Presentation is loading. Please wait.

Presentation is loading. Please wait.

Modeling Generation Capacity Investment Decisions

Similar presentations


Presentation on theme: "Modeling Generation Capacity Investment Decisions"— Presentation transcript:

1 Modeling Generation Capacity Investment Decisions
GridSchool 2010 March 8-12, 2010  Richmond, Virginia Institute of Public Utilities Argonne National Laboratory Vladimir Koritarov Center for Energy, Economic, and Environmental Systems Analysis Decision and Information Sciences Division ARGONNE NATIONAL LABORATORY Do not cite or distribute without permission MICHIGAN STATE UNIVERSITY

2 Resource Planning Methodologies
Screening Curves A comparison of annualized costs of different generating technologies across a range of capacity factors Deterministic Optimization Models: Optimization models using linear programming (LP) and/or mixed-integer programming (MIP) Representative models: MARKAL, MESSAGE, etc. Dynamic Programming Optimization Models: Typically include a detailed dispatch model and a dynamic programming (DP) model Provide a rigorous capacity expansion solution by examining thousands of possible future expansion paths Representative models: WASP, EGEAS, etc. New Methods for Deregulated electricity markets (e.g., Agent-Based Modeling): Applicable in competitive electricity markets Simulate independent decision-making of market participants May not provide least-cost solution for the system as a whole

3 Characteristics of Main Resource Planning Methodologies
Approach Pros Cons Screening Curves Quick and simple analysis Identifies clear winners and losers Does not consider power system characteristics No dispatch analysis No reliability analysis Deterministic Optimization Models Fast solution (single iteration) Require less input data than DP models Computationally intensive for detailed representation of real power systems (large number of variables and equations) Dispatch model rather simple (usually annual or multi-annual time step) Inaccurate reliability analysis Dynamic Programming Rigorous solution Detailed dispatch analysis Accurate reliability analysis Can be computationally intensive (iterative optimization process) Require large amount of input data

4 Screening Curves Provide a Simplified Approach for Quick Analysis of Economic Competitiveness
Separate technology costs into “fixed” and “variable” costs Construct cost curves for each technology Plot cost ($/kW-yr) vs. capacity factor Determine least-cost alternatives as a function of utilization Numerous limitations Not a substitute for a thorough analysis 2 2

5 Total Annualized Cost Includes Fixed and Variable Components
($/kW-yr) = × + Variable ($/kWh) Fixed Capacity Factor (fraction) 8760 (h/yr) Annualized Cost Variable Cost ($ / kW-yr) Fixed Cost Capacity Factor

6 Screening Curves Show Ranges of Competitiveness for each Technology

7 The Competitiveness of Certain Technologies is Sensitive to the Choice of Discount Rate

8 Fixed and Variable Cost
Lowest Cost Options Can be Projected onto a LDC to Obtain an Estimate of Supply Mix Fixed and Variable Cost Total Annualized ($ / kW-yr) Capacity Factor Coal (600 MW) 200 Nuclear (1000 MW) Gas (50 MW) .0635 .4866 Time (fraction) Normalized Load (fraction) Nuclear (.6362) Coal (.2327) Gas Turbine (.1311) .8689 1.0 .6362

9 The Screening Curve Approach Does Not Consider Many Important Factors in System Planning
Screening curves do NOT consider: Unit availability (forced outage and maintenance) Existing capacity Unit dispatch factors (minimum load and spinning reserve) System reliability Dynamic factors changing over time (load growth and economic trends) Etc. 11 11

10 Deterministic Optimization Models
Relatively simple, easy to understand approach The solution is obtained fast, in a single model run The input data requirements are lower than for the dynamic programming optimization models Can be computationally intensive if applied to real power systems (large number of variables and constraint equations require powerful solvers) Dispatch model is rather simple, usually on an annual basis. Some models use 2 or even 5-year time step. Numerous limitations in modeling system operation (e.g., no planned maintenance schedule) Inadequate reliability analysis (typically planning reserve margins and energy-not- served (ENS) are calculated). The ENS calculation is inaccurate due to simplified dispatch The optimal solution may not be feasible or realistic The LP solution does not consider discrete unit sizes (not all models have MIP capabilities)

11 Many Deterministic Models Analyze Energy Flows from Primary Resources to Demand
Energy Reserves/ Resources Example: Oil, natural gas, or coal reserves (billion tons) Primary Energy Production Crude oil production (bbls/day) Secondary Energy Production Power plant electricity production (MWh) Final Energy Demand Electricity delivered to customers Useful Energy Demand Lighting, heating, cooling, motive power

12 The Energy Flows Are Typically Represented as Network
Final Energy Demand Transmission & Distribution Secondary Energy Production Primary Energy Production

13 The Level of Detail Depends on the Characteristics of the Power System and Availability of Data

14 The Results Show Optimal Generation Mix to Meet the Demand

15 Dynamic Programming Optimization Models
Most suitable tools for resource planning since long-term capacity expansion problem is a highly constrained non-linear discrete dynamic optimization problem. Computationally very intensive since every possible combination of candidate options must be examined to get the optimal plan (Curse of Dimensionality). A new class of stochastic dynamic programming optimization models introduces uncertainty into the resource planning. These may include uncertainties in demand growth, hydro inflows and generation, fuel prices, wind and solar generation, electricity prices, etc. For example, WASP model incorporates the uncertainties of hydro generation, however other uncertainties (demand growth, fuel prices, etc.) are modeled through scenario analysis or sensitivity studies. Some models also try to include risk and calculate net present value (NPV) for different risk levels.

16 Dynamic Programming Optimization Models
OBJECTIVE: Identify the generating system expansion plan which has the minimum net present value (NPV) of all operating and investment costs for the study period. Demand forecast Years MW Upper RM Lower RM System Capacity Existing System Capacity New Capacity Additions

17 General Structure of Dynamic Programming Optimization Models
DP capacity expansion models typically combine a production cost (dispatch) model and a DP optimization model The production cost model simulates the operation of the power system for each identified state (system configuration) in each year of the study period The DP model finds the expansion path with the minimum NPV of all investment and operating costs that meets the demand and satisfies all reliability and other constraints Inputs: Demand forecast Load profiles Existing units Candidate technologies Economic data Reliability parameters and constraints Environmental data and constraints Results: NPV of investment and operating costs Timing and schedule of new capacity additions Operating costs by period Investment costs by year (cash flow) Reliability results Environmental emissions Production Cost Model Dynamic Programming Model

18 DP Expansion Models Typically Have Modular Structure
Module 1 LOADSY Load Description Module 2 FIXSYS Fixed System Description Module 3 VARSYS Candidates Description Module 4 CONGEN Configuration Generator Module 5 MERSIM Simulation of System Operation Module 6 DYNPRO Optimization of Investments Module 7 REPROBAT Report Writer IAEA’s WASP Model

19 Production Cost Model Simulates the Operation of the System
PURPOSE: To simulate the operation of electric power system so that operating costs and reliability of system operation can be calculated. Simulates all system configurations (states) identified by the model in all years Minimizes variable operating costs for the system (fuel costs + variable O&M) in each time period Either chronological hourly loads or load duration curves (LDC) are used to represent system loads in each time period Determines the maintenance schedule of generating units Uses loading order to represent dispatch of generating units: Economic loading order User-specified loading order Combination (e.g., to accommodate must run units) (Loading order can be adjusted to satisfy spinning reserve and other requirements) Uses probability mathematics to represent forced outages of generating units: Monte Carlo approach is typically applied if hourly loads are used in simulation Baleriaux-Booth (equivalent LDC) method is applied if LDCs are used

20 Baleriaux-Booth Method Considers Forced Outages Probabilities of Generating Units in Combination with System Load The capacity on forced outage is treated as additional load that must be served by other generating units Equivalent load duration curve (ELDC) is constructed using a convolution process to take into account forced outages of all generating units Reliability parameters Loss-of-Load Probability (LOLP) and Energy-not-Served (ENS) are determined based on the remaining area under the ELDC Time Capacity ELDC Original LDC LOLP Convolution process ENS Total capacity Peak load 1

21 Production Cost Model Provides Inputs for DP Optimization
Calculates the expected energy generation by each generating unit in each time period Calculates operating costs for each generating unit on the basis of expected energy generation in each time period Calculates total operating costs for the system in each time period Calculates system reliability parameters such as LOLP and ENS

22 Reliability Constraints Must Be Met for a Configuration to Be Considered for the Expansion Path
Demand forecast (D) Years MW (1+A)×D (1+B)×D System Capacity where: At = Maximum reserve margin Bt = Minimum reserve margin Dt = Peak demand (in the critical period) P(Kt) = Installed capacity in year t Kt = System configuration in year t Ct = Critical LOLP (loss-of-load probability) Reliability constraints: (1+At) x Dt > P(Kt) > (1+Bt) x Dt LOLP(Kt) < Ct

23 DP Optimization Minimizes the Objective Function
The objective function B typically comprises several cost components: Bj = t(Ijt - Sjt + Fjt + Mjt + Ujt) where: t = time, t=1,...,T I = Capital costs S = Salvage value F = Fuel costs M = O&M costs U = Unserved energy costs Note: All costs are discounted net present values

24 Example of Dynamic Programming Optimization
The total cost at each state is based on the following cost components: TC = VC + FC + TCX where: TC = Committed cost for current year VC = Variable operating cost for the current year FC = Fixed cost for new units constructed in the current year TCX = Committed cost for previous year (state) Variable operating cost (VC) for the current year includes: Fuel costs for existing and new generating units Variable O&M costs for existing and new units ENS costs Fixed cost (FC) includes capital cost, salvage value, and fixed O&M costs for all units constructed in the current year Previous year cost (TCX) includes production costs for earlier years and fixed costs for all generating units installed before the current year

25 Simple Dynamic Programming Optimization Problem
Year 1 Year 2 Year 3 VC = 620 FC = 400 TCX= 1420 TC = 2440 State 5 State 2 VC = 580 FC = 360 TCX= 1420 TC = 2360 VC = 420 FC = 300 TCX= 720 TC = 1440 State 6 VC = 560 FC = 400 TCX= 1420 TC = 2380 State 1 State 3 State 7 VC = 320 FC = 400 TCX= 0 TC = 720 VC = 350 FC = 350 TCX= 720 TC = 1420 VC = 600 FC = 350 TCX= 1500 TC = 2450 State 8 State 4 VC = 400 FC = 380 TCX= 720 TC = 1500 VC = 550 FC = 700 TCX= 1420 TC = 2670 State 9 State 6 is the least-cost state in Year 3 Following the backward pointers, it is easily found that the least-cost path is: 1-3-6

26 Dynamic Programming Optimization is Usually Conducted as An Iterative Optimization Process
Each solution represents the best path found among all possible paths containing system configurations (states) in the current model run Thousands of system configurations are examined in each model run The solution that cannot be further improved by modifying “tunnel widths” to include additional paths is the optimal solution

27 Key Outputs from DP Optimization Models Include
Optimal expansion schedule over the study period Expected generation from all units for all periods Reliability performance LOLP Unserved energy (ENS) Reserve margins Foreign and domestic expenditures Cash flow over time Pollutant emissions Sensitivity to key parameters

28 A New Class of Models Is Being Developed for Modeling Capacity Expansion in Competitive Electricity Markets Multiple competing market participants instead of single decision maker Each market participant (e.g., generation company) makes its own independent decisions Market participants have only limited information about the competition Markets are also open to new entrants Ideally an individual player cannot control the market Market participants face multiple uncertainties (demand forecast, fuel prices, electricity market prices, actions of competitors, new market entrants, etc.) Projection of future market prices of electricity is a major input for decision- making process

29 Objectives for Constructing New Capacity in Restructured Markets Differ from those under Vertically Integrated Systems Expansion investments are based on financial considerations, not lowest societal cost or energy security concerns Profits are often the main driving force behind the decision making process Financial decision criteria are typically based on measures such as rate of return on investment, payback period, and risk indicators Other factors such as market share may influence the decision making process Capacity expansion by competitors and new market entrants are uncertain Emphasis is on the risk and risk management for corporate survival versus guaranteed rate of return under the traditional regulatory structure

30 Agent-Based Modeling of Investment Decision Making in Competitive Electricity Markets
Generation companies are represented as individual agents performing profit-based company-level investment planning Generation companies develop expectations and make independent investment decisions each year under multiple uncertainties Uncertainties are often modeled as scenarios with associated probabilities of occurrence Argonne’s EMCAS model uses a scenario tree and calculates profitability curves for various investment options

31 EMCAS Profit-Based Expansion Model Integrates Three Key Components
4/15/2017 EMCAS Profit-Based Expansion Model Integrates Three Key Components Generation capacity investment (expansion) decisions When, what, how much (and where) should I invest? Infrastructure operational decisions How much will my unit be dispatched under various futures? How much profit will it make under all reasonable outlooks? Decision and risk analysis How much risk do I want to take? How do I trade off potentially conflicting objectives? The operation of existing facilities will affect market prices and when and where it becomes profitable to add new units Capacity Expansion (Build New Unit: What? When?) Plant Operation (Operate Given Unit: Generation) Decision & Risk Analysis Adding new units will affect the operation and profitability of existing facilities 31 Test 31

32 In EMCAS Uncertainties are Represented as Scenarios
4/15/2017 In EMCAS Uncertainties are Represented as Scenarios Multiple Possible Futures Agents compute expected profits under all scenarios to estimate profitability of an investment project Test

33 4/15/2017 Agents Choose the Alternative with the Highest Expected Utility Based on their Risk Preference and Multi-Attribute Utility Theory 1.0 Decision Maker’s Preference (Utility Function) Risk Averse Risk Neutral 0.5 where u(x) total utility for attribute set x = x1, x2, ..., xm ui(xi) utility for single attribute, i = 1,2, ..., m ki trade-off weight, attribute i Risk Prone 0.0 Worst Value Best Value where ui(xi) utility for single attribute, i = 1,2, ..., m βi risk parameter, attribute i upper limit, attribute i lower limit, attribute i 33 Test 33

34 Capacity Expansion in Deregulated Systems often Follows a Cyclical Pattern

35 The ABMS Expansion Results Can Reproduce such Behavior

36 Example Outputs from EMCAS: Long-Term Expansion Simulations
4/15/2017 Example Outputs from EMCAS: Long-Term Expansion Simulations Capital investment plans By technology By company Generation by unit Price forecasts Monthly price distributions Chronological price bands Monthly reliability indices Consumer costs Company revenues, costs, profits Test 36

37 Results From any Expansion Model Require Additional Analysis
Fuel supply requirements and availability Financial analysis and cash flow requirements Manpower requirements Infrastructure requirements Plant siting analysis Transmission expansion analysis Environmental analysis Etc.


Download ppt "Modeling Generation Capacity Investment Decisions"

Similar presentations


Ads by Google