1 Avatar ICD-10 Upgrade and Enhancements Project
March 26, 2014 Implementation Phase Presenters: Terry Reusser, Michael Snouffer, Jeff Esquibel

2 Avatar/myAvatar Overview
Medical record and billing system used in seven facilities across the state FBMC, NMBHI, NMRC, NMSVH, SATC, Turquoise Lodge, LLCP Facilities provide psychiatric, long-term, rehabilitative, behavioral health and drug treatment programs First implemented at NMRC in 2001 Original project know as Facility System Enhancement Project (FSEP) Rolled out to remaining facilities over a three year period Last major upgrade in 2011 Platform conversion from AIX to Windows New hardware All application modules and components upgraded in preparation for myAvatar Newest version called myAvatar Needed for ICD-10 Will run on existing hardware

3 Project Overview Business Objectives Technical Objectives
Upgrade Avatar to myAvatar to meet federal required ICD-10 code sets for HIPAA covered entities. Implement enhancements to myAvatar. Train all staff on the use of both the new version of myAvatar, enhancements and ICD-10 coding. Technical Objectives Create requirement, configuration documents and timeline. Implement myAvatar upgraded in test environment. Develop test plan and scripts. Execute test scripts in test environment. Track and fix defects. Upgrade myAvatar upgrade in production. Develop test plan and scripts for enhancements. Execute test scripts in test environment. Track and fix defects. Implement myAvatar enhancements in production.

4 MyAvatar Enhancements
Laboratory Information Management System (LIMS) for use at NMBHI Order Entry for use at NMBHI Order Connect for use at NMBHI Incident Tracking for all facilities

5 Project Highlights Funds requested for this certification: $460,000
Funds requested in Initiation Phase: $190,000 Project Management and IV&V Project Phase Certification Request: Implementation Project Start Date: December 2013 Project End Date: March 2015 Total project value: $650,000 Total expended to date: $0

6 Completed Planning Phase Activities
Vendor contract negotiated and in review Detailed Schedule, Budget and Communication Plans completed Resources identified and committed Project team Business process team Superusers IV&V contract negotiated and in contract review Project Management Plan completed TARC exception granted

7 Implementation Phase Activities
Project Management contract executed IV&V contract executed Vendor contract executed Track risk and issues Create and execute detailed test plan and test scripts for myAvatar upgrade and enhancements Create and execute detailed training plans for myAvatar upgrade and enhancements Create training documentation for myAvatar upgrade and enhancements

8 Implementation Phase Activities continued
Establish test and training environments for myAvatar upgrade and enhancements Test myAvatar upgrade and enhancements Place myAvatar upgrade and enhancements into production

9 Tentative Project Timeline

10 Questions?