Download presentation
Presentation is loading. Please wait.
1
Fundamentals of Project Management
Dr. George F. Jergeas Project Management Specialization University of Calgary
2
Schedule Day 1 Game Introduction PMI stuff Step 1 - Define phase
Step 2 - Plan phase Sequence activities Time estimate Day 2 Cost estimate Step 3 - Organize phase Select team and PM Step 4 - Control phase Step 5 - Close out phase
3
5 Step Project Management PLANNING IMPLEMENTATION
CONTROL DEFINE PLAN ORGANIZE CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools Sequence Project Activities Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders List the Objectives Determine Preliminary Resources Identify Critical Activities Organize Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages Project overview WBS Recruit Criteria Variance Reports Final Report Project network Define Work packages Status Reports Audit Reports Critical Path Assign Work Packages Staff Allocation Reports
4
Step 2 – Plan the project: Basics of Cost Estimating
5
Agenda Introduction What is an estimate Estimating process
What constitutes a good estimate Basic types of cost estimates Order of Magnitudes Definitive Estimates
6
Introduction Cost estimates
Key to successfully conceived, managed and completed projects Not limited to construction An approximation procedure Mistakes can be very costly!
7
What is a Cost Estimate? AACE Definition To the contractor
“A compilation of all the costs of the elements of a project or effort included within an agreed upon scope” To the contractor “To forecast cost required to complete a project in accordance with the contract, plans and specifications” To the owner cost includes: Administering the contract Contractor's charges, consultants and suppliers fees Price of land, financing and operating costs
8
What Constitutes a Good Estimate?
A clear, sound basis An agreed upon realistic execution plan A sound plan for estimating development Good estimating methods and data base Well documented basis of estimate Good experienced estimator
9
Order - of - Magnitude Estimates
A quick method of determining an approximate probable cost of a project due to the following specific situations: Time constraints High cost of a detailed estimate
10
Order - of - Magnitude Estimates
Prepared without detailed engineering data Square feet of floor area Cubic feet of volume Plant capacity for input and output Km of road surface type Use: In feasibility studies of a project and screening several types of alternatives or proposals Accuracy: +/- 30%
11
Definitive Estimates Prepared from very defined engineering data
Requires as a minimum: Plans and elevations Piping and instrument diagrams Single line electrical diagrams Equipment data sheets and quotations Architectural and structural details Soil data and sketches of major foundations A complete set of specifications Accuracy: +/- 5%
12
Components of a Cost Estimate
Direct Cost Labor: actual amount paid to field personnel Materials: essential to constructing and operating a facility including equipment installed permanently Equipment: used to perform a contract Subcontracts
13
Components of a Cost Estimate
Indirect Costs Overhead Home office overhead Job site overhead (general conditions) Taxes Risks Contingency Profit Escalation
14
Site Overhead (General Conditions)
Cost of items that cannot be charged to a specific element of work: Supervision Temporary facilities Office trailers Toilets Utilities Permits Photographs Clean-up
15
Profit Is the amount of money included by the contractor in its price as compensation for risk, effort and endeavor in undertaking a project. It is the money left after a contractor has met all costs (both indirect and direct). Profit amount included is very subjective and depends on: Size of project Extent of risk involved Need for work Extent of competition
16
Contingency An amount added to cover any additional costs that may occur during construction. To determine the amount of contingencies desirable, an estimator should rely on: Personal judgment, or Through statistical analysis of past project costs
17
Estimated Conference Planning Budget
$243,325 Site $170,425 Program $41,100 Marketing $31,800 Theme $600 Materials $13,300 Speakers $27,200 Date $1,000 Location $169,425 Lists $2,000 Brochure $29,800 Registration 3 conf calls with pgm comm Travel/expenses for 16 $500 per speaker 3 site $800/visit per person/day for 3 days for 1100 meeting $225/day/room for 3 days for 3 rooms Deposit 25,000 $80/1000 Obtain Speaker Materials $800 Prepare Conference Notebook $12,500 Design Brochure $12,800 Mail Brochure $17,000 Layout: 16 $50/page Printing: 30,000 $0.40/copy 1100 $5/binder photocopy materials 350,000 $0.02/page 25,000 $0.68/piece $50/speaker
18
PM ANNUAL CONFERENCE REVENUE & EXPENSE BUDGET
Revenues Registrations - $335……………………………………………………………..$368,500 Expenses Salary Graphic artist………………………………………………………………………………………………...800 Total Salary……………………………………………………………………………………………..800 Non-Salary Travel……………………………………………………………………………………………………...21,600 Printing…………………………………………………………………………………………………….19,000 Postage…………………………………………………………………………………………………...17,000 Mailing Lists……………………………………………………………………………………………….2,000 Telephone…………………………………………………………………………………………………….600 Supplies…………………………………………………………………………………………………….6,300 Speaker Honoraria……………………………………………………………………………………….8,000 Site Deposit………………………………………………………………………………………………..1,000 Food………………………………………………………………………………………………………165,000 Meeting Room Rental…………………………………………………………………………………..2,025 Total Non-Salary………………………………………………………………………………..242,525 Total Expenses………………………………………………………………………………………$243,325 Gross Profit…………………………………………………………………………………………$125,175 Indirect 40% of Total Expenses)……………………………………………………$97,330 Net Profit………………………………………………………………………………………………$27,845
19
Estimating Issues Underestimating Overestimating
Don’t be overly optimistic about time and costs Cause problems in the long run and produce unsatisfactory product Overestimating Danger that project will not get approval Over compensating for unexpected delays/problems
20
Estimating Issues Use your WBS: Define the lowest level of activities to estimate the time and dollars required Check activities costs on previous projects Take into account circumstances during implementation, weather, transportation costs, availability of materials and labour etc.
21
Summary There are different types of estimates
Each type used for specific purpose but no substitute of definitive estimates An estimate information data base is essential Good estimates come from looking at the details
22
Important Points Order-of magnitude estimating important to owner:
Owner examines the estimate before continuing with further development of project. Liability issue: based on the information contained in your estimate, major decisions are often made by the owner This places a responsibility and liability on you as an estimator
23
Important Points Acquaint yourself with terminology, elements of cost which include labor, equipment and material costs Develop habits of thoroughly reviewing contract documents Remember to document and maintain the data base
24
Step 2 - Plan the Project: Writing a Project Proposal
25
Agenda Writing a proposal The purpose Format Executive summary
Background Project manager Activity Schedule Budget/project cost
26
5 Phase Project Management PLANNING IMPLEMENTATION
DEFINE PLAN ORGANIZE CONTROL CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders List the Objectives Sequence Project Activities Determine Preliminary Resources Identify Critical activities Organise Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages
27
Writing a Project Proposal
Represents the transition from the planning (define, plan) to implementation (organising, control, close) Used as an information source to decide whether the project should proceed to the implementation phase Different terminology used DBM, Brief, Scope Definition Statement
28
Purpose The project proposal provides:
A statement of the need, the approach being taken and the expected benefits Description of project activities, timelines and resources required Documentation for project control Briefing document for new team members and others in the organisation
29
Purpose Tool for decision making, managing, controlling, training and reporting Written for: Senior management Project team Other managers who are indirectly involved Consultants
30
The remainder of this section should be reviewed by attendees.
Please go to slide #43
31
Format Executive summary
States the fundamental nature of proposal and benefits that are expected Should deal with: Nature and approach to technical problem Plan for implementation of project if approved Plan for logistic support and administration Description of team that will complete the work and their experiences on other projects
32
Technical Approach General description of the problem to be undertaken
Organisational approach Provides sufficient detail for the reader to understand what is intended Method for resolving critical problems outlined
33
Technical Approach Proposal to meet clients requirements identified
Procedures for testing and inspections to assure performance, quality, reliability and compliance
34
Implementation Plan Contains estimate of time, cost and materials to be used Lists sub-systems of project in cost estimate Estimates of personnel, equipment and resources are provided by period Major milestones are indicated
35
Logistics Plan Description of how skills, facilities, equipment will be supplied Administration strategy Nature and timing of reports budget, progress, evaluations and audits Handling and costing of change orders
36
Past Experiences How the proposed team has performed?
Who the key personnel are and their qualifications? Keep in mind - the purpose of the proposal is to convince the funder that the project should be supported
37
Format: Example Proposal components Project name
Project manager responsible Activities Schedule Budget
38
Format Project Name Label to identify the project
Should reflect uniqueness of the project Project Manager Person responsible for project Must be able to manage budgets, schedules, team and meet specifications
39
Format Activity Identified by number, description and name
Method for team to refer to an activity Should be short, but reflect task to be undertaken Description states in precise terms the work to be done
40
Format Schedule Based on the analysis of the network
Provides anticipated start and finish dates. Dates may change
41
Format Budget Information provided at an aggregated level
Details attached if requested by senior management Includes: Labour cost estimates Financing costs Materials and equipment costs (See Figures )
42
Project Definition Report
43
Any Questions?
44
Step 3: Organize the Project Implement the Project and Organize the Team
45
Agenda Organize the team
Determine the personnel requirement and skills Select the Project Manager Select the Project Team Characteristics of PM and team What makes teams work
46
5 Step Project Management PLANNING IMPLEMENTATION
Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit DEFINE PLAN ORGANIZE CONTROL CLOSE CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools List the Objectives Sequence Project Activities Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders Determine Preliminary Resources Identify Critical activities Organise Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages
47
Implementation Phase Start once the project has been approved
Project team for the implementation is formed/procured In-house and external Procurement procedures Work package assignments can commence Deliverables are agreed upon and clearly understood Control systems are established Time, Quality, Cost, Safety ….
48
Organising the Project Team
Projects are only as successful as the project manager and team who implements them Building an effective team takes a lot of work Must consider more than just a person’s technical skills
49
Organising the Project Team
The selection of team members is based on skills, availability and personality There needs to be a commitment and chemistry among the team members Team building is not a perfect art, there is always the risk of conflict
50
Organising the Project Team
Organized and located to facilitates open continuous communication This does not mean they have to be physically located together Team members may be reallocated for the duration of the project or remain in their function areas
51
Organising the Project Team
Large projects Dedicated core team Structured More defined roles Need for open and continuous communication lines Self contained
52
Organising the Project Team
Small projects Part-time commitment from team members Team members remain in their functional units Conflicting priorities/demands exist Conflicts may arise from having more than one boss or more than one team involvement
53
Organising the Project Team
Be sure all parties understand the need to: Build the team, What the priorities are within in the organisation and Their assistance is appreciated Project manager to ensure that the cross functional relationships are maintained and supported
54
Characteristics of an Effective Project Manager
Understands purpose of the project Has the necessary background and experience Effective leader with proven managerial ability
55
Characteristics of an Effective Project Manager
Has credibility with team and client Sensitive to project and corporate politics Excellent communication skills Consistent behaviour Facilitator rather than a dictator
56
Selection of Project Manager
Key position on the project Selection of appropriate individual is essential to success of the project Selection criteria should be established based on the skills required to carry out project
57
Project Manager Selection Criteria
1. Background and Experience Should be consistent with the nature and needs of the project Education should be compatible with nature and expectations of the project Look for a individual with a mix of conceptual, analytical, operational and practical experience
58
Project Manager Selection Criteria
2. Leadership Ability to design, co-ordinate, control and implement project plan Stay the course until completion Ability to see the big picture and understand the details
59
Project Manager Selection Criteria
3. Technical expertise Ability to direct, evaluate, and make decisions on technical alternatives Does not and can’t be an expert in all areas of the project Should have expertise in project management, team management and training
60
Project Manager Selection Criteria
4. Interpersonal skills Should be able to: Motivate, inspire, and coach Actively listen, give and receive feedback Empathise, relate feelings, needs and concerns in a positive manner Prevent and resolve conflicts, negotiate Keep team, senior management and stakeholders informed through effective communication channels
61
Project Manager Selection Criteria
5. Proven Managerial Ability Good track record, excellent indicator of the future Knowledge of the organisation and its operation Ability to effectively interface with all levels of the organisation Ability to link project goals to corporate mission and goals
62
Selecting the Team Selection of team members depends on a number of factors: Nature of the technical work to be done Level and type of expertise required at each phase of the project Availability of staff in the organisation and reporting relationships
63
Team Selection Criteria
Similar to those of the project manager More emphasis on the technical skills Interpersonal skills essential Ability to function as a team member with shared goals and objectives (us instead of me)
64
Effective Team Characteristics
Commitment to the project goals and completion Ability to communicate, share responsibility and power Flexible willing to change or try some new methods Technically competent Willing to: Admit mistakes Admit not have all the answers Accept feedback
65
Effective Team Characteristics
Politically astute Team players Creative and open to suggestions High self esteem, can do attitude Willing to work for more than one boss, across formal structure and authority system Results oriented
66
What Makes Teams Work Successful Projects: The team has fun
Have the support of senior management Everyone understands the reason for the project Conflicts are addressed and dealt with The entire organisation is committed
67
What Makes Teams Work Successful projects:
Team understands the organisation’s mission and how the project fits within that mission Team understands what is to be achieved and when it is achieved Trust and communication
68
Step 4 - Control the Project
69
5 Step Project Management PLANNING IMPLEMENTATION
Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit DEFINE PLAN ORGANIZE CONTROL CLOSE CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools List the Objectives Sequence Project Activities Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders Determine Preliminary Resources Identify Critical activities Organise Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages
70
Project Control Schedule control Cost control
Team performance evaluation Change control
71
Schedule Control
72
Incorporating Project Changes into the Schedule
When a change is requested or needed, you should: Estimate the impact on the schedule by incorporating any additional tasks and revised duration estimates Add activities that were overlooked when the original plan was developed Add new activities due to unanticipated events Obtain client approval before proceeding A new baseline plan is established and used as the benchmark for comparison
73
Approaches to Schedule Control
Schedule control involves four steps: Analyse the schedule to determine which areas may need corrective action Decide what specific corrective actions should be taken Revisit the plan to incorporate the chosen corrective actions Recalculate the schedule to evaluate the effects of the planned corrective actions
74
Approaches to Schedule Control
If the planned corrective actions do not result in an acceptable schedule, repeat the previous steps
75
Approaches to Schedule Control
Each time a schedule is recalculated: Identify the critical path Identify any activities that have a negative slack Compare paths where slippage have occurred (Slack got worse) with the previously calculated schedule Apply acceleration to the paths with negative slack: The most negative slack should be given top priority Focus on activities that are in progress or to be started in the immediate future Focus on activities that have long duration estimates
76
Acceleration To reduce schedule:
Apply more resources to speed up an activity Add more people Increase hours per day or increase days per week Assign person(s) with greater expertise or more experience Reduce the scope or eliminate the activity if possible Increase productivity through improved methods or technology
77
Acceleration Trade-off in the form of an increase in costs or a reduction in scope This could jeopardise elements of the overall project objective: scope, budget, schedule, and/or quality There may be a dispute over who should absorb any increased cost to accelerate Bonus provision if project is completed early Liquidated damages Project meetings are a good forum for addressing schedule control issues
78
Evaluation of Delays in the Work
Questions to determine that a delay in the work is compensable: Was the cause of the delay beyond the contractor’s control? Did the contractor fail to take normal precautions? Was the contractor ready and able to work?
79
Evaluation of Delays in the Work
Did the contractor submit a detailed schedule projecting project completion within the allotted time? Was the schedule updated regularly? Did the updated schedule justify time extension? Did this schedule contain a critical path analysis or equivalent? Has the contractor maintained sufficient forces in those operations along the critical path where needed to meet target dates?
80
Evaluation of Delays in the Work
How have causes, other than normal weather, beyond the control and without the fault or negligence of the contractor affected target dates along the critical path? Has the contractor proven “unusually severe weather” with such information as climatological data, return probability of severe storms, or flood depth data?
81
Evaluation of Delays in the Work
Did the weather phenomenon actually delay operations along the critical path or in secondary operations? Was the contractor shut down for other reasons?
82
Cost Control
83
Cost Control System Any cost control system should enable a project manager to observe current perfomance (productivity) levels, compare them with budget levels and institute corrective actions to keep productivity, and ultimately costs, within acceptable range
84
Elements of Effective Cost Control System
Observation Comparison of observation with budget Corrective action to take if necessary Can also serve as: A basis for a productivity improvement program A measure of productivity loss caused by adverse factors and changed conditions such as winter work, acceleration, design changes, etc.
85
Cost Control System Compares actual man-hours expended to earned hours
Actual work hours come from contractor’s daily time sheets Earned hours are calculated by multiplying the completed quantities during a period by estimated man-hours per unit quantity See figure following as an example
86
Labour Productivity Report
87
Cost overrun Budget Money Time Now Actual Expenditure Earned Value
NOTES:________________________________________________________ _______________________________________________________________ Earned Value Time Delay
88
Money Budget Ahead of schedule Earned Value Making Money Actual Time
NOTES:________________________________________________________ _______________________________________________________________ Actual Time
89
Fundamentals of Project Management
Example: Activity Variance Report Fundamentals of Project Management Tool Kit
90
Conclusion You can draw immediate attention to significant deviations from what was planned Indicate what corrective action is necessary and by whom Dependent on accurate reporting and correct allocation of hours expended
91
Performance Evaluation
92
Joint Evaluation Progress meeting Forum for identifying a problem
Specific criteria to evaluate effectiveness Teamwork Timely problem resolution Periodic survey Comparisons of survey responses identify areas of improvement and potential problems
93
Measuring Success Met target price, quality and schedule
Goals achieved Benchmarking Positive client feedback Great safety record Disputes resolved effectively
94
Joint Evaluation 1. Communications between the owner/contractor personnel are………… 2. Top management support of partnering process is……………………… 3. Problems, issues or concerns are…… 4. Cooperation between owner and contractor personnel is…………………… 5. Responses to problems, issues, or concerns frequently become………… Difficult, guarded Easy, open, up front Not evident Inconsistent Obvious, consistent Attacked promptly Ignored Cool, removed, detached, Genuine, unreserved, complete Personal issues Treated as project problems
95
Change Control: Changes and Extra Work
96
This Session Definition Impact costs
Basic principles in handling change orders Types of changes Elements of a change order Recommendations for good practice NOTES:________________________________________________________ _______________________________________________________________
97
Change Order Is a written agreement to modify, add to, or otherwise alter the work from that set forth in the contract documents at the time of opening bids, provided that such alteration can be considered to be within the scope of the original project; otherwise, a contract modification may be required It is the only legal means available to change the contract provisions after the award of contract
98
Change Order Could be addition to or deletion from the work
Changes in the method of execution or manner of work performance Change in owner-furnished materials or facilities Change in the contract time or order of the work Correct errors in the plans or specifications Direct results of contractor suggestions that are approved by the owner and its agents
99
Change Order Changes may involve Make sure payment covers
A price change in the contractor’s favor Cash credit to the owner No price change at all Make sure payment covers Impact costs & Loss of productivity Time extensions
100
Basic Principles in Handling Change Orders
No work should be included beyond the scope of the base contract The identity of the individuals authorized to request and approve change orders should be established early During the start up meeting the change order handling procedures must be established/discussed
101
Basic Principles in Handling Change Orders
All changes in the work must be authorized in writing prior to the execution The scope of a change order must be clear A request for a change proposal should contain enough information to enable the contractor to make a realistic estimate
102
Basic Principles in Handling Change Orders
The contractor should submit its proposal to execute a change order as soon as possible after receiving the request The owner’s approval or rejection should follow as soon as possible The Change Order should be fair. It should recognize the contractor’s right to include: Overhead and profit percentages Compensation for legitimate time-delay claims Compensation for legitimate impact costs if any
103
Types of Changes Directed changes
Owner directs the contractor to perform work that differs from that specified in the contract Easy to identify and mutually recognized Disagreements tend to center on questions of financial compensation and the effect of change on the schedule
104
Types of Changes Constructive Changes
Is an informal act authorizing or directing a modification to the contract caused by an act or failure to act Defective plans and specifications Engineer’s interpretation Higher standard of performance than specified Improper inspection and rejection Change in method of performance Owner nondisclosure Impossibility/impracticability of performance
105
Types of Changes Constructive Changes
Must be claimed in writing within time specified in the contract Major source of disputes
106
Change Order Form Description of change Reason for change
Change in contract price Change to contract time Statement that secondary impacts are included Approvals by owner’s and contractors representatives
107
Sample of a Change Order
PROJECT TITLE PROJECT NO. CONTRACT NO. CONTRACT DATE CONTRACTOR The following changes are hereby made to the Contract Documents: Construction of access bridge abutment No. 1 drainage system; and Reset two penstock bearing plates. All in accordance with revised DWG S-17209 Revision 4, dated August 29, 2000 JUSTIFICATION: Unforeseen soil conditions CHANGE TO CONTRACT PRICE Original Contract Price: $ Current contract price, as adjusted by previous change orders: $ The Contract Price due to this Change Order will be (increased) (decreased) by: $ The new Contract Price due to this Change Order will be: $ CHANGE TO CONTRACT TIME The Contract Time will be (increased) (decreased)by calendar days The date for completion of all work under the contract will be Requested by dated Recommended by dated Ordered by dated Accepted by dated
108
Recommendation for Good Practice
Percentages for overhead and profit to be applied Determination of the individual representative of the owner who is authorized to approve change orders Procedures to be followed in the submittal of change order proposals Change order forms to be used
109
Recommendation for Good Practice
Time extensions required, if any The detail required of contractors when submitting change order proposals - Will a complete breakdown of all costs be required? Brief description - Descriptive drawings Overtime necessary due to change orders - consideration of decreased productivity Responsibility for record drawings brought about due to the change orders
110
Dealing with Disputes: Keys to Project Control
111
Agenda Causes Obstacles to resolution Successful settlement
112
Causes of Disputes Design changes, errors/omissions and extras
Late owner-supplied equipment Lack of co-ordination Changed soil/site conditions Access to site Claims may arise on projects for a number of reasons. Some well known ones included above. Research and practice agree that the main causes of contract claims are design changes and errors. 72% of all contract claims can be traced to design changes, extras and errors. This is an issue that Project Managers should pay a great attention to as you can see from the following slides. From your previous experiences, list the main reasons or factors that caused an increase in cost or time.
113
Causes of Disputes Delays and acceleration
Insufficient bid preparation time Inadequate bid information Underestimation by contractors Inadequate management Claims may arise on projects for a number of reasons. Some well known ones included above. Research and practice agree that the main causes of contract claims are design changes and errors. 72% of all contract claims can be traced to design changes, extras and errors. This is an issue that Project Managers should pay a great attention to as you can see from the following slides. From your previous experiences, list the main reasons or factors that caused an increase in cost or time.
114
Resolving Disputes Face to face by parties themselves
By appointing a mutually acceptable third party By accepting the jurisdiction of the courts
115
Obstacle to Resolution
Owner’s bias Contractor’s bias Total cost claims -Owner’s bias -loss is caused by contractor’s action or inaction -loss is caused by contractor’s mismanagement -loss is caused by contractor’s under estimation -loss is caused by contractor’s strikes, weather - nothing to do with the owner -Contractor’s bias -loss is caused by owner’s mismanagement or interference -loss is caused by owner’s design changes -contractor is not responsible and managed the job properly -contractor did not underestimate the job -Total cost claims -claims are prepared that request the entire difference between actual cost and estimated costs. This means that there is one side responsible for all the cost overrun. This is not true. The above approach is NOT fair and does not lead to a fair and successful resolution of disputes. How do you deal with claims, i.e., how do you prepare or evaluate claims?
116
Successful Settlement
Get the facts Keep good records Know your contract Preserve your rights Show: Cause-Effect-Entitlement-Quantification To prepare a successful claim or to defend against a claim or evaluate a claim on behalf of an owner, you need to get the facts as discussed earlier and show in the claim report the cause-effect-entitlement-quantification relationship. This will enhance the claim report credibility and create an atmosphere for settlement based on facts not fiction with justification as to payment.
117
Settlement of Disputes
The following options are available: Negotiation Mediation Dispute Resolution Board Mini-trial Arbitration Litigation The best approach to settle disputes is to avoid them or prevent them from happening in the first place by properly managing your project as discussed in this course and other courses in this program. Next to best to avoidance of dispute is to resolve dispute through the face to face negotiation between the disputant without the involvement of a third party. The other alternatives are available to you as explained in the following slides.
118
Mediation Voluntary Non-binding Economical Assist negotiation
Mediation involves hearing positions and helping the participants resolve the dispute themselves. The success of mediation is 85% in self motivated mediation (i.e. both sides wanted mediation, 60% for court-imposed mediation). This is very economical compared to other alternatives. The only drawback is that decision of a mediator is not binding on the parties. Ideally, disputes should be resolved by either negotiation or mediation, not litigation. Mediation is the most cost effective method of disposing of disputes after negotiation.
119
Arbitration Binding 1 or 3 arbitrators Selection of arbitrators
Each party selects one arbitrator Both select a chairperson Could be expensive Arbitration was introduced to resolve dispute and reduce cost of litigation. Arbitration provides a binding solution to disputes. However, as the time and costs required to resolve arbitration disputes increases, the costs are beginning to approximate those of litigation.
120
Dispute Resolution Board
DRB consists of three members and is established at the beginning of project Non-binding This is another useful, economical option available to apply on projects.
121
Mini-trial Presentation of both sides’ arguments before an advisory panel and executives of both sides. May include a judge Predict the likely outcome and the strength and weakness of the case Voluntary and non-binding
122
Litigation Adversarial Costly
Voltaire: “I have only been ruined twice in my life. The first time was when I lost a lawsuit: the second, when I won one!” -Judgement is binding -Very expensive and adversarial -Contradict everything we say about Project Management kills the team, ruins relationships between the party and distract professionals from all sides away from the real goals and objectives. -Means we failed as Project Managers -Avoid it, all parties will be losers except litigation lawyers and claim consultants.
123
Problem Resolution Lowest level with time limit
Escalated to the next level of management No action is not an option
124
Problem Resolution
125
Problem Resolution Systematic approach Seek solutions
Increased and higher quality discussion Win-win solutions Equality of rights among parties Agree on no adversarial relations
126
Problem Resolution: Negotiation
Separate the people from the problem Focus on interests, not positions Invent options for mutual gain When possible, use objective criteria
127
Step 5 – Close the Project
128
Agenda Purpose Prerequisite activities Project termination process
Final project report Rewarding successes and learning from failures
129
5 Phase Project Management PLANNING IMPLEMENTATION
CONTROL DEFINE PLAN ORGANIZE CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders List the Objectives Sequence Project Activities Determine Preliminary Resources Identify Critical activities Organise Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages Project overview WEBS Recruit Criteria Variance Reports Final Report Project network Define Work packages Status Reports Audit Reports Critical Path Assign Work Packages Staff Allocation Reports
130
Purpose To ensure all deliverables are installed or implemented according to time, budget and specification
131
Purpose To ensure that the works have been completed as specified, and that all facilities work properly To provide a record of the actual execution, together with operating instructions To train staff in the use of the works
132
Purpose To formally close out contractual relationships Obtain sign off on final report to show contracted deliverables have been successfully implemented To formally terminate project team assignments To ensure adequate project documentation and baseline information for changes that may need to occur in the future To obtain client’s acceptance of project work and deliverables
133
Activities Test the engineering performance
Search for non-operational defects, e. g. those that affect only the appearance Inspect the facilities thoroughly and have defects remedied Prepare as-built drawings and record Start up, test and adjust all services Prepare operational instructions and maintenance manuals Train staff Monitor performance of work against original requirements
134
Deficiency Lists These are lists of required repairs or completion of deficient/incomplete items. Schedule for completion of deficiencies. Need a sign-off procedure. Need a handover process to turn project over to Owner in organized way.
135
Records During implementation, difficulties may arise which result in changes to the original design. Records of these changes will be kept during implementation, mainly for financial reasons. These must be brought together to make a complete record of the actual execution.
136
As-built Drawings Mandatory on some projects.
Should be provided on all projects. Reflect what was actually built. Contract documents must set a date for completion of as-built drawings. Make sure they are worked on as the project is built do not wait for the end of the job.
137
Warranties, Spare Parts and Manuals
Watch for differing warranty starts and durations. Recommended parts list. Operations and Maintenance Manuals. Service and warranty contacts and service agreements/expectations.
138
Termination Process Project termination can be complicated
A systematic approach is required to successfully cover all bases in terminating contracts and relationships. Stay in close contact with the client and administration to ensure close down meets with the client’s satisfaction.
139
Termination Process Generally the termination phases include:
1. Prepare termination logistics 2. Document project 3. Conduct post implementation audit and prepare and submit final report 4. Obtain client approval 5. Close operation
140
Conduct Post- Implementation Audit: Prepare and Submit Final Report
Termination Logistics PROJECT TERMINATION PHASES Close Operation Document The Project Project Termination Phases Obtain Client Approval Conduct Post- Implementation Audit: Prepare and Submit Final Report
141
1. Prepare termination logistics
Establish project termination design Assign a termination manager Assign a termination team to assist manager Conduct a termination meeting to review process Assign close-out tasks
142
2. Document the Project Prepare personnel termination reports
Close down project office and reporting system Terminate all financial documents Complete all payments and expenses Collect all debts prepare the financial project close out report
143
2. Document the Project Terminate all work orders, contracts, assignments and outstanding supplier and customer obligations. Document completion and compliance with all vendors and contractors. Close all project sites and return all project equipment.
144
3. Conduct Post -Implementation Audit
Complete Final Report Submit report to client Evaluation of project’s goals and activity achievement. Measured against the project plan, budget, time deadlines, quality of deliverables, specifications and client satisfaction.
145
Final Report Should answers the following questions:
Was the project goal achieved? Was the project work done on time? Was it done within budget? Was it done by specifications? Was the client satisfied with the project results? Memory or history of the project. File others can refer to, study progress and impediments of the project. Can follow many formats.
146
Final Report Usually includes the following elements:
Overall success and performance of the project Organisation and administration of the project Techniques used to accomplish project results Assessment of project strengths and weaknesses Recommendation of project manager and team for continuation or extinction of project
147
4. Client Approval Obtain Client approval. 5. Close Operation
Close all physical sites and terminate remaining project staff.
148
Rewarding Successes and Learning From Failures
Closing a project is a celebration of effort. Brings resolution to the process. Project manager should bring the team together to review their journey. Way of closing formal and informal relationships. Way to re-enforce learning that occurred. Final get together brings project full circle.
149
Summary All projects must be closed off.
Project should meet with client acceptance. Provide installed deliverables. Document the process and achievements. Provide closure for the team and client.
150
Critical Factors in Successful Project Implementation
Mission Senior Management Schedule Client Consultation Personnel Pinto, J. K. and D. P. Slevin (1987). IEEE Transactions on Engineering Management EM34(1): Technical Tasks Client Acceptance Monitoring & Feedback Communication Troubleshooting
151
Project Management Education / Training
Online resources (websites and list servers) Each other (sharing knowledge and experiences) Balance experience with education Project Management Institute: PMBOK Guide,
152
Additional Online Resources in Project Management
153
Concluding Remarks Projects - an increasingly important way of working
Project management is challenging, rewarding Keep it simple, use aspects of project management that make sense Don’t be an Accidental Project Manager Its OK to make mistakes…learn from them to improve project management practices
154
That’s all and thank you
Good luck in managing your projects
155
Sample Templates and Forms
156
5-Step Project Management PLANNING IMPLEMENTATION
CONTROL DEFINE PLAN ORGANIZE CLOSE Identify project activities Determine Personnel Needs Define Management Style Obtain Client Acceptance Install Deliverables Document the Project Issue Final Report Conduct Post- Implementation Audit State the Problem Identify Project Goals Estimate time and cost Recruit Project Manger Establish Control Tools Sequence Project Activities Recruit Project Team Prepare Status Reports Review Project Schedule Issue Change Orders List the Objectives Determine Preliminary Resources Identify Critical activities Organize Project Team Identify Assumptions and Risks Write Project Proposal Assign Work Packages Project overview WBS Recruit Criteria Variance Reports Final Report Project network Define Work packages Status Reports Audit Reports Critical Path Assign Work Packages Staff Allocation Reports
157
Sample Project Overview - Sample Objectives 1. Develop the Program
Project Overview Project Name - PM Conference Project Manager Problem/Opportunity Membership in PM Association has declined in the past four years and attendance at conferences has declined in past three years. The viability and financial stability of the organization depends on maintaining membership and successful annual conference. Goal Reverse downward trend in membership and annual conference attendance. Objectives 1. Develop the Program 2. Set the Conference Site and Date 3. Design and Implement the Marketing Plan Success Criteria 1. At least 50 of previous years conferences attendees will attend 2. At least 150 of 450 PMI Canada members will attend 3. At least 1.5% of the non-members receiving conference brochure will attend 4. At least 5% of the non-member attendees will join PM Association Assumptions and Risks 1. Interest in PM can be renewed through the annual conference 2. A quality professional program will attract members and non-members 3. Key speaker(s) fail to show up or submit written paper. Prepared by Date Approved by Date Sample
158
Fundamentals of Project Management
Project Overview Project Name Project Manager Problem/Opportunity Goal Objectives Success Criteria Stakeholders Risks and Assumptions Prepared by Date Approved by Date Fundamentals of Project Management Tool Kit
159
Fundamentals of Project Management
Stakeholder and External Issues Analysis STAKEHOLDER and External Issues Their Objective/Purpose Their Strategy Their Potential Impact on the project How They Operate Where they gain Support How to Manage them and your plan for mitigation Fundamentals of Project Management Tool Kit
160
Risk Management Template
Monitoring Schedule Response Plan Owner Impact Probability Risk
161
Sample WBS - Sample CONFERENCE PLANNING PROGRAM SITE MARKETING
THEME MATERIALS SPEAKERS DATE PLACE LISTS BROCHURE REGISTER OBTAIN MATERIALS PREPARE KITS DESIGN BROCHURE MAIL BROCHURE Sample
162
Fundamentals of Project Management
Estimated Project Planning Budget Description __________ Cost __________ Description __________ Cost __________ Description __________ Cost __________ Description __________ Cost __________ Description __________ Cost __________ Fundamentals of Project Management Tool Kit
163
Estimated Conference Planning Budget
$243,325 Site $170,425 Program $41,100 Marketing $31,800 Theme $600 Materials $13,300 Speakers $27,200 Date $1,000 Location $169,425 Lists $2,000 Brochure $29,800 Registration 3 conf calls with pgm comm Travel/expenses for 16 $500 per speaker 3 site $800/visit per person/day for 3 days for 1100 meeting $225/day/room for 3 days for 3 rooms Deposit 25,000 $80/1000 Obtain Speaker Materials $800 Prepare Conference Notebook $125,500 Design Brochure $12,800 Mail Brochure $17,000 Layout: 16 $50/page Printing: 30,000 $0.40/copy 1100 $5/binder photocopy materials 350,000 $0.02/page 25,000 $0.68/piece $50/speaker
164
Sample Project Schedule - Sample Project: ____________________
Project Manager: ____________________ Date: _____________ Sample
165
Fundamentals of Project Management
Project Schedule Project: ____________________ Project Manager: ____________________ Date: _____________ Fundamentals of Project Management Tool Kit
166
RACI Charts (F.T Hartman)
2.4.5 Major Element Amelia Drover Fred 2-5 Deliverable:_____________________ Manager:___________________ Project:_________ DATES A C G C F M J W B D M H F W L S W E ACTION Budget Actual Budget Actual W/Hrs. W/Hrs Cost Cost Activity Another activity Build something R A A C I I I C - R C I A A I A R A C I I C ,500 - R C I A A I A R A A C I I I C ,000 R A C I I C ,700 Another Item Yet another Design a bit Design more Sneeze Gesundheit - A R I C C A I I R C A A I C I ,785 - R I I C Another thing Wait for item More stuff Finish A C R C I C ,000 - I C A A R I A I R A I C I A A A A I C I I A A A R
167
RACI Charts Deliverable:_____________________ Manager:___________________ Project:_________ ACTION DATES ------People involved Other Info. (e.g., Cost) NOTES_________________________________________________________ _______________________________________________________________
168
RACI Chart 2 1 Inform Coordinate with Accountable to Responsible party
Task
169
PM ANNUAL CONFERENCE REVENUE & EXPENSE BUDGET
Revenues Registrations - $335……………………………………………………………..$368,500 Expenses Salary Graphic artist………………………………………………………………………………………………...800 Total Salary……………………………………………………………………………………………..800 Non-Salary Travel……………………………………………………………………………………………………...21,600 Printing…………………………………………………………………………………………………….19,000 Postage…………………………………………………………………………………………………...17,000 Mailing Lists……………………………………………………………………………………………….2,000 Telephone…………………………………………………………………………………………………….600 Supplies…………………………………………………………………………………………………….6,300 Speaker Honoraria……………………………………………………………………………………….8,000 Site Deposit………………………………………………………………………………………………..1,000 Food………………………………………………………………………………………………………165,000 Meeting Room Rental…………………………………………………………………………………..2,025 Total Non-Salary………………………………………………………………………………..242,525 Total Expenses………………………………………………………………………………………$243,325 Gross Profit…………………………………………………………………………………………$125,175 Indirect 40% of Total Expenses)……………………………………………………$97,330 Net Profit………………………………………………………………………………………………$27,845
170
Project Definition Report
171
Sample of a Change Order
PROJECT TITLE PROJECT NO. CONTRACT NO. CONTRACT DATE CONTRACTOR The following changes are hereby made to the Contract Documents: Construction of access bridge abutment No. 1 drainage system; and Reset two penstock bearing plates. All in accordance with revised DWG S-17209 Revision 4, dated August 29, 2000. JUSTIFICATION: Unforeseen soil conditions CHANGE TO CONTRACT PRICE Original Contract Price: $ Current contract price, as adjusted by previous change orders: $ The Contract Price due to this Change Order will be (increased) (decreased) by: $ The new Contract Price due to this Change Order will be: $ CHANGE TO CONTRACT TIME The Contract Time will be (increased) (decreased)by calendar days. The date for completion of all work under the contract will be Requested by dated Recommended by dated Ordered by dated Accepted by dated
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.