SURA Shelf Hypoxia Project Six Month Accomplishments, Progress, Plans & Challenges John Harding, Northern Gulf Institute Katja Fennel, Dalhousie University.

Similar presentations


Presentation on theme: "SURA Shelf Hypoxia Project Six Month Accomplishments, Progress, Plans & Challenges John Harding, Northern Gulf Institute Katja Fennel, Dalhousie University."— Presentation transcript:

1 SURA Shelf Hypoxia Project Six Month Accomplishments, Progress, Plans & Challenges John Harding, Northern Gulf Institute Katja Fennel, Dalhousie University Rob Hetland, Texas A&M University Jerry Wiggert, University of Southern Mississippi 3 December 2010

2 SURA Shelf Hypoxia Significant 6 Month Accomplishments (1/2) Hypoxia Data Identification/ Compilation – EPA (Fennel/Lehrter) – GCOOS – Initial MCH & LUMCON (Howard) – NOAA NCDDC/NODC (Beard/ Cross / Garcia) – MagMix (Wiggert/Schiller) Coordination with CI Team – Data Storage/ Formatting/ Access (Fennel/Howard/Howlett) – Model Output Samples Provided (Harding/Howlett) – Model Data Interpolation Discussions (Hetland/ Howlett) – Distributed Model Output & Data Access (Harding/ Howlett) – Evaluation Tools (NAVO “Bub” Diagrams) (Harding/Bub/Howlett) – NOAA CSDL Model Output to SURA Server (Patchen/Howlett)

3 SURA Shelf Hypoxia Significant 6 Month Accomplishments (2/2) Boundary & Pre-Operational Model Availability – HYCOM – complete (Morey) – IASNFS NCOM - complete (Ko/ Harding) – AMSEAS NCOM – complete (Harding/ Bub) Evaluation/ Validation – PAVE (NAVO Model/Profile Tool) provided (Wiggert/Bub) – Preliminary AMSEAS COAMPS/Buoy Winds analysis (Fitzpatrick) – Preliminary Hypoxia Model Evaluations (Fennel) – Technique discussions (Hetland, Fennel, Wiggert, Lipphardt, Harris, Lewitus, …)

4 SURA Shelf Hypoxia Currently in Progress at 6 Months (1/2) Hypoxia Data Identification/ Compilation – EPA – Additional 2007 Data (Fennel/ Lehrter) – GCOOS- Additional MCH data (Howard) – NOAA NCDDC/NODC – Locate Missing SEAMAP (Cross & Garcia) – MagMix - Evaluate ease of entry to NODC (Wiggert/Schiller) Coordination with CI Team - continuing – Data Storage/ Formatting/ Access (Fennel/Howard/Howlett) – Model Data Interpolation (Hetland/ Howlett) – Distributed Model Output & Data Access (Harding/ Howlett) – Evaluation Tools (NAVO “Bub” Diagrams) (Harding/Bub/Howlett) – NOAA CSDL Model Output to SURA Server (Patchen/Howlett)

5 SURA Shelf Hypoxia Currently in Progress at 6 Months (2/2) Boundary & Pre-Operational Model Availability – NOAA CSDL POM/FVCOM (Patchen/ Howlett) – AMSEAS NCOM on LamdaRail at MSU (Harding) – NECoast NCOM on LamdaRail at MSU (Harding, Cross) Evaluation/ Validation – Commence PAVE Comparisons (Wiggert/Bub) – Continue AMSEAS COAMPS/Buoy Winds (Fitzpatrick) – Continue Preliminary Hypoxia Model Evaluations (Fennel) – Continue Technique discussions (Hetland, Fennel, Wiggert, Lipphardt, Harris, Lewitus…)

6 SURA Shelf Hypoxia Planned in Next 3 Months (1/2) Hypoxia Data Identification/ Compilation – EPA – Complete 2007 Data (Fennel/ Lehrter) – GCOOS- Complete MCH & LUMCON data (Howard) – NOAA NCDDC/NODC – Include Missing SEAMAP (Cross & Garcia) – MagMix - Include & provide NODC ease of use feedback (Wiggert/Cross) Coordination with CI Team - Complete – Data Storage/ Formatting/ Access (Fennel/Howard/Howlett) – Model Data Interpolation (Hetland/ Howlett) – Distributed Model Output & Data Access (Harding/ Howlett) – Evaluation Tools (NAVO “Bub” Diagrams) (Harding/Bub/Howlett) – NOAA CSDL Model Output to SURA Server (Patchen/Howlett)

7 SURA Shelf Hypoxia Planned in Next 3 Months (2/2) Boundary & Pre-Operational Model Availability - complete Model Coupling – Complete (Hetland/ Morey) Model Runs – Uncoupled ROMS complete and to Fennel (Hetland) – Initial coupled ROMS runs complete and to Fennel (Hetland) – Uncoupled ROMS/Hypoxia runs complete (Fennel) – Initial coupled ROMS/Hypoxia runs complete (Fennel) Evaluation/ Validation – PAVE Comparisons On going (Wiggert) – AMSEAS COAMPS/Buoy Winds On-Going (Fitzpatrick) – Initial ROMS Model Evaluations (Hetland) – Initial ROMS/Hypoxia Model Evaluations (Fennel) Shelf Hypoxia Team Face to Face Meeting – 3,4 March 2011

8 SURA Shelf Hypoxia Challenges Faced, Resolved, Impeding Hetland Post Doc for Hydro. Model Runs – Original fell through – Delayed start of coupling & model comparison runs – Resolved – Post Doc Arriving at TAMU 5 Dec 2010 PAVE problems on Wiggert computers – Delayed AMSEAS evaluations – Resolved in November thanks to NAVO update