Presentation to the Portfolio Committee on Trade and Industry on the NRCS’ Third Quarter Performance Report for the 2016-17 Financial Year Mr Edward.

Similar presentations


Presentation on theme: "Presentation to the Portfolio Committee on Trade and Industry on the NRCS’ Third Quarter Performance Report for the 2016-17 Financial Year Mr Edward."— Presentation transcript:

1 Presentation to the Portfolio Committee on Trade and Industry on the NRCS’ Third Quarter Performance Report for the Financial Year Mr Edward Mamadise Acting Chief Executive Officer 14 February 2017

2 NRCS representation Mr. Edward Mamadise Ms. Elmarie Cornelius
Acting Chief Executive Officer Ms. Elmarie Cornelius Acting Chief Financial Officer Ms. Meisie Katz General Manager Foods and Associated Industries Mr. Bongani Khanyile General Manager Electro-technical Mr. Edward Matemba Manager: Strategy and Risk

3 Scope of Presentation Status on Portfolio Committee Commitments
Electro-technical LOAs Progress on IT commitments Strategic Overview of the NRCS Strategic Goals, Mission, Vision Legislative mandate Regulated industries Highlights Performance against Targets Non-Financial Performance Financial Performance Challenges

4 NRCS Strategy, Mission and Vision
NRCS Strategic Goals Mission & Vision To ensure an optimally capacitated institution To develop, maintain and administer compulsory specifications and technical regulations To maximise compliance with all specifications and technical regulations To inform and educate our stakeholders about the NRCS Mission To develop compulsory specifications and technical regulations, and maximise compliance of regulated products and services Vision A credible and respected regulator for the protection of the public, the economy and the environment

5 Legislative Mandate Mandate of the NRCS is derived from the following Acts. National Regulator for Compulsory Specifications Act (Act No. 5 of 2008) Legal Metrology Act (Act No. 9 of 2014) National Building Regulations and Building Standards Act (Act No. 103 of 1977) The Foodstuffs, Cosmetics and Disinfectants Act (Act 54 of 1972)

6 Industries regulated by NRCS
Industry Sector Product regulated / Service rendered Automotive Vehicles, Replacements components, Manufacturers Importers and Builders Chemicals, Materials and Mechanicals Building materials (Cement. Treated timber, Safety glass and other safety glazing material). PPE (Safety Footwear, Swimming aids, personal flotation devices, respirators Electro-technical Electrical appliances and products, Electronic appliances and products Foods and Associated Industries (FAI) Fishery products, canned meat and processed meat Legal Metrology Calibration of measuring instruments, weights, measures and gaming equipment Building Regulations Ensure uniform interpretation of National Building Regulations and Standards Act, administer review Board

7 Key highlights NRCS conducted 10 694 inspections
5 988 fishery and associated products consignment/productions 4 706 inspections for automotive, electro-technical, chemicals, materials and legal metrology related products. Non- Compliant Products NRCS found non-compliant products estimated at R69 million. Automotive – Value of Non-compliance R2m. Brake friction material containing asbestos CMM – R0,832m. Disinfectants, paraffin stoves plastic bas & swimming aids Electro-technical – Value of Non-compliance R0,987m. CFL’s, lamp holders, luminaires, cord extension sets, incandescent lamps and adaptors, dishwashers, geysers, cell phone chargers Foods and Associated Products – Prawns and canned fish - non compliance – mostly pathogenic Vibrio spp and these products were imported. The estimated monetary value of these products is R 47,918,730.00 Legal Metrology - The total monetary value of products tested R million. The estimated value of the non-compliant products found is R17.4 million.

8 Progress on Commitments made to the Portfolio Committee

9 BACKLOG SHORT-TERM INTERVENTIONS - UPDATE
COMMITMENT Progress to date Separation of administrative from technical processes Separation of Administrative and Technical processes completed - Implementation ongoing Develop and piloted risk-based approach Low Risk & Medium Risk: Manual implementation on going using checklists. Human Resources Recruitment and Selection process underway, incumbents to start beginning April Interviews conducted 9 and 10 February 2017 Applications process during intervention period (Dec to Jan 2017) Applications Processed – 6 636 Applications above 120 days LOA issued Since Feb 2017, number of capturers has been increase 3 to 7 to deal with the backlog on LOA issuing stage. Applications cancelled - 145 Applications awaiting capturing – 1 404 Applications unassigned – 73 Applications in progress - 635 Applications pending awaiting industry response – 2 377

10 Business requirements received from business and built into the system
NRCS Systems Improvements Progress – SHORT TERM INTERVENTIONS The NRCS appointed a service provider to improve current CRM system for a period of six months. Business requirements received from business and built into the system The building was completed and ICT is currently doing quality assurance before testing. Delays experienced in User Testing which was planned for December 2016 due to user availability. Testing started on the 23rd Jan 2016 after the holiday recess and expected to be finalised by the end of February 2017

11 NRCS Systems Improvements Progress – LONG TERM INTERVENTIONS
Both Modernization and ERP specification were finalized in November 2016 but could not be advertised during December 2016 due to holidays recess period. The ICT steering committee met on the 17th of January and advised the CEO that the two specifications be combined. The CEO approved. Both specification were referred back to the BSC in line with SCM requirements. A new committee was appointed to combine and finalize the RFI Bid (BSC sat on the 2nd of February 2017 and document finalized & circulated for inputs to the ARC and ICT Steering committee.) The RFI will be finalized and advertised before the end of February 2017

12 Project Current Status
The e-EXCO resolved that the committee will now be headed by the CIO assisted by Mr Riyano after the resignation of the CFO. The e-EXCO also resolved that the project teams be dissolved and the functional areas as identified be dealt with by the main committee. The CEO emphasized that business must sign off on their business requirements for the project as part of the business reengineering process. The NRCS will also appoint an external Project Manager to manage the project due to its size and impact.

13 NRCS Systems Improvements Progress – SHORT AND LONG TERM INTERVENTIONS
Document NRCS processes and identify areas of Improvement Benchmark with similar entities for best practices Re-Engineering of NRCS processes in line with NRCS Strategic Objectives & Implement an ICT Solution that meets NRCS requirements 08/16 09/16 10/16 11/16 12/16 01/17 12/17 01/18 06/17 88% Complete 10% Complete 6 Months – 18 Months Completed Tasks -Appointment of Service provider (6 Months period) System Optimisation -Fix Errors on system -Allocate user roles System Enhancement -Gather Requirements -Document and Sign off Completed Tasks -Project Approval -Engagement with Local vendors

14 Actual Performance Against set targets
(Non-Financial performance)

15 Strategic Goal 1: To develop, maintain and administer compulsory specifications and technical regulations Performance Indicator / Measure Annual Target Quarter 3 Target Quarter 3 Actual Performance Variance Reason for Variance Number of new VC’s/Tech Regulations submitted to the dti for approval. 10 Compulsory Specifications/ Technical Regulations 4 Compulsory Specifications/ Technical Regulations 1 VC/TRs submitted to the dti for approval/1st gazetting -75% Inadequate capacity within the Regulatory Research and Development area Administer Review Board: % of Review Board decisions finalised within 30 calendar days 100% None

16 Compulsory Specifications submitted to the dti
VC 8076, Safety of Lighters ( First gazette) VC 8054, Chemical Disinfectants ( Final gazette) VC 8056, Pneumatic Tyres for passenger vehicles and their trailers ( Final gazette) VC 8059 , Pneumatic Tyres for commercial vehicles and their trailers ( Final gazette) VC 8013, Hydraulic brake and clutch fluids (Final gazette)

17 SG 2: To maximise compliance with all specifications and technical regulations: Automotive
Performance Indicator / Measure Annual Target Quarter 3 Target Quarter 3 Actual Variance Reason for Variance Corrective Action Number of Inspections conducted by the NRCS – Automotive, Electro-technical, CMM and Legal Metrology 18 900 4 345 4 706 +8,3% More retail inspections were conducted due to the need to respond to non-compliant products in the marketplace. No Action Required Percentage of Inspections conducted on locally produced, imported and exported canned fishery and meat product consignments   100% of inspections conducted on all declared produced canned fishery and meat products Inspected 100% of all declared consignments and productions   Total Inspections conducted 5988 No Variance N/A

18 SG 2: To maximise compliance with all specifications and technical regulations: Chemicals, materials and mechanicals Performance Indicator / Measure Annual Target Quarter 3 Target Quarter 3 Actual Variance Reason for Variance Corrective Action Number of inspections conducted on locally produced Frozen products and fishery and canned meat processing factories and vessels in accordance with the compulsory specification and procedures 2 135 inspections 511 inspections 529 3,5% Land based facilities are inspected by the NRCS on request by the Industry. The number of requests received in this quarter were higher than expected. No action necessary at this stage. Percentage of approval applications processed within the set timeframes 90% of all approval applications processed within 120 calendar days 47% (1 742 out of 3 739) of all approval applications processed within 120 calendar days -43% 1) Backlog within the Electro-technical domain 2) Inadequate Capacity 3) Applications submitted without all required documents or unacceptable Test Reports 4) Delays in implementing dormant VCs within CMM Implemented overtime Appointed new employees Utilizing field inspectors to eradicate the backlog Implemented the 30 days cancellation policy for applicants who fail to respond to NRCS findings

19 Breakdown of Approvals per Industry (Business Unit)
Opening Balance Applications received during the quarter Processed and Finalised within 120 days Processed and Finalised over 120 days Total Approvals Finalised Applications carried over to Quarter 4 % Within 120 Days Legal Metrology Gaming Applications 102 356 250 208 100% Legal Metrology Type Approvals 73 49 58 1 59 63 98% CMM Approvals 423 54 38 70 108 369 35% Automotive Approvals* 1802 1037 888 31 919 1882 97% Electro-technical Approvals** 5170 2919 508 1895 2403 5583 21% Total 7570 4415 1742 1997 3739 8105 47%

20 SG 3: To inform and educate our stakeholders about the NRCS
Performance Indicator / Measure Annual Target Quarter 3 Target Quarter 3 Actual Performance Variance Reason for Variance Number of stakeholder consumer education events or campaigns 12 NRCS consumer education events or campaigns 3 NRCS consumer education events or campaigns 4 Consumer Awareness Campaigns were conducted +33% The variance was due to the Poultry workshop that was organised by the Department of Agriculture, Forestry and Fisheries

21 Strategic Goal 4: To ensure an optimally capacitated institution
Performance Indicator / Measure Annual Target Quarter 3 Target Quarter 3 Actual Performance Variance Reason for Variance Corrective Action Percentage (%) of vacancy rate 6% 9.62% vacancy rate as of 31December 2016 . Resignations and retirements coupled with a moratorium on filling of vacancies as a measure to manage Human Resources costs Filling at least 5 vacant posts during Quarter 4 Developed, approved and implemented ICT Master System Plan (MSP) Develop and approve ICT Master System Plan Draft concept for MSP finalised Draft Master Systems Plan (MSP) developed and circulated for IT Steering Committee in January 2017 MSP was referred back to take into consideration the need to modernize the NRCS

22 Human Resources Staff Complement – Total 300 comprising of 293 permanent staff and interns. One appointment was made during the quarter Five terminations Three resignations One dismissal One by mutual separation Vacancies 29 budgeted vacant positions Vacancy Rate 9,62% NRCS prioritising the appointment of the Deputy CEO and CFO Staff training NRCS awarded bursaries worth about R to employees commencing studies at various higher institutions of learning in 2017 calendar year

23 Financial Performance

24 Financial Overview: Income Statement

25 Financial Overview: Revenue

26 Financial Overview: Revenue

27 Financial Overview: Expenditure

28 Financial Overview: Expenditure

29 Financial Overview: Expenditure

30 Progress on Revenue qualification

31 Recap: Revenue Qualification
Grap 23 – Non-exchange Revenue Revenue recognition based on a taxable event Taxable event different from the timing of revenue NRCS Act, NRCS Regulations Taxable event is the import / manufacture of regulated products Unclear timing of revenue Weak on punitive measures Systems and controls Systems and processes that allow for timely recognition of revenue Integrated information Integration of information internally (Surveillance, Approvals and Revenue) Third party integration

32 Recap: Revenue Qualification Plan
Internal control improvements NRCS Modernisation ERP system implementation Business process re-design SARS Collaboration Information sharing and system integration Legislative options Legal opinion re: NRCS Act Amendment to the Act, or Engage the dti on the NRCS Act LOA Conditionality Quarterly volumes forecast Introduce LOA validity period

33 Revenue Qualification Plan: Progress
Progress to date NRCS Modernisation ERP system implementation Business process re-design Request for information has been revised to ensure full integration across systems within the NRCS Implementation strategy was discussed and agreed with ICT Steering Committee and Audit and Risk Committee SARS Collaboration Information sharing and system integration HSS codes project with SARS was finalised Way forward: Roll out to all NRCS regulated commodities (Planning phase) to be combined with the modernisation project Legal opinion re: NRCS Act To determine if the NRCS Act needs to be amended the dti has indicated that changing the NRCS Act and Regulations will be a lengthy process, therefore the NRCS will proceed with implementing business process re-design based on current legislation LOA Conditionality Quarterly volumes forecast Introduce LOA validity period In the process of investigating mechanisms to operationalise Pending resolution of the LOA backlog

34 Challenges

35 Audit findings

36 Key challenges Operational challenges Border enforcement challenges:
Inadequate capacity and relatively unstable human resource environment The application and regulation of products covered under Compulsory Specifications that are outdated. High transportation and storage costs for confiscated goods. Long turnaround times and capacity constraints at the test houses compromises the effectiveness of the Regulator Border enforcement challenges: Inadequate information supplied on the bill of entry and shipping manifests High number of abandoned goods at Ports of Entry which results in high transportation and storage costs after confiscation. Revenue challenges Funding and Expenditure: NRCS performing mandates that are not fully funded, reduction in funding in the current and prior year and relatively high employee costs. Collection dependent on the industry co-operation Declining economic activity impacting revenue collection

37 Abbreviations and Acronyms
AG – Auditor General CMM – Chemicals, Materials and Mechanical DAFF – Department of Agriculture, Forestry and fisheries FY – Financial year LOA – Letter of Authority NBR – National Building Regulations NCC – National Consumer Commission SABS – South African Bureau of Standards SAPS – South African Police Services SARS – South African Revenue Services TR – Technical Regulation VC – Compulsory Specification YTD – Year to Date