Rules
General Bids must be in 2012 prices (£/MWh) Withdraw & re-submit bids during submission window No bids accepted after window closes Relevant ASP is used if no bids are submitted Detail Submit combination of different bid price, capacity, TCW, & TCD No bids above the ASP Max 10 Bids per project No more than 3 bids for the same Delivery Year (DY) No two bids can have the same price Must be same DY or later than original application Must be same capacity or less than original application TCD must fall within the TCW Lowest price in each DY expressed to nearest whole pence (e.g. £100.01) All other bids (except for lowest in each DY) expressed to nearest 0.1 pence (i.e. £ ) Only 1 Sealed Bid can have the same first DY and capacity as original application For AD, Hydro, Onshore, Solar projects the bid capacity must be > 5 MW

21 Phased Projects’ Specific Rules
Detail Must include a single Strike Price to apply to all phases The total capacity of all phases must be no greater than 1500 MW The first phase must represent at least 25% of the total capacity of the CFD Unit after all phases are completed The first phase is targeted to complete by a date no later than 31st March 2019 The target commissioning date of the last phase is no later than 2 years after the date referred above

22 Sealed Bids Form Demo Original Applications’ Information:
Single Phased Project Technology: Onshore Wind Applicant name: Panizio Ltd Application ID: CFD-PNZO-01-01 Name of CFD Unit: Eolo Farm TCD: 15 July 2016 DY: 2016/2017 TCW start Date: 1 January 2016 TCW end Date: 31 December 2016 Capacity: MW ASP: £95 per MWh

23 Sealed Bids Submission Guidance
Guidance Notes Excel Macros must be enabled Do NOT manually hide or unhide rows Do NOT copy and paste data into cells Do NOT copy and paste the form in another excel file Do NOT rename the sealed bids form Validate Sealed Bids and save the form

24 Contracts for Difference
Applicant Processes Yasharn Smith EMR Delivery Manager

25 Sealed Bids Submission process
Auction Notice Published Pre-populated Sealed Bid Forms (Sent on - 16/12/14) Applicants Fill in Sealed Bid Forms Applicants Validate Form Send form to DB Withdraw Application/ Sealed Bids & Resubmit DB Uses Bids to Run Auction

26 Auction Notice Notice of Auction will be sent from the DB to:
Inform qualified applicants that the value/capacity (min) of a pot(s) has been exceeded and therefore a competitive allocation is required for that pot; Inform applicants of the dates for opening and closing sealed bids submission window Provide links to: to guidance on how to submit and fill a sealed bids form Sealed Bids withdrawal form Application withdrawal form

27 Application/ Sealed Bids Withdrawal
Applicants participating in an auction may Withdraw applications during the submission window; Withdraw and re-submit sealed bids during the submission window. The CfD sealed bids withdrawal form and the CfD application withdrawal form will be made available on the EMR DB Portal when an auction commences The DB has contingency processes in place to manage these processes and will communicate to applicants if required

28 Submission through Egress
Applicants must send filled in (validated) sealed bids form/withdrawal forms to the Delivery Body through Egress Switch: Applicant contact details required here DB will not accept Sealed Bid forms from unregistered person

29 Submission through Egress
Applicants must not change the file name of the pre-populated Sealed Bid form sent from the DB Upload file to be sent here Select CFD Sealed Bids on the [Type of Submission] drop down box; Click on the Add Files button; A file dialog box will appear which enables Users to select their files, upload Validated Sealed B Enter an alternative address if required for copies of submission to be shared

30 Preparing for Contract Signing and Next Steps
Nic Rigby Low Carbon Contracts Company IC Event 21 January 2015

31 Agenda Introduction Notification to Contract Signing
Initial Conditions Precedent and Beyond

32 Disclaimer Parties should rely upon the drafting of the relevant CFD Agreement and FiT CFD Standard Terms and Conditions in relation to the contract they enter into, not these slides Parties are recommended to obtain their own Legal advice. Once Allocation Results are announced Low Carbon Contracts Company will not be available for any discussions on contract interpretation.

33 Contract Management Tasks
Pre-Application Considering requests for minor and necessary amendments to generic CFDs before the potential applicant decides to apply for a CFD From Allocation to Start Date Execution: preparation of CFD and arranging execution satisfaction of Initial Conditions Precedent Milestone Satisfaction: Substantial Financial Commitment by Milestone Delivery Date. Start Date: satisfaction of Further Conditions Precedent and certification of Start Date. Post Start Date (when payment flows commence) Payment and settlement Reference Price review and Strike Price indexation Audit of metering and reporting Fuel monitoring and sampling compliance Today’s Agenda

34 What Does Success Look Like
Win the offer of a CfD Contract in the auction If you get past 1 then you must Sign a Contract by 27 March Meet Initial Conditions Precedent within 10 Business Days of signing the CfD Contract

35 Agenda Introduction Notification to Contract Signing
Initial Conditions Precedent and Beyond

36 The Contracts for Difference (Standard Terms) Regulations 2014
Offer to contract 10.—(1) An offer of a CFD is made by the CFD counterparty signing two copies of a CFD completed in accordance with regulation 9(3) and sending both copies to the eligible generator. (2) The CFD counterparty must make an offer of a CFD within 10 working days of receiving a CFD notification. (3) The eligible generator, to whom the offer of a CFD is made, enters into a CFD where— (a) the eligible generator signs both copies of a CFD and returns one copy to the CFD counterparty; and (b) the CFD counterparty gives the eligible generator a notice stating that the CFD counterparty has received a copy of the CFD from the eligible generator which has been signed by both contracting parties. (4) The CFD counterparty must give the notice under paragraph (3)(b) as soon as reasonably practicable after the CFD counterparty receives a signed copy of a CFD from an eligible generator. (5) Where a CFD is entered into, the CFD counterparty must inform the delivery body as soon as reasonably practicable. Failure to accept an offer 11.—(1) Where the CFD counterparty does not receive a signed copy of a CFD from an eligible generator within 10 working days of the offer being made, the offer lapses. (2) Where an offer lapses, the CFD counterparty must, as soon as is reasonably practicable, give the eligible generator and the delivery body a notice which states that the offer has lapsed.

37 End of Auction to Contract Signing
Action by Process Timing N Grid Provide Low Carbon Contracts Company (LCCC) with list of successful Applicants 26 February LCCC (Your allocated Contract Manager) Send data ex N Grid and draft contract to Applicants for checking LCCC Send 2 copies of Signed Contract to Applicants Within 10 Working Days (Regs) LCCC/ Applicants Signing day(s) Week beginning 23 March Applicant Return 1 signed copy of Contract to LCCC Working Day (Regs) = Weekdays – Bank Holidays in any part of the UK

38 In practice – Getting your contract signed
All parties allocated a CFD will get a dedicated Contract Manager Each Contract Manager covers all the projects that are operated by a Company or Group. Contract Managers already allocated to Investment Contract Generators. Contract mangers appointed as soon as we receive Auction results Nic Rigby Arezou Farhadi James Krzyszkowski Puk Lykke-Moller Stephanie Houston

39 In practice – first 10 working days
Low Carbon Contracts Company will write and set out exactly what you must do and by when in a “Key Dates Letter” Contract Managers appointed The LCCC have very limited time to check information provided by the generator in application to delivery body We can only change information that was not used as part of decision making process in allocation We will be able to change a postcode but not MW If we do not get a very rapid reply to any requests for confirmation of data - LCCC will have no choice but to send agreement with the information that we hold Please note allocation is not public knowledge at this point!

40 How the process works in more detail
WorkingDays (Regs) Counter Typical date Time Obligation Action Thur 26 Feb Before 5pm Process initiated N Grid provide data to Low Carbon Contracts Company 10, and initiates new counter 12 Mar Last date for Low Carbon Contracts Company to send out 2 signed copies of contract LCCC will e mail scanned copies via Egress and post paper copies. 10 Fri 27 Mar 5pm 1 copy of Contract must arrive at Fleetbank House Scanned via Egress e mail and/or deliver paper copies.

41 What you will receive The CFD agreement + Signature required at
The Conditions applicable to the CFD Agreement between the Parties are the terms and conditions set out in version 1 of the document published by the Department of Energy & Climate Change entitled “FiT Contract for Difference Standard Terms and Conditions” as at 29 August 2014 (as amended, modified, supplemented or replaced by the CfD Agreement and as may be amended, modified, supplemented or replaced from time to time in accordance with the Conditions). For the purposes of confirmation of this and identification, the Parties have signed this covering page to the Conditions. Signature required at - end of contract text, and - on this page to confirm 29 August version of Standard Terms and Conditions,

42 In practice – follow up The LCCC must notify generators of receipt of countersigned agreement LCCC must inform the delivery body of CFDs entered into LCCC will notify both generator and delivery body of any lapsed offers Parties that allow to lapse or terminate are subject to Non Delivery Disincentive For 13 Months no re-applications allowed

43 Agenda Introduction Notification to Contract Signing
Initial Conditions Precedent and Beyond

44 Initial Conditions Precedent
Meet Initial Conditions Precedent (Schedule 1) within 10 Business Days Legal opinion that Duly formed & power to enter contract Standard letter available on our web site Identification “Know your customer” checks Provide map of facility

45 Extreme Compass Co-ordinates
Extreme co-ordinates – WGS84 Latitude Longitude Northerly Easterly Southerly Westerly

46 Map Requirements To scale and scale provided
Four extreme compass co-ordinates must be shown in WGS84 format All boundaries must be shown All mayor parts of the facility (eg sub station, turbine locations must be shown, fuel storage)

47 Contract Management Approach
Each Company who wins a Contract has a dedicated Contract Manager Diverse experience of Contract Management and Industry experience Once allocation round results are announced Low Carbon Contracts Company will not be available for any discussions on contract interpretation. Trade Associations have lists of Legal Advisers Post Initial Conditions Precedent Low Carbon Contracts will provide Q & A (signposts) on Contract questions But will not provide Contract explanation Applicants need to access legal advice

48 Early preparation Check Egress works for all key parties
Send e mail to and we will reply via Egress. 2. If e mails re CfD Contract need to go to different or additional parties then please inform Low Carbon Contracts Company On Allocation Day when you receive “Key Dates Letter” including Invitation to Signing Ceremony. 3. Decide if you want to attend Signing Ceremony.

49 Fleetbank House E mail to let us know when you intend to deliver or with any queries. Please use Egress for all confidential e mails re Contracts Question and Answer document can be found at Visit our web site or contact the team for more information 49

50 Closing Remarks Low Carbon Contracts focus will be on getting everyone from offer of CfD to post Initial Conditions Precedent. Private law contract as offered on 29 August 2014 All parties expect to be treated equally Stretching the requirement can’t be done equitably So no allowances can be made Check your ability to meet Contract commitments, including Milestone Requirement. Be aware of impact of not signing, Non Delivery Disincentive. 50

51 Contracts for Difference
Closing Remarks and Questions John Perkins CfD Manager