Download presentation
Presentation is loading. Please wait.
Published byDavin Cure Modified over 9 years ago
1
Buffalo Lake Dam Project Update date Meeting June 30, 2012
2
Purpose of this Meeting Provide update on status of the project Describe the timeline for the project Questions and Answers
3
SITE OVERVIEW North Buffalo Lake Existing Primary Spillway Existing Lock and Gates Existing Boat Launch and Parking Existing Embankment
4
How Did We Get here Primary cause - Flood of June 2008 and re- routing of traffic over the “Dredge Bank”. DNR orders the road closed and to fix, replace or remove dam by 2012. The “Dredge Bank “ was constructed in 1855
5
How Did We Get Here 2010-2011 alternatives evaluation - AECOM study January 22, 2011 public presentation State Bldg. Commission Approval - April 2011 Included in state FY2011-2013 Budget Mead and Hunt contracted June 2012
6
Condition of Existing Structures and Embankment Present Conceptual Alternatives and Range of Costs Conceptual Public Use and Recreation Improvements Discuss Buffalo Lake Drawdown and Potential Construction Impacts Questions January 22, 2011 Meeting Summary
7
Condition of Lock and Sluice Gates The lock’s stone walls are generally in good condition. Voids in the lock floor were observed by the diver. Upstream face of sluice gates. Gates are in fair condition. Corrosion and some pitting is present.
8
Condition of Primary Spillway Downstream surface of concrete capped spillway. Generally in good condition. Note additional flash boards placed for dive inspection. Left Abutment Wall - Downstream Constructed of stone masonry. Stonework is failing. Wall is in poor condition.
9
Condition of Primary Spillway Right Abutment Wall Better condition than left wall. Note steel tieback whalers. Tuck pointing of masonry joints. Right Abutment Wall Erosion of lower joints.
10
Condition of Embankment South Portion of Embankment Looking West Upstream slope very steep Rip rap cover is sparse with no bedding to prevent erosion. North Portion of Embankment Looking South Rip rap cover is sparse with no bedding to prevent erosion.
11
Condition of Embankment Downstream Slope of Embankment in South Portion. Steel probe pushed in 4 feet by hand. Upper zone of embankment is very loose. South Portion of Embankment Large sinkhole repaired in 2008.
12
WDNR Conclusions and Preferred Options Montello Dam FeaturePreferred OptionRange of Costs Sluice Gates and Lock Chamber Replace Existing Gates at Current Location (B) $400,000 - $450,000 Primary SpillwayReplace Entire Spillway and Include a Fish Passage Structure (B) $2.5 - $3.0 Million EmbankmentOption D: Two-way Road and Walking Path from North End to Existing Boat Launch Location Pedestrian / Bike Path on South Half (D) $5.0 - $6.0 Million Public Use and Recreation Enhancements Launch, Piers, Wharfs, Benches, Lights, Portage $350,000 - $400,000 Project Total $8.25 - 9.85 Million The preferred options identified below may change based on funding, public input, and final design.
13
WDNR Conclusions and Preferred Options (Continued) What to Expect: Most Likely Need Full Drawdown and a Partial Breech of the Primary Spillway Best Case – Begin Drawdown After Labor Day – Finish Construction the Following Summer or Fall Best Case – Begin in 2012 – Could be 2013 Selected Options Should Allow Concurrent Construction of Gates, Spillway, and Embankment
14
Project Components Install Slurry Cutoff Wall Embankment Stabilization Spillway Replacement Replace Sluice Gates Fish Passage Boat Landing Public Use Facilities
15
Projected Schedule – per Mead & Hunt and DNR Contract Signed - June 2012 Begin Drawdown – September 4, 2012 Provide Review Documents – September 2012 Provide Final Design Documents – January 2013 Advertise for Bid – February 2013 Bid Date – March 2013 Contract Award & Construction Start - May 2013 Drawdown Dependent Construction Complete, Refill Buffalo Lake – May 2014 Substantial Completion – November 2014 Project Close Out – December 2014
16
Next Steps June 30, 2012 - public update meeting August 18 - meet with Lake District and EA comment period on drawdown Late September - public meeting on proposed final design
17
Thank You! Questions?
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.