Regional Planning Meetings 2005 Planning and Engineering Overview Presented by Vivek Khanna, Airport Engineer.

Similar presentations


Presentation on theme: "Regional Planning Meetings 2005 Planning and Engineering Overview Presented by Vivek Khanna, Airport Engineer."— Presentation transcript:

1 Regional Planning Meetings 2005 Planning and Engineering Overview Presented by Vivek Khanna, Airport Engineer

2 Airport Information Management System Features Airport Guide Airport Guide Capital Improvement Program Capital Improvement Program Administrative Codes Administrative Codes Airport Development Worksheets Airport Development Worksheets Pavement Management Pavement Management System Plan System Plan Consultants contact list Consultants contact list Online at http://www.aeronautics.ok.gov

3 Airport Guide Page Online at : http://www.aeronautics.ok.gov

4 Pavement Management Program 33% of pavement requiring only routine maintenance 33% of pavement requiring only routine maintenance 67% of pavement requiring more significant rehabilitation 67% of pavement requiring more significant rehabilitation As time passes more pavement will require significant rehabilitation As time passes more pavement will require significant rehabilitation Inventory Data for 81 Oklahoma Airports 2005 2010

5 Airport Information Construction history Construction history Pavement type Pavement type Pavement thickness Pavement thickness General geotechnical information General geotechnical information Pavement Condition Pavement Condition

6 Cost-Effective Pavement Maintenance $1.00 Rehab here 75 % of Pavement Life 12 % of Pavement Life 40% Drop In Quality 40% Drop In Quality $4.00 to $5.00 here Pavement Condition Pavement Age

7 Airport Development Worksheets On-line at: http://www.aeronautics.ok.gov Goal: Present a Long-range development plan Goal: Present a Long-range development plan Include all UNCONSTRAINED AIP ELIGIBLE needs Include all UNCONSTRAINED AIP ELIGIBLE needs Planning-Level Estimates Planning-Level Estimates Compatible with FAA Compatible with FAA Framework: Framework: Airport Deficiencies Airport Deficiencies Short term – 0 to 5 yr Short term – 0 to 5 yr NPE NPE CIPs – Airport, OAC CIPs – Airport, OAC 6-10 and 11 -20 year needs 6-10 and 11 -20 year needs The first step in a disciplined Capital Plan! The first step in a disciplined Capital Plan!

8 ADWS Updates Two-year cycle Two-year cycle 75 sponsors responded 75 sponsors responded Cover letter of Interest Cover letter of Interest Signed by Sponsor‘s authorized representative Signed by Sponsor‘s authorized representative Project Data-sheet Project Data-sheet Identify the ODO and project scope Identify the ODO and project scope Justify project Justify project Project sketch Project sketch Planning cost-estimate Planning cost-estimate

9 FAA’s NPIAS Needs Update 2005 FAA will use Commission’s 0-5yr ADWS database FAA will use Commission’s 0-5yr ADWS database Update the NPIAS needs Update the NPIAS needs Electronically upload the 0-5yr ADWS into FAA’s database Electronically upload the 0-5yr ADWS into FAA’s database Reported to Congress Reported to Congress 20% of total 0-5yr ADWS - annual NPE 20% of total 0-5yr ADWS - annual NPE Important not to under identify airport’s needs! Important not to under identify airport’s needs!

10 Typical Projects Pavement Maintenance Pavement Maintenance Navigational aids Navigational aids AWOS AWOS Land acquisition Land acquisition Pavement rehabilitation, widening or extension Pavement rehabilitation, widening or extension Efficient Drainage Efficient Drainage Action Plans and ALPs Action Plans and ALPs


Download ppt "Regional Planning Meetings 2005 Planning and Engineering Overview Presented by Vivek Khanna, Airport Engineer."