Executive Sponsor: Tom Church, Cabinet Secretary
NM Department of Transportation (NMDOT) Document Imaging Implementation and Content Migration Executive Sponsor: Tom Church, Cabinet Secretary Business Owners: David Coriz, NMDOT Records Management Bruce Oakeley, NMDOT ISM Bureau Chief IT Records Management Division Document Conversion – EDMS System Project Certification for Initiation and Planning January 22, 2014
2
Overview Project Goals: 1) Replace an obsolete document management solution with modern document imaging technology that NMDOT can expand on for many years. 2) Migrate the current data to a new repository. Business Problem: The current document imaging system (IBM FileNet) is 13+ years old and NMDOT has been having some major problems with the software. The current, outdated system has 4+ terabytes of vital records that need to be preserved for many years to come. Desired Outcomes: Continue to certify electronic content as official Public Records: Improve service delivery to constituents Improve productivity Achieve cost savings Reduce risks associated with paper records. Certification Request: Approval of Initiation and Planning of this project, using $730,000 of NMDOT Road Funds.
3
Electronic Data Management Solutions (EDMS) provide opportunities to:
Business Opportunity Electronic Data Management Solutions (EDMS) provide opportunities to: Provide better, faster, expanded services to constituents Deploy e-Government and “paperless” solutions Reduce costs, streamline processes, improve productivity Automatically control compliance and risk factors Provide audit and security to meet mandated requirements Assess and improve records retention programs Collaborate with the State’s Multi-Agency initiative.
4
NMDOT expects significant savings in:
Cost Savings NMDOT expects significant savings in: COM systems hardware and maintenance expenses Microfilm media expenses Microfilm hardware maintenance expenses Distribution expenses for COM and microfiche output Microfiche/microfilm reproduction expenses Storage space Labor for key entry, filing, and manual retrieval Report reproduction and distribution (avoiding millions of dollars in paper, toner and ink costs).
5
Risks of Keeping the Status Quo
Costs of printing documents that originate in electronic format Costs of maintaining NMDOT Official Public Records in paper Cost of locating records Physical storage costs Legal costs File maintenance labor costs Vital data loss for maintaining on outdated hardware/software Security risks Poor environmental conditions at current, off-site storage facility.
6
Major Deliverables by Project Phase
Due Date Major Deliverables Initiate 1 week Communication Plan. Escalation Plan. Timeline Schedule. Project collaboration Analyze 5 weeks Enterprise Foundation Definition document. Functional Requirements Document. Technical Architecture Document. Solution Design Document Build| Hardware installation 4 weeks Install infrastructure hardware components. Installed storage infrastructure. Install virtualization and Operating System Software components. Build | Software Installation 3 weeks Documentum Platform Bundle Install. Out-of-the-box Documentum software install. Build | Development Configure Documentum environment with taxonomy and library services. Configure retention policies. Migrate content from FileNet Imaging Services to Documentum. Migration of COLD data. Utility to ingest content from Fileshare. Updated Kofax release scripts to export to Documentum. Build | Test 4 weeks Completion of System Test Scripts procedure. Defect list tracking reports for User Acceptance Testing (UAT). Execution of User Acceptance Testing (UAT). Train 2 weeks Completed Training. Quick Reference Guide. System as-built documentation Deploy System go live Close Project Review Meeting. Project Archival Activities. Follow-up Activities.
7
Total Cost of Ownership
Description FY14 FY15 FY16 FY17 & After Training On Site 17,325 Consulting Services System Implementation 525,099 Hardware Servers 20,000 Software Licenses 595,824 Annual Maintenance 134,220 Contingency 5 % Reserved 63,623 Total $1,336,091 $154,220
8
NMDOT Document Imaging Implementation and Content Migration
Questions?