Download presentation
Presentation is loading. Please wait.
Published byJessie Bennett Modified over 5 years ago
1
How Much Hidden Profit is There in Self-Performed Work?
Debbie Townsend R.L. Townsend & Associates, LLC September 10, 2019
2
What is self-performed work?
Construction Scopes Performed by the Prime Contractor Benefits to the Owner per CM: Control of Schedule Cost Savings Quality Safety
3
What type of work is included?
Typical Bid Packages Include Concrete & Drywall General Requirements or General Works Examples include: Protection of work, Layout, Equipment, Cleanup, SWPPP, Safety Related Work Miscellaneous Scopes of Work Examples include: Scopes to assist other trades with their work
4
Story 1 BIo Containment project
5
Story 1 - Bio Containment care unit
18 Month Renovation Project 6 Rooms, State of the Art, Special Surfaces & Negative Airflow $11MM to $12MM GMP Heavy MEP - 50% of Cost of Work Tight Budget Contract Language for Self-Performed Work is “cost plus 7.5%”
6
Bio Containment Building – CMAR Contract
Out of State Contractor – Low balled GC’s & Fee 3rd Party Project Management Representative Knowledgeable Owner
7
Owner problems from the start
Contractor Staffed the Job with Inexperienced College Graduates The Project Manager that was “Sold” with the Job Moved to Another Project at about 25% Complete The Replacement Project Manager was Fired Soon Thereafter The Replacement for the Replacement PM was the Superintendent
8
You know you have a problem when…….
Contractor Submits a Self-performed Bid Package of $5MM. Many Components were Lump Sum. Contractor agreed to $2MM Self-Performed Work (General Works) to be Billed Cost Plus 7.5% Contractor then Billed Change Orders on a Lump Sum Basis Contractor added General Works to 100% of the Change Proposals. Contractor thinks the GMP is an Open Checkbook and the Contingency is “his money” Contractor Does Not Provide Buyout Info, PC Log, Allowance Log, etc. Owner Reps Position… “Will resolve in the audit”
9
General works Billing
10
The audit of self-performed work
The Audit Started when the Project was Close to Substantially Complete The Lump Sum CO Issue had to be Resolved The Pay Apps were Reviewed and Multiple Duplicates Identified The Contractor Stated there were No Duplicate Charges
11
Examples of a duplicate – General Works
Base Contract Billed at Cost plus 7.5% Lump Sum Change Orders CM Billed $77,862 for Casework as a Base Contract Cost Plus 7.5% in Pay App 19 The Subcontract Amount was $77,862 CM billed a Lump Sum PCI for Drawing Updates in the Amount of $148,155 in Pay App 20 The $148,155 Included the Same $77,862 that was Billed in Pay Application 19
12
more examples Description of Work Amount Location of Billing Invoice #
Scaffolding $9,760 Billed on Pay App 10 51A0175 Billed on Pay App 11 $2,318 Billed on Pay App 22 51E0143 Billed in a PCI on PA 25
13
Another duplicate – crane rental
Pay App # Amount Outcome of Cost Review 16 $12,826 Verified to Job Cost $ 2,680 Previously billed to another project $ 4,587 Also included in a PCI 19 $ 4,400 23 $ 2,835 25 Duplicate Charge from PA 19 Duplicate Charge from PA 23 Total $34,563
14
Estimated Overcharges = $1,765,176
And then what happened? We Considered the Pay Apps as Unreliable Self-Performed Work Job cost was Requested Multiple Times but Not Received We were at an Impasse with the Contractor The Owner asked us to Write a Report with an ESTIMATE of the Overcharge Estimated Overcharges = $1,765,176
15
The story continues. . . Contractor Provided Job Cost and Labor Reports for Self-Performed Work Based on the New Information, we Revised the Estimate of Overbilling to be $900,000 Contractor said the Job Cost Reports were Not Accurate as they did not Include All Costs
16
The real cost……according to the contractor
Contractor then Manually Prepared a List of Invoices, Payroll, Rental Charges, Job Cost Reports This Report was Provided as “the Accurate Job Cost”
17
Example of contractor’s list of cost
Invoice Date Invoice Description Invoice Amount X Job Costing Transaction Report $ 23,052.53 $ $ Invoice $ $ Invoice Floor Mats $ Home Depot $ Hardware $ Sign $ Edge Guard Rental $ 7,320.38 Supplies $
18
was the report accurate??
We Found: Rental Equipment Charges were Overstated Subcontract Charges were Overstated Numerous Duplicates were Identified Payroll was Overstated Fee was Overstated Lump sum CO was Added
19
What happened next? Contractor Continued to Claim there were no Duplicates We had a Meeting with Owner and Contractor to Discuss Next Steps Owner made a Few Concessions to Resolve Issues and told the Contractor to Correct the Audit Issues We Flipped our Audit Approach from Identifying Credits to Identify What Should be Billed
20
How did it get resolved? Compared his Final Numbers with Our Final Numbers He Continued to Present Additional Charges Payroll from Another Job Duplicates from his Job List Duplicate Fringe Benefits Costs Accounted for on the Main Job
21
Its not over until its over
Owner Agreed to some Small Concessions Owner Finally said we are DONE. Prepared a CO and PA Contractor Retired
22
$5 MM Self Performed work
Story 1 - Final results $12 MM Final GMP $5 MM Self Performed work $856 K in Overcharges Identified and Credited in Self-Performed Work 17% of Self-Performed Work 7% of GMP
23
Story 2 College Building
24
Story 2 – academic building on a college campus
New Construction $25 MM GMP Contract included Cost Plus a 7.5% Fee Language for Self-Performed Work Contractor Previously Hired for Multiple Jobs by Owner
25
Academic building - Participants
Owner Senior Project Manager Owner Project Manger Contractor
26
You know you have a problem when…..
Contractor submitted multiple scopes of miscellaneous work which were not included in any bid package. Therefore, No Competition Contractor Awarded Themselves Multiple Scopes on a Lump Sum Basis Totaling $1.5MM. The Owner Rep Challenged the Scopes and the Lump Sum but was Overruled After the Work Started, the Contractor Submitted Lump Sum CO’s with Minimal backup. The Owner Rep Challenged the CO Process but was Overruled
27
At 50% completion……. The CM wanted to Convert the GMP to Lump Sum
The Owner PM Requested us to Audit the Terms The Conversion was not in the Best Interest of the Owner The Owner PM had a Difficult Time Convincing the Owner Senior PM not to Convert
28
The audit of self-performed work
At Substantial Completion we were asked to Perform a Close Out Audit Contractor would Not Provide Job Cost for Self-performed Work Contractor Only Answered Questions they wanted to Answer We Identified Many Duplicates Billings We Identified Potential Duplicate Scope We Identified Excess Pricing of Scope
29
Who Rents a crane on an hourly basis for 3 months?
Self Performed Work Who Rents a crane on an hourly basis for 3 months?
30
Duplicate charges – contractor gave credits
Contractor billed the Scope of Work in SPW CP 11 AND as a direct cost in the Main Job Scope Amount SPW Change Proposal Direct Cost – Main Job Provide Select Fill $ 4,113 CP 11 Pay App 6 Fill Dirt Delivered to Site $ 8,754 $ 4,759 Grading & Compacting $ 6,569 Haul Off Drilling Spoils $10,400 Total Duplicate Cost $34,595
31
Duplicate charges – contractor gave credits
Contractor billed the same Costs to Self-Performed Work and the Main Job Scope Amount Temporary Labor $ 27,975 Trailer Decks $ 6,898 Temporary Fencing $ 4,759 Remove Elevator Spoils $ 6,400 Building Pad Prep $ 9,237 Total Duplicate Cost $55,269
32
Is this Duplicate scope?
Self-Performed Scope included “Weekly Cleaning & Debris Removal” $150,421 PLUS $25,822 for “Supplemental Clean Up” $76,650 was also billed to General Conditions for Trash Removal and Dumpster The GMP included $108,262 for Weekly Cleanup & Dumpster AND……. Subcontracts included daily cleanup plus composite clean-up crew
33
Is this Duplicate scope?
Self-Performed Subcontract included “Install HM Frames” $20,247 Drywall Subcontract:
34
Is this overstated cost?
Self-Performed Work Subcontract GMP Self-Performed Scope included “Roof Blocking” $150,525 In wall blocking = $61,115 Roof blocking = $89,410 Total In Wall & Roof Blocking = $150,525
35
Was this scope performed?
Self-Performed Scope included “Commissioning” $99,528 Owner PM Maintained that Commissioning was Performed by the Contractors General Conditions Personnel Contractor said they Received a Bid, and it was too high so they “self-performed” commissioning without Owner approval. Contractor did provide a credit of $49,764 for work they couldn’t support.
36
When you don’t hear what you expect, ask around
Talked to: Contracts Manager Attorney Regional Manager Associate Chancellor Other Owners
37
What did we find out? Attorney said the Audit should trump the Approvals by the Owner PM The Associate Chancellor not happy with Sr. Project Manager converting GMP contracts to lump sum on Previous Projects Regional Management not Aware of Sr. Project Manager allowing Contractor to Modify Contract Language Sr. Project Manager – Not Fond of Audits. Not Fond of Controls. Has Friends in High Places Prior Employee of Contractor said they automatically add 33% OH&P to all Self-Performed Work
38
They Deemed this to be a “Lessons Learned” Project
The decision… Management tried to Obtain the Self-Perform Work Job Cost Multiple Times After Numerous Meetings, Phone Calls, etc. it was Decided, Since the Owner PM had Approved the lump sum Self- Performed Work, they would not change that decision They Deemed this to be a “Lessons Learned” Project
39
How did it end? Credits from the Contractor were Limited to $170,000 Senior Project Manager has been Moved to a New Position Regional Management is Going to Minimize use the Contractor Regional Management has Started Training on Contract Language, etc.
40
Story 3 New High School
41
Story 3 - High School New Construction GMP $107,000,000
27 Month Schedule Contract Language for Self-Performed Work is “Cost Plus 15%” Audit involved prior to the CM Award
42
The contract language is the key to success
The maximum fees payable to the Contractor on self-performed work will be 15% on the contractually defined reimbursable cost of self-performed labor, labor burden, materials, and equipment. The maximum fees payable to the Contractor on specialty sub-subcontract work necessary for the self-performed scope of work will be at 5% of the cost of the sub-subcontract work. If the contractor does not self-perform the majority of the scope of self- performed work and as a result subcontracts a significant portion of the scope of work to another trade contractor, then no self-performed work fees will apply to the cost of any such sub-subcontracted work.
43
High school participants
Texas Contractor they had worked with before Owner – District Superintendent Owner – District Assistant Superintendent Owner – CFO Owner – Project Manager Owner – Attorney
44
You know you have a problem when…….
The Contractor wants to Renegotiate the Contract Language for Self-Performed Work The Owner said NO
45
You know you still have a problem when…….
The Contractor doesn’t turn in the GMP until 4 Days Prior to the Board Meeting They Submit a Letter to the PM with $7MM of Potential Self-Performed Scope The Assumption and Clarifications included Language which Changed the Self-Performed Work to Lump Sum They include a fixed Labor Burden Percentage
46
3 days of intense Battle between Owner, Attorney & Contractor
What to Do? 3 days of intense Battle between Owner, Attorney & Contractor On day 3, the Attorney said follow the Contract or be Terminated
47
3rd time is the charm….or not
Letter from the contractor after the sub bids were vetted
48
Strategies to Make up Fee – Charge for work not done
Audit Actions taken to Prevent Charges Billed for Work Not Done: Walk the Site Monthly Drone Pictures Uploaded Weekly Assistant Superintendent attends OAC Meetings
49
Strategies to Make up Fee – Excess charges for work performed
Review of Pay App Identified 40% Labor Burden on Hourly Workers Training Cost Billed Temp Labor Billed with a 37% MU Subs used for the Main Jobs were also used for SPW 25% for Indirect Cost Billed 15% fee on All Cost
50
Estimate of overcharge as of 8/31/19
$300,000 in Overhead Cost 12% overcharge for Labor Burden $100,000 for Cell phone, IT, Travel & Truck Allowance $10,000 in OH&P for Sub already working on the project $10,000 for Equipment Training $10,000 for Drone Pictures $15,000 for General Conditions Costs Contractor Owned Equipment to be Calculated
51
Estimate of overall cost avoidance by not going with lump sum SPW
Description Amounts Original Budget $4,230,797 Estimate of Spend based on current billings ($2,800,000) Estimated Savings $1,430,797 Plus: Estimate of Overhead Recovered $ 500,000 Estimate of Total Savings $1,930,797
52
What is currently being done?
The Owner has put the Contractor On Notice Regarding the OH&P The Owner Is Waiting Until the End of the Project to Negotiate the Final Amounts
53
Summary Cost Plus a Fee Contract Language
What is the right fee if any? Require REAL competitive pricing Do not Modify the GMP Do not Allow any Letters, Change Orders, etc. which Modify the Terms of the Agreement
54
Summary - Continued Develop a Strong Advocate
Review the Work Being Done Monthly Review How the Work is Being Billed Monthly Communicate on a Regular Basis with the Owner
55
questions
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.