Presentation is loading. Please wait.

Presentation is loading. Please wait.

Skanska UK PAS2080 and the carbon process

Similar presentations


Presentation on theme: "Skanska UK PAS2080 and the carbon process"— Presentation transcript:

1 Skanska UK PAS2080 and the carbon process
Welcome & thanks for joining us In this presentation, we’ll explain: What impact do buildings have on climate change? What Skanska UK’s goals are Why supply chain emissions are so important What can we all do collectively to reach those goals Ruth Finlayson Environment and Carbon Manager – Infrastructure

2 Why low carbon? “ The defining environmental issue of our generation is accelerated climate change. “ We are putting carbon emissions reduction where it belongs: at the front and centre as one of the largest challenges the construction industry faces.” Gregor Craig, President and CEO, Skanska UK Skanska UK’s President and CEO, Gregor Craig, says that accelerated climate change is the defining environmental issue of our generation. He says that Skanska UK is taking an industry-leading position on reducing carbon emissions: we have set a target of net-zero emissions by This will include all the emissions produced by our supply chain, from their work on our projects. Greg says that reducing emissions is one of the most important challenges the construction industry faces. He believes it should be an industry priority to reduce emissions, and that all construction companies should be aiming for net-zero emissions – including the supply chain. He says the sector also faces significant efficiency and productivity challenges, and that there is a body of evidence that links carbon with cost. Greg says that delivering better, and cheaper, solutions for our customers is another compelling reason to take carbon reduction seriously. November 2019 PAS2080 and the carbon process

3 Net-zero carbon by 2045 Skanska’s target: including our suppliers
This is our main target. We aim to be carbon-neutral, with net-zero emissions, across our portfolio of projects by 2045. This includes all the supply chain emissions produced from work on our projects, during construction or maintenance work. We think that this is an achievable goal. November 2019 PAS2080 and the carbon process

4 Skanska UK direct emissions plus supply chain emissions
The whole story Skanska UK direct emissions plus supply chain emissions When we add in our estimate of supply chain emissions, it shows our real impact is around 10 times that. Here is a key figure to remember: Between 2010 and 2018, when we include our supply chain emissions, Skanska UK has emitted over 3 million tonnes of carbon. That’s equivalent to burning around 18,000 acres of forest, that’s an area 8 times the size of Richmond Park. November 2019 PAS2080 and the carbon process

5 PAS2080 and carbon management
Creates a strategy for carbon management across the life of a project To deliver the benefits the whole value chain should be aligned and consistent in their approach PAS2080 provides the framework for a carbon management process November 2019 PAS2080 and the carbon process

6 Cut carbon – Cut cost Build nothing Build less Build clever
Figure Adapted from PAS 2080 Build nothing Build less Build clever Build efficiently 80% 50% 20% 100% November 2019 PAS2080 and the carbon process

7 Digital integration BIM model GIS data
Share information across the common data environment to manage the flow of decisions across disciplines Allow for design iterations to calculate carbon/cost changes GIS data Collaborative solutions for a complex environment November 2019 PAS2080 and the carbon process

8 Carbon/cost baseline Using the cost model we calculate the carbon equivalent to use as a baseline for carbon reduction targets Identify carbon hotspots and big wins Skanska UK believes it’s important to tell the whole story, when it comes to carbon emissions. Let me show you the size of the difference for Skanska UK. Looking back to 2010, you can see the carbon emissions that we’ve traditionally reported, from our own offices and cars. You can see it fluctuates at around 35 thousand tonnes of carbon every year. November 2019 PAS2080 and the carbon process

9 National Grid PORR Skanska A Hak Tender stage Revised design stage
November 2019 PAS2080 and the carbon process

10 Skanska Revised design stage Tender stage Tender stage
November 2019 PAS2080 and the carbon process

11 Carbon workshops Review the project for sustainable design, materials/resources, efficiencies, lean construction and carbon reduction Decision ID Package Element Description of decision Category Potential Benefits Potential Impact Decision Status (Design) Action Required 001 SITE SETUP Site Lighting Photovoltaic lighting to be considered for enabling works and main works lighting. CARBON 1. Reduced carbon 2. Reduced cost MEDIUM IMPLEMENTED Procure solar lighting - Prolectric 002 Generator fuel type Use waste derived fuel (diesel) to power TBM and site generator. 1. Reduced cost 2. Reduced carbon REJECTED Make contact with fuel alternatives 005 CIVILS Concreting works 4-5 mixes approved with cement replacements 1. Responsible sourcing 2. Reduced carbon 3. Use of recycled material (natural resource saving) ACCEPTED IN PRINCIPLE What is in the tender as baseline? 006 Demobilisation/ Demolition Identify reuse and recycling options 1. Reduced cost 2. Reduced carbon 3. Reduced Waste HIGH INVESTIGATING Develop demobilisation/ demolition plan. 007 Drainage - SuDS Sustainable drainage system WATER Minimised impact on local watercourses and best practice pollution control. Write best practice following SUDS completion. Site lighting (site setup) Photovoltaic lighting to be considered for enabling and main works. Benefits: Reduced carbon Reduced cost Carbon Impact: Medium Generator fuel (site setup) Use waste derived fuel (diesel) to power TBM and site generator. Benefits: Reduced carbon Reduced cost Carbon Impact: Medium Concreting 4-5 approved cement mix replacements. Benefits: Reduced carbon Responsible sourcing Recycled – cost saving Carbon Impact: Medium Demobilisation/ demolition Identify reuse and recycling options. Benefits: Reduced carbon Reduced cost Reduced waste Carbon Impact: High Drainage – SuDS Sustainable drainage system. Benefits: Minimised impact on local watercourses Best practice pollution control Water Impact: Medium November 2019 PAS2080 and the carbon process

12 Carbon workshops Review the project for sustainable design, materials/resources, efficiencies, lean construction and carbon reduction Decision ID Package Element Description of decision Category Potential Benefits Potential Impact Decision Status (Design) Action Required 001 SITE SETUP Site Lighting Photovoltaic lighting to be considered for enabling works and main works lighting. CARBON 1. Reduced carbon 2. Reduced cost MEDIUM IMPLEMENTED Procure solar lighting - Prolectric 002 Generator fuel type Use waste derived fuel (diesel) to power TBM and site generator. 1. Reduced cost 2. Reduced carbon REJECTED Make contact with fuel alternatives 005 CIVILS Concreting works 4-5 mixes approved with cement replacements 1. Responsible sourcing 2. Reduced carbon 3. Use of recycled material (natural resource saving) ACCEPTED IN PRINCIPLE What is in the tender as baseline? 006 Demobilisation/ Demolition Identify reuse and recycling options 1. Reduced cost 2. Reduced carbon 3. Reduced Waste HIGH INVESTIGATING Develop demobilisation/ demolition plan. 007 Drainage - SuDS Sustainable drainage system WATER Minimised impact on local watercourses and best practice pollution control. Write best practice following SUDS completion. Site lighting (site setup) Photovoltaic lighting to be considered for enabling and main works. Benefits: Reduced carbon Reduced cost Carbon Impact: Medium Generator fuel (site setup) Use waste derived fuel (diesel) to power TBM and site generator. Benefits: Reduced carbon Reduced cost Carbon Impact: Medium Concreting 4-5 approved cement mix replacements. Benefits: Reduced carbon Responsible sourcing Recycled – cost saving Carbon Impact: Medium Demobilisation/ demolition Identify reuse and recycling options. Benefits: Reduced carbon Reduced cost Reduced waste Carbon Impact: High Drainage – SuDS Sustainable drainage system. Benefits: Minimised impact on local watercourses Best practice pollution control Water Impact: Medium Implemented Rejected Accepted Investigating Implemented November 2019 PAS2080 and the carbon process

13 2,298 tCO2e 2,040 tCO2e 11% Launch pit Tender stage Original baseline
Reduction in GHG emission 2,298 tCO2e 2,040 tCO2e Tender stage Original baseline November 2019 PAS2080 and the carbon process

14 Highways works November 2019 PAS2080 and the carbon process

15 Carbon breakdown – design
November 2019 PAS2080 and the carbon process

16 Carbon breakdown – structures
November 2019 PAS2080 and the carbon process

17 Carbon breakdown – temporary works
November 2019 PAS2080 and the carbon process

18 Carbon breakdown – drainage
November 2019 PAS2080 and the carbon process

19 Work with the supply chain Practical solutions to reduce carbon and cost
Autonomous electric plant and vehicles Zero carbon compound Low temperature asphalt Precast CEMFREE concrete Recycled aggregate Recycled steel piles November 2019 PAS2080 and the carbon process

20 Questions? November 2019 PAS2080 and the carbon process


Download ppt "Skanska UK PAS2080 and the carbon process"

Similar presentations


Ads by Google