Presentation is loading. Please wait.

Presentation is loading. Please wait.

GALENA WASTEWATER TREATMENT UPGRADES Informational Presentation for the Sassafras River Association Presented by Ryan J. Rangel, PE April 23, 2015.

Similar presentations


Presentation on theme: "GALENA WASTEWATER TREATMENT UPGRADES Informational Presentation for the Sassafras River Association Presented by Ryan J. Rangel, PE April 23, 2015."— Presentation transcript:

1 GALENA WASTEWATER TREATMENT UPGRADES Informational Presentation for the Sassafras River Association Presented by Ryan J. Rangel, PE April 23, 2015

2 Presentation Outline 1. Overall Project Timeline – (Already Partially Discussed by Mr. Felty) 2. Need for the Project 3. Initial Treatment Technologies Considered 4. MDE Becomes a Stakeholder 5. Final Treatment and Equipment Examples 6. Expected Benefit of New WWTP 7. Questions

3 Timeline Since McCrone’s Involvement (2012) June/July 2012 McCrone completes PER/ER for a County sewer system and upgrades to Town WWTP. December 2012 – Design contract signed and McCrone begins work. February 2013 – McCrone completes schematic design for 130,000 GPD April 2013 – Meet with MDE for SD review. MDE offers BRF money. June 2013 – MDE Planning allows for 110,000 GPD of capacity at new plant. Same time frame, proposed equip. is confirmed to meet BNR limits.

4 Timeline Since McCrone’s Involvement (2012) - Continued Late June 2013 – MDE requires denite filter replace cloth filter. Late August 2013 – McCrone submit revision to Schematic Design Report to address lower flow and how filter can be incorporated into design. Late February 2014 – MDE provides official comments to August submittal. May 2014 – McCrone submits additional information to MDE to address comments and add grit removal to the design. June 2014 – Full design continues after comment from MDE.

5 Timeline Since McCrone’s Involvement (2012) - Continued October 2014 – 90% Submittal of Construction Documents made to MDE December 2014 – MDE Comments on 90% Submittal March 2015 – 100% Submittal of construction documents made to MDE. April 2015 – Awaiting MDE comments. Should be shortly. Late May 2015 – Go to Bid Early October 2015 – Award contract and start construction. Early 2017 – Complete 15 month construction.

6 Need for the Project Existing WWTP

7 Need for the Project Existing WWTP

8 Need for the Project Existing WWTP - Auto-Enhanced Picture

9 Need for the Project Existing WWTP has trouble meeting current limits for Total Suspended Solids and Ammonia Current discharge limits at 60,000 GPD ◦ 30 mg/L BOD monthly avg. - 5,475 lbs/year ◦ 90 mg/L TSS monthly avg – 16,425 lbs/year ◦ 2.5 mg/L – 5.5 mg/L NH3 – No real TN Limit ◦ 10.7 mg/L Total Phos. – 2605 lbs/year

10 Need for the Project Town is under a consent order to design and construct a new facility. County has areas with failing septic systems that they wanted to address in the Georgetown area. Looked at other service areas while considering Georgetown. No current County wastewater collection system exists.

11 Georgetown Collection Area Lee Avenue Collection Area Maplewood Lane Collection Area Olivet Hill Collection Area Proposed County Collection System Areas Existing WWTP

12 Original Treatment Objectives Avg. Flow Rate (GPD) BOD5 (mg/L) TSS (mg/L) Total Phosphorus (lbs/year) Total Nitrogen (mg/L)pH Min. DO (mg/L) Max. E.Coli (MPN/100 mL) 130,00055 0.65 based on an annual cap of 256 lbs 3.88 based on an annual cap of 1538 lbs 6.5- 8.5 5.0126

13 Treatment Technologies Analyzed Sequencing Batch Reactor (SBR) Oxidation Ditch Membrane Bio Reactor (MBR) Did not review fourth (Moving Bed Bio Reactor - MBBR) because of lack of time from vendor

14 Treatment Technologies Analyzed Treatment Basics

15 Treatment Technologies – Project Costs Project costs for all technologies were within the level of accuracy for a typical study (10%). McCrone developed a set of subjective factors to evaluate the alternatives from a non- monetary perspective. The SBR is recommended based on essentially an equivalent cost and higher score on subjective factors.

16 Influent Screen Raw Wastewater Pump Station Valve Vault SBR Basins Post Eq Basin Tertiary Filtration UV Disinfection Post Aeration Plant Drain (All Structures and Buildings) Surface Discharge Wasted Solids Aerobic Digester Dewatering Equipment Solids to Landfill Air Chemical Addition Air Existing Lagoon Used as Emergency Overflow from All Process Structures To Influent Screen Overflow Return from Ex. Lagoon Legend Gravity Flow Pressure Flow Air Line Air Non- Potable Water System Process and Maintenanc e Uses Original Treatment Schematic

17 MDE Becomes a Stakeholder At schematic design review meeting with MDE, Bay Restoration Fund (BRF) money was offered if Town decreased limits to ENR levels. ENR Levels = 3.0 mg/L Total Nitrogen and 0.3 mg/L Total Phosphorus MDE also required additional treatment processes including grit removal and denitrification filter.

18 Influent Screen and Grit Removal Raw Wastewater Pump Station Valve Vault SBR Basins Post Eq Basin Denite Filter UV Disinfection Post Aeration Plant Drain (All Structures and Buildings) Surface Discharge Wasted Solids Aerobic Digester Dewatering Equipment Solids to Landfill Air Chemical Addition Air Existing Lagoon Used as Emergency Overflow from All Process Structures To Influent Screen Overflow Return from Ex. Lagoon Legend Gravity Flow Pressure Flow Air Line Air Non- Potable Water System Process and Maintenance Uses Revised Treatment Schematic Chemical Addition Chemical Addition Overflows From SBR, Post Eq and Digester

19 Examples of Pieces of Equipment Influent Screen - ¼” self cleaning screen to remove inorganics and protect equipment and downstream processes.

20 Examples of Pieces of Equipment Grit Removal – Remove non-organics from waste stream. Protects downstream components. Saves space in process tanks.

21 Examples of Pieces of Equipment Grit Classifier – Rinse organic matter from grit and concentrate grit from grit slurry.

22 Examples of Pieces of Equipment Influent Pump Station – Pump up onsite flows to the SBR process.

23 Examples of Pieces of Equipment Sequencing Batch Reactor – Main biological process to remove BOD and nutrients. One basin performs several operations.

24 Examples of Pieces of Equipment Sequencing Batch Reactor – Main biological process to remove BOD and nutrients. One basin performs several operations.

25 Examples of Pieces of Equipment Sequencing Batch Reactor – Main biological process to remove BOD and nutrients.

26 Examples of Pieces of Equipment Denitrification Filter – Sand filter that helps to polish off nitrogen and suspended solids.

27 Examples of Pieces of Equipment Denitrification Filter – Installation in Washington County. Similar unit as Galena’s.

28 Examples of Pieces of Equipment UV Disinfection – Use ultraviolent light to destroy or keep bacteria from regrowing.

29 Examples of Pieces of Equipment UV Disinfection – 254 nm wavelength. Install at Worton WWTP.

30 Examples of Pieces of Equipment Dewatering Unit – Press water from solids for lower hauling costs.

31 Impact of Upgrades

32 Questions


Download ppt "GALENA WASTEWATER TREATMENT UPGRADES Informational Presentation for the Sassafras River Association Presented by Ryan J. Rangel, PE April 23, 2015."

Similar presentations


Ads by Google