MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA.

Similar presentations


Presentation on theme: "MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA."— Presentation transcript:

1 MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA Gary Jakovich, FHWA Jon Nekritz, FHWA Phil Grotenhuis, MDOT Matt Chynoweth, MDOT Terry Lavoy, MDOT Wesley King, MDOT

2 Shallow Structure Types Channel Bridge Cable-Stayed Bridge with slab superstructure Tied-Arch Bridge with slab superstructure “Conventional beam bridge with integral supports” Segmental voided slab

3

4

5

6 Pre-fabrication Segmental Concrete Superstructure Pre-cast piers Pre-cast abutments Pre-cast deck panels Pre-cast bridge barrier Temporary Bridges Bailey/Acrow

7

8

9

10 High Performance Materials Polymer Asphalt High Performance concrete High Performance steel Self-Consolidating Concrete High Strength Concrete Initial Overlays

11

12

13 Retaining Walls Remove retaining walls, purchase additional Right of Way (ROW), Lay slope back at 3:1 Soldier Pile, Soil Nailed or Secant Walls

14 Service Drive Expansion Near Wayne State University (WSU) parking garage expand service drive over slope.

15 Foundations for Interchanges Single/mono shaft Large diameter closed in steel pipe pile Post grouted shaft

16 Railway Crossings Construct temporary railroad bridges as necessary Diverge rail traffic onto one bridge in areas with multiple tracks Roll in pre-fabricated bridge over short closure period Edge girder floor beam system

17 Interchange Construction Staging Build new ramps before eliminating movements Construction Planner Manage sequence of construction for whole interchange Ramp Bridges Segmental Box Steel Box/Plate Temporary Structures to move traffic

18

19 Advanced Contracting Identify bridges for early construction/replacement due to poor condition Advanced relocation of utilities Design to Minimize Future Maintenance Eliminating expansion joints, design for continuity Minimize number of bearings

20 Erection Methods Self Propelled Modular Transport (SPMT) Roll In High capacity cranes Erection Gantry

21


Download ppt "MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA."