Presentation is loading. Please wait.

Presentation is loading. Please wait.

Geometric Design CEE 320 Steve Muench.

Similar presentations


Presentation on theme: "Geometric Design CEE 320 Steve Muench."— Presentation transcript:

1 Geometric Design CEE 320 Steve Muench

2 Outline Concepts Vertical Alignment Horizontal Alignment
Fundamentals Crest Vertical Curves Sag Vertical Curves Examples Horizontal Alignment Superelevation Other Non-Testable Stuff

3 Concepts Alignment is a 3D problem broken down into two 2D problems
Horizontal Alignment (plan view) Vertical Alignment (profile view) Stationing Along horizontal alignment 12+00 = 1,200 ft. Piilani Highway on Maui

4 Stationing Horizontal Alignment Vertical Alignment
Therefore, roads will almost always be a bit longer than their stationing because of the vertical alignment Draw in stationing on each of these curves and explain it

5 From Perteet Engineering
Typical set of road plans – one page only From Perteet Engineering

6 Vertical Alignment

7 Vertical Alignment Objective: Primary challenge
Determine elevation to ensure Proper drainage Acceptable level of safety Primary challenge Transition between two grades Vertical curves Sag Vertical Curve G1 G2 G1 G2 Crest Vertical Curve

8 Vertical Curve Fundamentals
Parabolic function Constant rate of change of slope Implies equal curve tangents y is the roadway elevation x stations (or feet) from the beginning of the curve

9 Vertical Curve Fundamentals
PVI G1 δ PVC G2 PVT L/2 L x Choose Either: G1, G2 in decimal form, L in feet G1, G2 in percent, L in stations

10 Relationships Choose Either: G1, G2 in decimal form, L in feet
G1, G2 in percent, L in stations Relationships

11 Example A 400 ft. equal tangent crest vertical curve has a PVC station of at 59 ft. elevation. The initial grade is 2.0 percent and the final grade is -4.5 percent. Determine the elevation and stationing of PVI, PVT, and the high point of the curve. PVI PVT G1=2.0% G2= - 4.5% PVC: STA EL 59 ft.

12 PVI G1=2.0% PVT G2= -4.5% PVC: STA 100+00 EL 59 ft.
400 ft. vertical curve, therefore: PVI is at STA and PVT is at STA Elevation of the PVI is 59’ (200) = 63 ft. Elevation of the PVT is 63’ – 0.045(200) = 54 ft. High point elevation requires figuring out the equation for a vertical curve At x = 0, y = c => c=59 ft. At x = 0, dY/dx = b = G1 = +2.0% a = (G2 – G1)/2L = (-4.5 – 2)/(2(4)) = y = x2 + 2x + 59 High point is where dy/dx = 0 dy/dx = x + 2 = 0 x = 1.23 stations Find elevation at x = 1.23 stations y = (1.23)2 + 2(1.23) + 59 y = ft

13 Other Properties G1, G2 in percent L in feet G1 x PVT PVC Y Ym G2 PVI
Yf Last slide we found x = 1.23 stations

14 Other Properties K-Value (defines vertical curvature)
The number of horizontal feet needed for a 1% change in slope G is in percent, x is in feet G is in decimal, x is in stations

15 Crest Vertical Curves For SSD < L For SSD > L SSD h2 h1 L
PVI Line of Sight PVC G1 PVT G2 h2 h1 L For SSD < L For SSD > L

16 Crest Vertical Curves Assumptions for design Simplified Equations
h1 = driver’s eye height = 3.5 ft. h2 = tail light height = 2.0 ft. Simplified Equations Minimum lengths are about 100 to 300 ft. Another way to get min length is 3 x (design speed in mph) For SSD < L For SSD > L

17 Crest Vertical Curves Assuming L > SSD…

18 Design Controls for Crest Vertical Curves
from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

19 Design Controls for Crest Vertical Curves
from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

20 Light Beam Distance (SSD)
Sag Vertical Curves Light Beam Distance (SSD) G1 headlight beam (diverging from LOS by β degrees) G2 PVC PVT h1 PVI h2=0 L For SSD < L For SSD > L

21 Sag Vertical Curves Assumptions for design Simplified Equations
h1 = headlight height = 2.0 ft. β = 1 degree Simplified Equations What can you do if you need a shorter sag vertical curve than calculated? Provide fixed-source street lighting Minimum lengths are about 100 to 300 ft. Another way to get min length is 3 x design speed in mph For SSD < L For SSD > L

22 Sag Vertical Curves Assuming L > SSD…

23 Design Controls for Sag Vertical Curves
from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

24 Design Controls for Sag Vertical Curves
from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

25 Example 1 A car is traveling at 30 mph in the country at night on a wet road through a 150 ft. long sag vertical curve. The entering grade is -2.4 percent and the exiting grade is 4.0 percent. A tree has fallen across the road at approximately the PVT. Assuming the driver cannot see the tree until it is lit by her headlights, is it reasonable to expect the driver to be able to stop before hitting the tree? Assume that S>L (it usually is not but for example we’ll do it this way), therefore S = ft. which is less than L Must use S<L equation, it’s a quadratic with roots of ft and ft. The driver will see the tree when it is feet in front of her. Available SSD is ft. Required SSD = (1.47 x 30)2/2(32.2)( ) + 2.5(1.47 x 30) = ft. Therefore, she’s not going to stop in time. OR L/A = K = 150/6.4 = 23.43, which is less than the required K of 37 for a 30 mph design speed Stopping sight distance on level ground at 30 mph is approximately 200 ft.

26 Example 2 Similar to Example 1 but for a crest curve.
A car is traveling at 30 mph in the country at night on a wet road through a 150 ft. long crest vertical curve. The entering grade is 3.0 percent and the exiting grade is -3.4 percent. A tree has fallen across the road at approximately the PVT. Is it reasonable to expect the driver to be able to stop before hitting the tree? Assume that S>L (it usually is), therefore SSD = ft. which is greater than L The driver will see the tree when it is feet in front of her. Available SSD = ft. Required SSD = (1.47 x 30)2/2(32.2)( ) + 2.5(1.47 x 30) = ft. Therefore, she will be able to stop in time. OR L/A = K = 150/6.4 = 23.43, which is greater than the required K of 19 for a 30 mph design speed on a crest vertical curve Stopping sight distance on level ground at 30 mph is approximately 200 ft.

27 Example 3 A roadway is being designed using a 45 mph design speed. One section of the roadway must go up and over a small hill with an entering grade of 3.2 percent and an exiting grade of -2.0 percent. How long must the vertical curve be? For 45 mph we get K=61, therefore L = KA = (61)(5.2) = ft.

28 Trinity Road between Sonoma and Napa valleys
Horizontal Alignment

29 Horizontal Alignment Objective: Primary challenge Fundamentals
Geometry of directional transition to ensure: Safety Comfort Primary challenge Transition between two directions Horizontal curves Fundamentals Circular curves Superelevation Δ

30 Horizontal Curve Fundamentals
PI T Δ E M L PC Δ/2 PT D = degree of curvature (angle subtended by a 100’ arc) R R Δ/2 Δ/2

31 Horizontal Curve Fundamentals
PI T Δ E M L PC Δ/2 PT R R Δ/2 Δ/2

32 Example 4 A horizontal curve is designed with a 1500 ft. radius. The tangent length is 400 ft. and the PT station is What are the PI and PT stations? Since we know R and T we can use T = Rtan(delta/2) to get delta = degrees D = /R. Therefore D = 3.82 L = 100(delta)/D = 100(29.86)/3.82 = 781 ft. PC = PT – PI = 2000 – 781 = PI = PC +T = = Note: cannot find PI by subtracting T from PT!

33 Superelevation Rv Fc α Fcn Fcp α e W 1 ft Wn Ff Wp Ff α

34 Superelevation Divide both sides by Wcos(α)
Assume fse is small and can be neglected – it is the normal component of centripetal acceleration

35 Selection of e and fs Practical limits on superelevation (e)
Climate Constructability Adjacent land use Side friction factor (fs) variations Vehicle speed Pavement texture Tire condition The maximum side friction factor is the point at which the tires begin to skid Design values of fs are chosen somewhat below this maximum value so there is a margin of safety

36 Side Friction Factor New Graph
from AASHTO’s A Policy on Geometric Design of Highways and Streets 2004

37 New Table Minimum Radius Tables

38 WSDOT Design Side Friction Factors
New Table WSDOT Design Side Friction Factors For Open Highways and Ramps from the 2005 WSDOT Design Manual, M 22-01

39 WSDOT Design Side Friction Factors
New Graph WSDOT Design Side Friction Factors For Low-Speed Urban Managed Access Highways from the 2005 WSDOT Design Manual, M 22-01

40 Design Superelevation Rates - AASHTO
New Graph Design Superelevation Rates - AASHTO There is a different curve for each superelevation rate, this one is for 8% from AASHTO’s A Policy on Geometric Design of Highways and Streets 2004

41 Design Superelevation Rates - WSDOT
New Graph Design Superelevation Rates - WSDOT emax = 8% from the 2005 WSDOT Design Manual, M 22-01

42 Example 5 A section of SR 522 is being designed as a high-speed divided highway. The design speed is 70 mph. Using WSDOT standards, what is the minimum curve radius (as measured to the traveled vehicle path) for safe vehicle operation? For the minimum curve radius we want the maximum superelevation rate. WSDOT max e = 0.10 For 70 mph, WSDOT f = 0.10 Rv = V2/g(fs+e) = (70 x 1.47)2/32.2( ) = ft. This is the radius to the center of the inside lane. Depending upon the number of lanes and perhaps a center divider, the actual centerline radius will be different.

43 Stopping Sight Distance
SSD Ms Obstruction Basically it’s figuring out L and M from the normal equations Rv Δs

44 Supplemental Stuff Cross section Superelevation Transition
FYI – NOT TESTABLE Supplemental Stuff Cross section Superelevation Transition Runoff Tangent runout Spiral curves Extra width for curves

45 FYI – NOT TESTABLE Cross Section

46 Superelevation Transition
FYI – NOT TESTABLE Superelevation Transition from the 2001 Caltrans Highway Design Manual

47 Superelevation Transition
FYI – NOT TESTABLE Superelevation Transition Can also rotate about inside/outside axis from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

48 Superelevation Runoff/Runout
FYI – NOT TESTABLE Superelevation Runoff/Runout from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

49 Superelevation Runoff - WSDOT
FYI – NOT TESTABLE New Graph Superelevation Runoff - WSDOT from the 2005 WSDOT Design Manual, M 22-01

50 Spiral Curves FYI – NOT TESTABLE No Spiral Spiral
Ease driver into the curve Think of how the steering wheel works, it’s a change from zero angle to the angle of the turn in a finite amount of time This can result in lane wander Often make lanes bigger in turns to accommodate for this Spiral from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

51 FYI – NOT TESTABLE No Spiral I-90 past North Bend looking east

52 Spiral Curves WSDOT no longer uses spiral curves
FYI – NOT TESTABLE Spiral Curves WSDOT no longer uses spiral curves Involve complex geometry Require more surveying Are somewhat empirical If used, superelevation transition should occur entirely within spiral

53 Desirable Spiral Lengths
FYI – NOT TESTABLE Desirable Spiral Lengths from AASHTO’s A Policy on Geometric Design of Highways and Streets 2001

54 Operating vs. Design Speed
FYI – NOT TESTABLE Operating vs. Design Speed 85th Percentile Speed vs. Inferred Design Speed for 138 Rural Two-Lane Highway Horizontal Curves According to NCHRP Report 85th Percentile Speed vs. Inferred Design Speed for Rural Two-Lane Highway Limited Sight Distance Crest Vertical Curves

55 Primary References Mannering, F.L.; Kilareski, W.P. and Washburn, S.S. (2005). Principles of Highway Engineering and Traffic Analysis, Third Edition. Chapter 3 American Association of State Highway and Transportation Officials (AASHTO). (2001). A Policy on Geometric Design of Highways and Streets, Fourth Edition. Washington, D.C.


Download ppt "Geometric Design CEE 320 Steve Muench."

Similar presentations


Ads by Google