1 Earned Value Project Management D. R. McNatty & Associates
---A Tutorial--- PART II - Implementation with Primavera presented by Don McNatty D. R. McNatty & Associates PREPARATION: OPEN P3 PROJECT D:\DATA\EVPRES\PROJECTS\SLD1 Be sure the resource PCT is blank (ev-23k) and the DD = 6/28 THE PURPOSE OF THIS PART OF THE PRESENTATION IS TO RELATE THE THEORY OF EV THAT QUENTIN HAS SHOWN YOU TO HOW WE APPLY IT USING P3 AND SURETRAK.

2 Agenda Basis of EV and Performance Reporting in P3 and SureTrak
Methods for capturing and storing data Methods for calculating and applying CPI and SPI Example Reports and how they are created APPLYING EVPM THEORY INVOLVES CAPTURE & STORE THE DATA, Standard fields, custom data items and code fields. PERFORM CALCULATIONS using global change, export/import, ODBC, report writer COMMUNICATE To your project management team using built-in, custom P3 and ST reports as well as a variety of other reporting options. The examples used are from real projects Names are changed to protect those guilty of actually trying to do this right way.

3 Basis of EV and Performance Reporting in P3 and SureTrak
Stores current period and to-date P3 can calculate BCWP/BCWS on target 1 EV Pct is Input - basis and calculation come from out side P3 except for LOE ETC/EAC can be calculated with Global Change CURRENT PERIOD & TO-DATE SOME PEOPLE FEEL THEY NEED HISTORY BY PERIOD TO DO EARNED VALUE SHOW HOW “ACTUALS” STRETCH THE EARNED VALUE AT THE DATA DATE IS ACCURATE. USE CDI’S OR OUTSIDE PROGRAMS TO STORE SPECIFIC PERIOD VALUES FOR REPORTING PURPOSES. CALC BCWS/BCWP ON TARGET 1 ONE PROBLEM IN APPLYING EVPM IS THAT THE BASIS OF THE EV CALC MUST BE A BUDGET THAT REFLECTS WHAT IS ACTUALLY GOING ON NOW. SOME SPECS AND CONTROL SYSTEMS PREVENT YOU FROM INCORPORATING CHANGES AS THEY HAPPEN. USE T1 FOR THE REAL BUDGET FOR INTERNAL REPORTS. (MTA) IN P3 - SHOW OPTIONS FOR EV - SHOW HOW IT CALC’S SURETRAK DOES BASED ON CURRENT ONLY EV PCT IS INPUT INPUT METHODS MANUAL, IMPORT, GLOBAL CHANGE RES VS ACTIVITY PCT - EACH RES CAN HAVE IT’S OWN PCT CALC ETC/EAC WITH GLOBAL CHANGE SHOW EXAMPLE OF GLOBAL CHANGE - SHOW AND EXECUTE.

4 Methods for capturing and storing data
Hammocks to store “non-schedule” scope Custom data items to store past period data and report “trends” Target 2 (or 1) to capture “performance baseline” Must use a “performance baseline” when the “Approved Baseline” doesn’t reflect scope. Code Fields to store alpa/numeric data HAMMOCKS HAMMOCKS OR ACTIVITIES WITH XF CONSTRAINTS ARE SELF STATUSING AND A GOOD PLACE TO CAPTURE LOE RESOURCES. IF ACTUAL COSTS CAN NOT BE COLLECTED AT THE ACTIVITY LEVEL - USE HAMMOCKS TO CAPTURE ACTUALS, THEN CODES TO REPORT AT THE HAMMOCK LEVEL - USE EV TO CALCULATE ETC AT THE ACTIVITY LEVEL CDI’S - PAST PER DATA/TRENDS CAN HAVE 8 CUSTOM DATA ITEMS AT ACTIVITY LEVEL AND 8 AT RESOURCE LEVEL. USE WITH P3 REPORT WRITER TO SHOW TRENDS AND CREATE CUSTOM COLUMNS THAT COMPARE CURRENT CPI TO PREVIOUS CPI AND FLAG “BETTER”, “WORSE” ... T2 FOR PERF BASELINE EXPLAIN CONCEPT OF PERF BASELINE - SOME SPECS REQUIRE T1 TO BE THE “APPROVED” BASELINE - USE T2 FOR YOUR OWN BASELINE - PARADE RECOGNISES AS AN ALTERNATE BASELINE. CODE FIELDS - ALPHA/NUMERIC HAVE USED TO CAPTURE PERIOD DATA FOR REPORTS BEFORE CDI’S WERE AVAILABLE

5 USING HAMMOCKS TO CAPTURE SUMMARY ACTUALS
Resource B A100-01 Resource A C D A100-02 Resource A C D A100-03 Resource A B C D (B+D) A C D Resource Pct BUDGET ACTUAL EARNED ETC EAC Method A100 USING ACTUALS FOR HAMMOCKS ONLY FUNTION OF THE HAMMOCK IS TO CARRY ACTUALS GETS IT’S DATES FROM THE DETAILED BUDGET CARRYING ACTIVITIES SHARES A COMMON CODE VALUE WITH DETAILED ACTIVITIES DETAILED ACTIVITY MUST HAVE ETC IMPORTED OR CALCULATED CAN NOT USE CPI OR SPI TO CALCULATE ETC OR EAC ON DETAILED ACTIVITIES UNLESS YOU EXPORT TO A DATABASE THEN IMPORT BACK TO P3 EASIEST IS TO TO A GLOBAL CHANGE ETC = BC - BCWP ASSUMES ORIG ESTIMATE IS OK FOR BAL OF WORK CAN DO A REPORT FROM P3 TO CALC ETC BASED ON CPI AT A SUMMARY LEVEL FOR COMPARISON AND FLAGGING 37 340 340 Import Actuals A100-01 100 100 100 Status Pct A100-02 25 250 63 187 187 Status Pct, GC ETC A100-03 150 150 150 TOTAL 33 500 340 163 337 677 Roll-up on Code Value

6 Methods for calculating and applying CPI/SPI
Linked spreadsheets to document earned value calculations Set the autocost rules to preserve, not destroy Global Change to calculate and store CPI/SPI Global Change to calculate EAC and ETC based on performance Arithmetic window in custom reports LINKED SPREADSHEET TO CALCULATE EV FROM THE P3 LOG WINDOW - ACCESS THE EXCEL BACKUP FILE SET AUTOCOST RULES DISCONNECT THE LINK BETWEEN PCT AND RD IF INPUTTING EV PCT AT THE ACTIVITY LEVEL. NO OTHER RULES IMPACT EV - BUT IF YOU IMPORT ACTUALS OR USE GC FOR ETC - TURN OFF RULES 4 & 5 GLOBAL & CDI’S CHG TO CALCULATE/STORE CPI/SPI GLOBAL CHANGE CPI = BCWP / CTD (CPI IS A CUST DATA ITEM) GLOBAL CHANGE TO CALC/STORE EAC/ETC GLOBAL CHANGE ETC = BC - BCWP (EAC IS CTD + ETC) ARITHMETIC WINDOW - CALC CPI/SPI, COMPLETE SHOW P3 REPORT WRITER EARNED VALUE REPORT

7 Example reports and how they are created
Graphs based on P3 Reports P3 Standard Reports SureTrak Standard Reports P3 Custom Reports P3 Graphics SureTrak Graphics EXAMPLE REPORTS AND GRAPHICS THE PROJECT CONTROL TEAM HAS MANY TOOLS AT THEIR DISPOSAL TO COMMUNICATE PROJECT INFORMATION IN A MANNER THAT IS TIMELY AND GETS THE POINT ACROSS. TIMELY USUALY MEANS THAT WE ARE USING THE P3 DATA BASE AS THE SOURCE GETTING TO THE POINT QUICKLY IS A CHALLENGE - THE AUDIENCE DOES NOT WANT TO READ THROUGH A LOT OF TABULAR DATA - BUT WANTS A QUICK OVERVIEW - WITH ACCESS TO BACKUP TABULAR DATA. THESE REPORTS ARE EITHER PRODUCED DIRECTLY FROM P3 AND SURETRAK OR BASED ON DATA DIRECTLY OUT OF P3 AND ST.

8 Graphs based on P3 reports
Bubble Reports Deliverables Performance Cost Status by Category Design Support Services Perfomance Performance Summary by Discipline Discipline Progress toward milestone GRAPHIC REPORTS USE GRAPHICS SOFTWARE - VALUES IN GRAPH TABLES COME FROM AND ARE BACKED UP BY P3 REPORTS.

9 Graphic report based on P3 Custom Report Data
D0301 XXXXXXXXXXXXXXX STATION & TUNNELS D0321 BIG CITY STATION D0322 PEDESTRIAN STATION D0326 CITY ROAD/RESTORATION/LANDSCAPE D0352 N. XXXXXXXXXXX SITEWORK D1610 TRACKWORK INSTALLATION V620 AUTOMATIC TRAIN CONTROL (D.F.I.) V710 ESCALATORS/ELEVATORS PAGE 1 D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED REPORT DATE 10AUG97 RUN NO XXXXXXXXXXXX TRANSPORTATION AUTHORITY START DATE 01JUN92 FIN DAT 15:26 RW-G1 BUBBLE CHART - PERF DATA DATE 31MAY97 PAGE NO ACTIVITY DESCRIPTION TOTAL PCT HOURS COST MHOUR COST TIME ID FLOAT COMPL CPI CPI PERF PERF LEFT C D0301 XXXXXXXXXXXXXXXXXX STATION-TUNNELS % | GREEN | GREEN | RED | C D0321 BIG CITY STATION % | YELLOW | YELLOW | GREEN | C D0322 PEDESTRIAN STA % | RED | RED | BLUE | C D0326 CITY ROAD/RESTORATION/LANDSCAPE % | | | GREEN | C D0352 N. XXXXXXXXX SITEWORK % | | | GREEN | C D1610 TRACKWORK INSTALLATION % | RED | RED | GREEN | Graphic report based on P3 Custom Report Data

10 MHOUR & COST PERF IF CPI = 0, SAY “ “ IF CPI > 0, SAY “RED” IF CPI > .95, SAY “YELLOW” IF CPI > .99 SAY “GREEN” TIME LEFT IF PCT = 100, SAY “BLUE”, ELSE SAY “GREEN” IF TF < 0, SAY “RED

11 + 16A PROJECT ADMINISTRATION + 3SS SPECIALTY SUB CONSULTANT
Project Start 06/01/92 Project Finish 06/30/00 Data Date 05/31/97 Run Date 08/10/97 © Primavera Systems, Inc. NF75 Sheet 1 of 1 D. R. McNatty & Associates C:\P3WIN\P3OUT\COST Date Approved Checked Reision Activity description Budgeted Cost to Date Cost to Complete Variance + 11F FACILITIES 8,893,420 6,994,104 1,899,357 -41 + 12S SYSTEMS 4,398,210 2,468,304 2,578,946 -649,040 + 15C PROJECT CONTROL 2,593,503 2,276,535 299,493 17,475 + 16A PROJECT ADMINISTRATION 935,329 886,000 339,148 -289,819 + 2SD SECTION DESIGNER 3,398,849 3,643,019 -244,170 + 3SS SPECIALTY SUB CONSULTANT 354,740 211,898 314,369 -171,527 + 4OD OTHER DIRECT COSTS 6,951,189 5,220,677 1,366,304 364,208 GRAPH DATA BASED ON P3 LAYOUT PAGE 3

12 Performance/Utilization by Function
PAGE 4 Hours by Function Hours Design Support to Construction Performance/Utilization by Function Percent

13 P3 Custom Report Report: RW-C XXXXX XXXXXX SEGX - NORTH XXXXXXXXXX EXTENSION REPORT DATE 11AUG97 Project Name: NF75 DATA DATE 31MAY DESIGN SERVICES DURING CONSTRUCTION PAGE NO. 1 | LOG INS | SHOP DRWGS | RFI Etc. | CHANGE NOTICE | AS - BUILTS | TO TAL º CONTRACT | | | | | | º | Budget Actual | Budget Actual | Budget Actual | Budget Actual | Budget Actal | Budget Actual º ARCHITECTURAL CIVIL ELECTRICAL FACILITIES-GENERAL MECHANICAL SYSTEMWIDE INTERFACE STRUCTURAL TRACK WORK UTILITIES = ====== ====== = ====== ====== = ====== ====== = ====== ====== = ====== ====== = ====== ====== =

14 Performance Summary by Contract Unit Based on data from P3 report G3
PAGE 6 Percent Complete

15 Performance Summary by Contract Unit (Report G3)
D. R. McNatty & Associates PRIMAVERA PROJECT PLASAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO XXXXXXXXXXXXXXXXXXXXXXXXXXXXX AUTHORITY JUN92 FIN DATE 30JUN00 16:44 RW-G3 PERF SUMMARY BY CONTRACT DATA DATE 31MAY97 PAGE NO. 1 DESCRIPTION EARLY EARLY BUDGET SCHEDULED PLANNED EARNED EARNED HOURS PCT HRS HOURS AT HRS AT START FINISH HOURS HOURS HRS PCT HOURS HRS PCT & TO DATE TO DATE & COMPLETION CMP PCT FACILITIES D0301 POLLYWOOD/LOWLAND STATION-TUNNELS JAN93A 19JUL % % % % D0321 ORANGE CITY STATION SEP92A 31MAY % % % % D0326 ORANGE CITY ROAD/RESTORATION/LANDSCAPE JUN97 04JUN % % % % D0352 POLYLWOOD SITEWORK JAN95 05MAY % % % % D1610 TRACKWORK INSTALLATION JUN96A 30JUN % % % % V710 ESCALATORS/ELEVATORS MAY97A 03JAN % % % % V740 VENTILATION EQUIPMENT MAR97A 30DEC % % % % V000 ENGINEERING SUPPORT JUL92A 30JUN % % % % V000 FACILITIES DIVISION JUL94A 30JUN % % % % 01JUL92A 30JUN % % % % SYSTEMS B620 AUTOMATIC TRAIN CONTROL (D.F.I.) FEB96A 20JUN % % % % S000 SYSTEMS DIVISION JUL92A 30JUN % % % % 01JUL92A 30JUN % % % % PROJECT CONTROL P000 PROJECT CONTROL JUN92A 31DEC % % % % 01JUN92A 31DEC % % % % PROJECT ADMINISTRATION A000 PROJECT ADMINISTRATION JUL92A 30JUN % % % % 01JUL92A 30JUN % % % % SECTION DESIGNER D0301 POLLYWOOD/LOWWLAND STATION-TUNNELS FEB93A 14MAR94A % % % % D0321 ORANGE CITY STATION MAY94A 01DEC95A % % % % D0322 PEDESTRIAN IRVINE STA SEP92A 28APR95A % % % % D0326 ORANGE CITY ROAD/RESTORATION/LANDSCAPE JUN97 27MAY % % % % 01SEP92A 27MAY % % % % ======== ======== ========== ========== ========== = ========== ========== = ========== ========== = ========== ========== = 01MAY92A 30JUN % % % % PAGE 7 Planned Earned Actual At Compl

16 Discipline Progress Toward In-Progress Design Submittal
Each Discipline provided a target percent complete for their work at the 60% submittal - earned value is measured based on earning rules developed with the baseline PAGE 8 Discipline Progress Toward In-Progress Design Submittal The purpose of this report is to demonstrate to the client that all disciplines are ready for the submittal

17 P3 & SureTrak Standard Reports
Earned Value Report - Resources Earned Value Report - Costs Earned Value Report - SureTrak P3 Standard Reports Show P3 EV report - Resources Show P3 EV report - Costs SureTrak Standard Report Show SureTrak EV report

18 P3 Resource Earned Value Report
D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO EARNED VALUE REPORT - QUANTITY START DATE 1JUN92 FIN DATE 30JUN00 20:24 RE-01 Resource Earned Value Report DATA DATE 31MAY97 PAGE NO. 1 COST PCT CUMULATIVE TO DATE VARIANCE AT COMPLETION...... ACCOUNT RESOURCE ACTIVITY ID CMP ACWP BCWP BCWS COST SCHEDULE BUDGET ESTIMATE A1F* FACILITIES A1FFA KQ-ACTUALS A1FRI KQ-ACTUALS A1FSF KQ-ACTUALS A1FUT KQ-ACTUALS L A1FAR JH-7FBB L A1FAR JH-7FBC L A1FAR JH-7FBE L A1FAR JH-7FZZ L A1FAR JH-7HAB L A1FAR JP-6ADP L A1FAR JP-6AZZ L A1FEL JP-6ADP L A1FEL JP-6AZZ L A1FEL JP-7FBB L A1FEL JP-7FBC L A1FEL JP-7FBE L A1FEL JP-7FBE L A1FST JH-7FBB L A1FST JH-7FBC L A1FST JH-7FBE L A1FST JH-7FZZ L A1FST JH-7FZZ L A1FST JH-7HAB L A1FST JP-6ADP L A1FST JP-7FBC L A1FST JP-7FBE L A1FTR KA-6TDP A1F* TOTAL =================================================================================================================================== PAGE 9

19 P3 Cost Earned Value Report
D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO EARNED VALUE REPORT - COST START DATE 1JUN92 FIN DATE 30JUN00 21:00 CE-01 Cost Earned Value Report DATA DATE 31MAY97 PAGE NO. 1 COST PCT CUMULATIVE TO DATE VARIANCE AT COMPLETION...... ACCOUNT RESOURCE ACTIVITY ID CMP ACWP BCWP BCWS COST SCHEDULE BUDGET ESTIMATE A1F* FACILITIES L A1FAR JH-7FBB L A1FAR JH-7FBC L A1FAR JH-7FBE L A1FAR JP-6ADP L A1FAR JP-6AZZ L A1FAR JP-6AZZ L A1FAR JP-6AZZ L A1FAR JP-7FBB L A1FAR JP-7FBC L A1FAR JP-7FBE L A1FFA KQ-C3AA L A1FFA KQ-C3AA L A1FFA KQ-C3AA L A1FRI KQ-6JAJ L A1FRI KQ-6JAJ L A1FRI KQ-6JAJ L A1FST JH-6CZZ L A1FST JH-7FBB L A1FST JH-7FBC L A1FST JP-6ADP L A1FST JP-7FBB L A1FST JP-7FBC L A1FST JP-7FBE L A1FUT JH-7FBE L A1FUT JP-7UAA L A1FUT JU-7UAA L A1FUT KA-7A7A L A1FUT KQ-CWACE A1F* TOTAL =================================================================================================================================== PAGE 10

20 PAGE 11

21 P3 Custom Reports Resource Performance by Workpackage
Cost/Schedule Performance Baseline and Change Orders Resource Performance Summary CPI Trend Report RESOURCE PERF BY WORKPACKAGE Show example of EMC reports COST SCHEDULE PERF Show example of EMC reports - point out baseline and change line items RESOURCE PERFORMANCE SUMMARY CPI TREND Show example using CDI’s

22 PAGE 12 PLANNED EARNED ACTUALS
D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG XXXXXXXXXXXXXX TRANSPORTATION AUTHORITY RW-G4 PERF SUMMARY BY Category PAGE NO. 1 DESCRIPTION EARLY EARLY BUDGET SCHEDULED PLANNED EARNED EARNED HOURS PCT HRS HOURS AT HRS AT START FINISH HOURS HOURS HRS PCT HOURS HRS PCT TO DATE TO DATE COMPLETION CMP PCT FACILITIES JUL92A 30JUN % % % % SYSTEMS JUL92A 30JUN % % % % PROJECT CONTROL JUN92A 31DEC % % % % PROJECT ADMINISTRATION JUL92A 30JUN % % % % SECTION DESIGNER SEP92A 27MAY % % % % ======== ======== ========== ========== ========== = ========== ========== = ========== ========== = ========== ========== = 01MAY92A 30JUN % % % % PLANNED EARNED ACTUALS

23 PAGE 14

24 CPI/SPI TREND GRAPH PAGE 15

25 P3 & SureTrak Graphics Performance Layout - P3
Performance Layout - SureTrak Performance Curves - P3 P3 Graphics Show Performance Layout Show Performance Curves SureTrak Graphics Show ST EV graphic curves

26 + PROJECT ADMINISTRATION + SPECIALTY SUB CONSULTANT
Performance Layout - P3 Project Start 06/01/92 Project Finish 06/30/00 Data Date 05/31/97 Run Date 09/04/97 © Primavera Systems, Inc. Early Bar Progress Bar Critical Activity NF75 Sheet 1 of 1 ENGINEERING CONSULTANT D:\DATA\EVPRES\PRIMA Date Approved Checked Revision + 11F + 12S + 15C + 16A + 2SD + 3SS + 4OD 1992 1993 1994 1995 1996 1997 1998 1999 2000 + FACILITIES + SYSTEMS + PROJECT CONTROL + PROJECT ADMINISTRATION + SECTION DESIGNER + SPECIALTY SUB CONSULTANT + OTHER DIRECT COSTS Resource/Cost Profile Legend Detail scale (left): X Cumulative scale (right): X x x 60 32 28 50 24 PAGE 16 40 20 30 16 12 20 8 10 4 1992 1993 1994 1995 1996 1997 1998 1999 2000 Current Estimate Earned Value Planned

27 Performance Layout - SureTrak
PAGE 17

28 Performance Curves - P3 PAGE 18

29 Summary Understand what Earned Value is and how you can apply it to your project Performance Measurement must be based on an accurate budget Use performance indices to provide perspective to your forecasts Define Earned Value at lowest budget level Measure and report performance at a level where responsibility can be recognized Communicate performance creatively UNDERSTAND WHAT EV IS AND HOW TO APPLY Just agree how to measure before you start Apply based on agreement PERF MEAS MUST BE BASED ON ACCURATE BUDGET Most failures of EV/PM is because budgets are inaccurate Must incorporate changes if resources are being expended USE PERF INDICES (CPI/SPI) TO GIVE PERSPECTIVE Check PM’s ETC against CPI/SPI to validate Use CPI and CPI/SPI to provide 2 of 3 points for 3 point forecasts DEFINE EV AT LOWEST BUDGET LEVEL If you can estimate there - you should be able to measure there ETC’s at the same level as original estimate DO NOT NEED ACTUALS at this level Show how lower level budget and ev are used with higher level actuals.