Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Belene NPP Project Configuration Management Presented by Alexey Matveev Varna, May 27-29 2009.

Similar presentations


Presentation on theme: "1 Belene NPP Project Configuration Management Presented by Alexey Matveev Varna, May 27-29 2009."— Presentation transcript:

1 1 Belene NPP Project Configuration Management Presented by Alexey Matveev Varna, May 27-29 2009

2 Belene NPP Project Configuration Management JSC Atomstroyexport is developing the configuration management system to implement Benele construction Project and meet the terms of Terms of Reference. The principal tasks of the configuration management system are: NPP structures, systems and components comply with the established requirements; The physical and functional performances of the plant are accurately described in NPP documentation.

3 Definitions Configuration Management: technical and organizational activities incorporating: −identification of configuration; −configuration control; −submittal of reports on configuration status; −verification of configuration of united information space. ISO 10007 “The Guidelines for Configuration Management”

4 Project Management Book of Knowledge (PMBok) Configuration Management is a set of formal procedures applied to exercise the technical and administrative management aimed at proper review and registration of the requested changes in the Project content, before they are processed within the overall change management process. Definitions

5 Configuration management comprises: change identification; change assessment; change coordination; change approval or rejection; Change introduction. One of the main tasks while implementing the above processes is the analysis of the effect of one change upon all the related elements. Belene NPP Project Configuration Management

6 Contractor’s Configuration Management Plan The Contractor develops Belene NPP Configuration Plan to define the work organization and describe the system. Requirements of CM Plan will be mandatory for meeting by all the Contractor’s Subcontractors. To ensure compatibility of the system with CM system of the Employer this document is developed based upon the “Belene NPP Configuration Management Procedure” BNPP-02-003, which has been agreed upon with the Employer. Work Organization

7 Configuration Identification Belene NPP construction Project configuration elements are: NPP design documentation (as NPP itself); EPC Contract/Agreement dated 29.11.2006. All the physical and functional performances required to define a configuration element within its whole lifecycle shall be documented. Elements of Configuration Management

8 Basic Provisions During Belene NPP Project implementation the following configuration management elements are singled out to be combined into a system: Identification system; Design documents (including commissioning and operation documents); As-built documents (buildings and structures); EPC Contract; Contracts with Subcontractors; Project Cost; Equipment; Project Schedule; Project data base. Contractor’s Configuration Management Plan

9 Configuration Management Elements Equipment Unit Case WD Com.Doc. Oper.Doc ТР Subcontracts Монтаж Contract Coding Schedule Cost Database Contractor’s Configuration Management Plan

10 466Б.02.01.01.ВО Element: “Identification System” Contractor’s Configuration Management Plan Dates of equipment and documents submittal

11 The main tasks of the Identification System are: Unambiguous identification of the subject of control; Assurance of links between the configuration management elements. The Project Management Manual (PMM) procedures are used to set forth the coding rules (for equipment, documents, correspondence etc.), among them: BNPP-01-018 “Document Identification System”; BNPP-07-002 “Identification and Numbering of the Equipment”; BNPP-07-005 “Application of KKS coding system for “Belene NPP” Project” etc. Element: “Identification System” Contractor’s Configuration Management Plan

12 The main task of the said documents is the description of the subject of configuration (Belene NPP), comprising: Design drawings and specifications; Equipment procurement specifications; Work implementation designs; Technical solutions; Commissioning documents; Operation documents etc. Element: “Design Documents” Contractor’s Configuration Management Plan

13 The basic element “Buildings and Structures. Unit Case” incorporates the following subjects of management: Buildings, rooms; Civil structures (documents (drawings) “as-built”); Work takeover certificates; Concealed work takeover certificates; Inspection finding report; Element and system test reports; Welded joint control reports etc. As-built documents for civil and erection and commissioning activities combined into a united system make up the Unit Case. “Buildings and Structures. Unit Case” Contractor’s Configuration Management Plan

14 Project time schedules are the basic CM element to control the dates. Multi-level hierarchical system of time schedules is adopted in the Project. Element: “Project Time Schedule” Contractor’s Configuration Management Plan

15 Element: “Project Time Schedule” Contractor’s Configuration Management Plan Primavera Project Management v.6.0 is selected to be the software for network time scheduling in the Project. The effects of Configuration System elements upon Project implementation dates are analyzed using Summary Integrated Overall Time Schedule of the Project and Detail Time Schedules of implementation of individual types of activities.

16 Element: “Equipment” Contractor’s Configuration Management Plan The basic element of CM “Equipment” incorporates the following subjects of management: Composition of process systems; Equipment, items and materials – aggregates; Aggregate part; Shop drawings (manufacturer’s drawings); Equipment design documents; Shipment documents.

17 Element: “EPC Contract, Subcontracts” Contractor’s Configuration Management Plan Basic element of the CM “Contract, subcontracts” incorporates the following management subjects: Contractor’s Bid; Agreement between the Contractor and the Employer dated November 29, 2006; Text of the EPC Contract, including Appendices and Addenda thereto; Texts of Subcontracts for implementation of individual types of activities;

18 Element: “Cost” Contractor’s Configuration Management Plan Basic component of the CM “Cost” incorporates the following subjects of management: The Bid price; The price of Agreement between the Contractor and the Employer of November 29, 2006; Overall Contract price; Price of individual Articles of EPC Contract; Price of Addenda to the Contract; Price of Subcontracts for implementation of individual types of activities.

19 “Project Database”| Contractor’s Configuration Management Plan Project Database WD, Commissioning Documents Operating Documents Equipment design documents Other documentsProcurement specificaitons Nonconformity reports EPC Contract, Addenda, Subcontracts Design changes Database of NPP Project used in configuration management includes about 40 local databases and is designed to arrange full internal accounting.

20 An Example of Change Introduction Contractor’s Configuration Management Plan Release of Change Notification (new type of valve) Introduction of change into the initial technical data Is the valve ordered? Analysis of effect upon dates and cost. Order. Development of Design Inputs/ Specs Change introduction into Working Documents Affects Technical Design? Introduction of changes into TD Release of WD revision Delivered? Keeping inventory of reserve at the warehouse Modification of supply subcontract Analysis of effect upon dates and cost. Modification of Addendum to EPC Contract Manufacture and supply Making supply subcontract Signing Addendum to EPC Contract Manufacture and supply HANDOVER FOR INSTALLATION

21


Download ppt "1 Belene NPP Project Configuration Management Presented by Alexey Matveev Varna, May 27-29 2009."

Similar presentations


Ads by Google