Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Similar presentations


Presentation on theme: "Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors."— Presentation transcript:

1 Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors Authority Presented by Susan Martinovich

2 Improvements to I-15 from Tropicana Ave. to South of Blue Diamond Rd., including:  Widening I-15  Addition of Collector Distributor roads  Improved ramps at interchanges  Tropicana Avenue  Russell Road  I-215  Blue Diamond Road  Silverado Ranch Blvd What is the I-15 South Design-Build Project ?

3 Improvements to I-15 from Tropicana Ave. to south of Blue Diamond Rd., including:  New bridges over I-15 at Warm Springs Road and Sunset Road  Landscaping and Aesthetics  Intelligent Transportation System  Ramp Meters  Variable Message Signs  Cameras What is the I-15 South Design-Build Project?

4 I-15 South Design-Build Project Blue Diamond Rd. Silverado Ranch Blvd. Russell Rd. 215 Tropicana Ave.

5 Design-Build Lump Sum Contact $246,500,000 Prelim. Engr. (includes procurement) $16,000,000 Construction Engineering $17,000,000 Incentives, Escalations, and Utilities $6,000,000 Project Costs

6 Notice to Proceed – September 2009 Design substantially completed – Fall 2010 Construction began – December 2009 All I-15 Lanes completed and open - March 2012 Project Completion – Spring 2012 Schedule

7 Design - 95% complete Construction - 48 % complete Project Status

8 Budget/Cash Flow

9 Currently 300+/- working on design and construction Peak employment estimated at 400+/- Employment

10 Southbound I-15 auxiliary lane and 2-lane off ramp to Silverado Ranch Road - Open Northbound I-15 Auxiliary lane from Silverado Ranch - Open Sunset Bridge - Under Construction I-15/I-215 interchange - Under Construction C-D Roads and bridges - Under Construction Russell Road (widening) - Under Construction Construction to Date

11 Upcoming Milestones Sunset Bridge Open January 13 Warm Springs Bridge To be demolished Feb 2011 To re-open as 6-lane bridge Spring 2012 I-15/ I-215 Construction To be complete Feb 2012 Russell Road Widening To be complete Aug 2011


Download ppt "Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors."