3 June 2008 1 Rapid Replacement of the Hood Canal Bridge Approach Spans Joseph Merth, P.E. Bridge Design Engineer 3 June 2008
2
2 Overview Introduction Current Project Approach Design Approach Construction Challenges West Approach East Approach Floating Structure
3
3 June 2008 3 Location Olympic Peninsula Seattle Hood Canal Bridge Puget Sound
4
3 June 2008 4 Location The Hood Canal Bridge provides the vital transportation link between the northeast Olympic Peninsula and Kitsap, King, Pierce and Snohomish counties Hood Canal Bridge Hood Canal
5
3 June 2008 5
6
6 Hood Canal Bridge
7
3 June 2008 7 Hood Canal Bridge
8
3 June 2008 8 West Half Floating Structure East Half Floating Structure Draw Span East Approach West Approach Transition Span Transition Span
9
3 June 2008 9 Bridge Facts Length – 7869 feet (Longest floating bridge over salt water) Floating portion – 6530 feet Max water depth – 340 feet Tidal Variation – 16.5 feet Center draw span opening – 600 feet
10
3 June 2008 10 Bridge History Original Construction – January 1958 Open to traffic – 12 August 1961
11
3 June 2008 11 West Half Fails February 13, 1979 Sustained winds of 85mph 120mph gusts
12
3 June 2008 12 West Half Replacement Reopened Oct. 25 th, 1982 Post-tensioned pontoons Increased anchor size
13
3 June 2008 13 Current Project Replace Approaches (completed) Replace Transition Spans Replace East Half Pontoons (6 to 8 wk. closure) Widen West Half Superstructure From 28’ to 40’ (completed)
14
3 June 2008 14 Approaches Provide fixed link from shore to floating structure Help resist longitudinal wind and wave forces from the floating structure Wind/Wave Forces Floating Structure Approach Spans Transition Span Tidal Movement
15
3 June 2008 15 Original West Approach 2 – span haunched steel PL Girder 190’ length Buttress added for West half replacement Buttress
16
3 June 2008 16 Original East Approach 6 – span haunched steel PL Girder 643’ length Wind/Wave forces – Pier 4 Pier 4
17
3 June 2008 17 Approach Retrofit Original Retrofit Requirement Deck Replacement Seismic Retrofit Pier 4 retrofit (add buttress wall) Required 6-8 week closure WestEast
18
3 June 2008 18 Approach Replacement Replace entire approaches (superstructure/substructure) Build to current standards – 40’ roadway, seismic Ability to widen to 4 lanes (60’) in the future
19
3 June 2008 19 Typical Section 6’ Dia. Column 10’ Dia. Shaft 40’ Roadway Prestressed Girder
20
3 June 2008 20 West Approach Elevation 1 span (W83G Girders) 154’ total length CL Pier 1 CL Pier 2 154’
21
3 June 2008 21 East Approach Elevation 609’ CL Pier 5CL Pier 6CL Pier 7 CL Pier 8CL Pier 9 Pier 10 5 spans (W74G Girders) 609’ total length
22
3 June 2008 22 Replacement Challenges Limited closure – extended weekend Construct superstructure adjacent to existing approach Distribute wind/wave forces into East Approach
23
3 June 2008 23 Rolling Scheme
24
3 June 2008 24 Rolling Scheme Prior to Rollover
25
3 June 2008 25 Rolling Scheme Prior to Rollover
26
3 June 2008 26 Rolling Scheme Prior to Rollover
27
3 June 2008 27 Rolling Scheme Prior to Rollover
28
3 June 2008 28 Rolling Scheme During Rollover
29
3 June 2008 29 Rolling Scheme During Rollover
30
3 June 2008 30 Rolling Scheme During Rollover
31
3 June 2008 31 Rolling Scheme During Rollover
32
3 June 2008 32 Rolling Scheme During Rollover
33
3 June 2008 33 Rolling Scheme After Rollover
34
3 June 2008 34 Rolling Scheme After Rollover
35
3 June 2008 35 Rolling Scheme After Rollover
36
3 June 2008 36 Wind/Wave Forces
37
3 June 2008 37 Hinge Diaphragm
38
3 June 2008 38 Hinge Diaphragm
39
3 June 2008 39 Hinge Diaphragm
40
3 June 2008 40 Hinge Diaphragm
41
3 June 2008 41 Hinge Diaphragm
42
3 June 2008 42 Hinge Diaphragm Longitudinal Stop Longitudinal Bearing
43
3 June 2008 43 Hilman Roller Rolling Assembly A A Section A-A Rolling Plate Hilman Roller Temp. Elast. Brg.
44
3 June 2008 44 Hilman Rollers 5 spans 800 to 1500 kips DL/Pier 7600 kips Total 2 Hilman rollers/span (300 or 500 ton capacity) East Approach 1 span 1000 kip DL/Pier 2000 kips Total 2 Hilman rollers/span (300 ton capacity) West Approach
45
3 June 2008 45 Construction
46
3 June 2008 46 Work Trestle Trestle and Falsework scheme included in Contract Contractor required to submit for review and approval Falsework system designed for ½ seismic acceleration (0.15g)
47
3 June 2008 47 Work Trestle 58,000 ft 2 260 – 2’ Diameter Piles 4 months to construct East Approach
48
3 June 2008 48 Substructure 12 – 10’ Diameter Shafts 5 ½ Months Construction Epoxy Coated Rebar – Entire Structure East Approach
49
3 June 2008 49 Superstructure
50
3 June 2008 50 Hydraulic Jacking – Horizontal West Approach – 2 synchronized jacks East Approach – 6 synchronized jacks Max horizontal force/jack – 30 to 80 kips Max ¼” differential horizontal movement between adjacent piers during rolling New Bridge - Original Position New Bridge - After Rollover
51
3 June 2008 51 Hydraulic Jacking – Horizontal Rolling Plate Jacking Rod
52
3 June 2008 52 The Rollover
53
3 June 2008 53 Hydraulic Jacking – Vertical
54
3 June 2008 54 Hydraulic Jacking – Vertical
55
3 June 2008 55 Hydraulic Jacking – Vertical
56
3 June 2008 56 Hydraulic Jacking – Vertical
57
3 June 2008 57 Hydraulic Jacking – Vertical Rolling Plate
58
3 June 2008 58 Hydraulic Jacking – Vertical Jacking performed pier by pier 10 synchronized jacks interior piers, 5 at end piers Max relative differential movement between jacks = ¼” Max relative differential movement between piers = 2” Pressure system used for vertical jacking
59
3 June 2008 59 East Approach Aerial Photos Before During After
60
3 June 2008 60 Approach Closure Schedule West Approach Thursday (11 Aug 05) Friday (12 Aug 05) Saturday (13 Aug 05) 8:00PM Close Bridge 4:00AM Exist. Bridge Rolled 6:00PM New Bridge Rolled 10:20PM Bridge Opened to Traffic East Approach Sunday (21 Aug 05) Monday (22 Aug 05) Tuesday (23 Aug 05) 8:00PM Close Bridge 4:00PM Exist. Bridge Rolled 12:00AM New Bridge Rolled 8:40PM Bridge Opened to Traffic 51 hrs 49 hrs
61
3 June 2008 61 Closure Challenges
62
3 June 2008 62 Abutment and Approach Slabs Precast Abutment Endwall Precast Approach Slabs
63
3 June 2008 63 Abutments
64
3 June 2008 64 Abutments Crossbeam
65
3 June 2008 65 Abutments Cast-in-place Endwall
66
3 June 2008 66 Abutments
67
3 June 2008 67 Abutments Precast Endwall
68
3 June 2008 68 Abutments
69
3 June 2008 69 Precast Approach Slab Abutments
70
3 June 2008 70 Precast Abutment Endwall Construction Cast-in-Place EndwallPrecast Endwall Cast-in-place Endwall Precast Endwall
71
3 June 2008 71 Precast Abutment Endwall Construction Precast Backwall Backfill Voids
72
3 June 2008 72 Precast Approach Slab 6 Sections 25’ x 8’ x 1’-1”
73
3 June 2008 73 Expansion Joints
74
3 June 2008 74 750 kips Lessons Learned Unequal Bearing Loads
75
3 June 2008 75 Lessons Learned Unequal Bearing Loads
76
3 June 2008 76 Lessons Learned Unequal Bearing Loads
77
3 June 2008 77 Lessons Learned Unequal Bearing Loads
78
3 June 2008 78 Lessons Learned Unequal Bearing Loads 300 kips/bearing Design Load.
79
3 June 2008 79 Lessons Learned Unequal Bearing Loads
80
3 June 2008 80 Lessons Learned Unequal Bearing Loads Jacking and shimming required Prior to Shimming After Shimming Design DL = 300 kips Estimated DL = 500 kips
81
3 June 2008 81