Progress Report GUID on Information Systems Audit

Similar presentations


Presentation on theme: "Progress Report GUID on Information Systems Audit"— Presentation transcript:

1 Progress Report GUID on Information Systems Audit
A presentation by SAI India for 28th INTOSAI WGITA-FIJI

2 Background New project taken at the behest of FIPP, as part of SDP of IFPP Project Consolidating and aligning guidance on IT Audit with ISSAI 100 Project now titled – Guidance on Audit of Information Systems IFPP reserves series for guidance on IT Audit ISSAI 5300 to be taken as GUID 5100 in IFPP Approved Project Duration: to (24 months) Project in line with FIPP deadline for submission before XXIII INCOSAI 2019 Members of Project Team Lead: India Members: Australia, Poland, Russia, USA Project Progress Report on Revising GUID on IT Audit – Presentation by SAI India

3 Revising GUID on IT Audit
Project Objectives Draw upon existing Standards (ISACA), guidelines and frameworks (COBIT) and similar material related to IT audit Align with ISSAI 100, 200 (FA), 300 (PA) and 400 (CA) Consult material contained in GUID 5450 and other guidance To be overarching, general principles GUID on IT Audit and provide basis for GUIDs on IT related specific subject matter Require alignment with ongoing WGITA Project for revising ISSAI 5310 on IT Security Audit (now GUID 5101) Revising GUID on IT Audit

4 GUID 5100: Project methodology – Drafting Process
GUID developed keeping in mind the FIPP’s requirement: GUID should establish clear linkages with Financial, Compliance, Performance audit Provide reference to different aspects of IT Audit for which subject specific GUIDs are proposed to be developed. Follows the Due Process for Professional Pronouncements. Inputs and comments from CAS, PAS and FAAS taken while developing the exposure document. FIPP’s drafting convention for GUID followed. Project Progress Report on development of GUID Presentation by SAI India

5 Project Stages and Status: GUID 5100
Stage-1: Project Initiation Document approved by FIPP in October 2017. Stage-2: Exposure Draft Completed and circulated in September, 2018; Approved by Chair, KSC, and FIPP in November 2018. Uploaded ( in Jan19 for comments by 24 April. Stage-3: Endorsement Version Will be developed based on the comments received. To be submitted to FIPP at their August 2019 meeting Stage-4: Final GUID 5100 Final GUID 5100 to be submitted to INCOSAI 2019 Project Progress Report on development of GUID Presentation by SAI India

6 Proposal before WGITA WGITA members are requested to:
Take note of the Progress Report Provide comments on the exposure draft before the due date of 24th April 2019. Draft GUID exposed on for comments. Project Progress Report on development of GUID Presentation by SAI India