Presentation is loading. Please wait.

Presentation is loading. Please wait.

City of Cudahy Packard Avenue Streetscape Project INFORMATIONAL MEETING #2 Prepared for the City of Cudahy Common Council Packard Avenue Businesses & Property.

Similar presentations


Presentation on theme: "City of Cudahy Packard Avenue Streetscape Project INFORMATIONAL MEETING #2 Prepared for the City of Cudahy Common Council Packard Avenue Businesses & Property."— Presentation transcript:

1 City of Cudahy Packard Avenue Streetscape Project INFORMATIONAL MEETING #2 Prepared for the City of Cudahy Common Council Packard Avenue Businesses & Property Owners

2 Introductions City of Cudahy Mary Jo Lange – Director of Public Works/City Engineer Tim Birkel – Engineering Supervisor/On-Site Project Manager Ryan Schmidt – On-Site Engineer/Inspection Stark Asphalt Steve Bautch – Project Manager

3 Project Scope Curb & Gutter Asphalt Roadway Decorative Concrete Sidewalks Benches Trash Receptacles Streetlights Traffic Signals Tree/Shrub Plant Boxes Flower Planters Hanging Flower Baskets Bio-Retention/Bio-Swales

4 Extent of Work  Full Reconstruction of Roadway & Sidewalks – Holmes Ave. to Cudahy Ave.  Mill & Overlay Existing Asphalt Pavement – Pulaski Ave. to Holmes Ave.  Reconstruction of Side Streets East to Alley – Barnard, Squire, & Munkwitz Ave

5 Full Road Closure Detour Route on Kirkwood Ave. ◦Layton Ave. Open to Thru Traffic ◦Barnard Ave. Open to Trough Traffic ◦Holmes Ave. Open to Local Traffic Only Map of Detour Route (Traffic Control Plan) All Businesses Open Signs At Layton & Packard Google Maps Detour Walkthrough

6 Tentative Schedule Construction Start Utilities – End of March 2015 Roadway – Mid April 2015 Trees, Plantings, & Furnishings Installed 2016 Construction Finish Mid October 2015 Incentives to Finish Earlier City Parking Lot and Plaza 2016-2017

7 Looking Ahead Tentative Contractor Start Date April 13 th 2015 Access for the most up to date construction progress and information can be found on the newly created Packard Avenue Construction Facebook Page. https://www.facebook.com/pages/Packard-Avenue-Construction- Updates/1632076927015211 Facebook link will be located on the City’s website at www.cudahy.wi-gov starting April 2015.www.cudahy.wi-gov Safety for everyone is our number-one priority! Please read and be informed – and thank you for your patience and cooperation during this challenging time.

8 On-Site Meetings 5117 Packard – Fine Auto Sales 5005 Packard - Superior Linen 4969 Packard – Authentic Automotive 4949 Packard – Gregory Siech Property, FM Auto 4944 Packard – Speedway 4925 Packard – Guardian Angels Daycare 4801 Packard - Landmark Credit Union 4648 Packard – Dan Kozaczok Property 4774 Barnard – Arlyn’s Laundromat

9 Questions? Access Issues to Businesses and Residential Entryways ◦Encouraged to use rear door access if possible (use alleys) ◦After removal of sidewalks, Contractor to stone ◦Possibly build wood steps to entryways ◦No foot access during removal and 12 hours of pouring concrete Driveway openings Street lighting outages Deliveries & mail service Parking on side streets Engineering staff will be taking video of building fronts prior to construction

10 City of Cudahy Engineering Department 5050 S. Lake Drive Cudahy, WI 53110 (414) 769-2212


Download ppt "City of Cudahy Packard Avenue Streetscape Project INFORMATIONAL MEETING #2 Prepared for the City of Cudahy Common Council Packard Avenue Businesses & Property."

Similar presentations


Ads by Google