1 Basement Construction

2 1. Casting of The Bored Piles
Setting up of King Post Casting of 1st Storey Slab 1st storey structural slab as construction stage Diaphragm Wall King Post Bored Pile

3 2. Excavation to bottom of foundation

4 3. Casting Foundation and B3F Slab
B2F Columns B2F Slab B3F Columns

5 Ground Anchor System

6 1st Storey Slab

7 Excavation at Block A using long-arm excavator

8 Excavation work in progress at Area M near Block 190

9 Ground anchor works along Toa Payoh Lorong 6 near MRT Line

10 Xypex DS2 being applied at basement 3

11 View of basement 3 from Blk D

12 View of basement 3 from Blk 188

13 Basement Waterproofing System
Basement 3 Slab Silica Fume concrete used Xypex Concentrate DS2 added on surface prior to power floating providing waterproofing and abrasion resistance. Slab thickness 700 to 1200 Concrete G40 Xypex Concentrate DS2 Xypex is a unique chemical treatment for waterproofing and protection of concrete. The active chemicals react with moisture of fresh concrete causing a catalytic reaction which generates a non-soluble crystalline formation of dendritic fibres within the pores and capillary tracts of the concrete. Thus the concrete becomes permanently sealed against the penetration of water or liquids from any direction