1 LCLS Lehman Review February 7-9, 2005
XTOD FY06 Schedule LCLS Lehman Review February 7-9, 2005

2 XTOD Transports Photons from e- Dump to FEH
Electron Dump Near Experimental Hall Linac Far Experimental Hall Undulator Hall Electron Transport Front End Enclosure X-Ray Tunnel

3 The FEE contains the majority of XTOD instruments and diagnostics
Slit Be Mirrors 2 & 3 Diagnostics Package Collimator 1 Solid Attenuator Fast close valve Gas Attenuator Ion Chamber Ion Chamber SiC Mirror 1 SiC Mirror 2

4 Near Hall Contains XTOD Transport , Penetrations, and Diagnostics
Package

5 Tunnel Contains XTOD X-Ray Beam Transport System

6 XTOD Staff by Discipline
Rodney Victorine Resource Manager Jolyn Scholes Resource Analyst R. Bionta LLNL LCLS Project Leader D. McMahon XTOD Project Engineer C. Kelly-Clark Administrator M. Eberstein G. Otani Procurement EE E. Ables ME P. Duffy M. Mckernan S. Shen J. Trent L. Tung Comp. & Ctrls K. Fong K. Kishiyama S. Lewis L. Ott Physics S. Friedrich S. Hau-Reige R. London M. Pivovaroff D. Ryutov Hazards R. Beale

7 XTOD Organization by WBS
1.5.1 Management and Safety Account # Controls Account # FEE Mech/Vac Design Account # Slit Account # Wave Model Account # Steve Lewis x Keith Kishiyama x William Abraham x Mark McKernan x John Trent x Stewart Shen x Pat Duffy x Louann Tung x John Trent x Pete Tirapelle x Linda Ott x Richard Bionta x Donn McMahon x Rodney Victorine x Monte Carlo Account # Gas/Solid Attenuator Account # Hazards Control Richard Beale x Kirby Fong x X-Ray Tunnel Mech & Vacuum Account # Dmitri Ryutov x Stewart Shen x Martin Roeben x Keith Kishiyama x Direct Imager Account # Procurement Mike Eberstein x Gary Otani x Stewart Shen x Pat Duffy x Louann Tung x John Trent x Paul Pax x Elden Ables x TTF Damage Experiment Account # Indirect Imager Account # Stefan Hau-Riege x Rich London x Mike Pivovaroff x Sasa Bajt x Elden Ables x FEL Offset Mirror System Account # Total Energy Account # Mike Pivovaroff x Sasa Bajt x Stephan Friedrich x Owen Drury x Elden Ables x Spectrometer Account # Mike Pivovaroff x Paul Pax x

8 systems being designed and the remaining significantly advanced.
The XTOD development plan will conclude with operations commencing in March ‘09 FEE NEH Tunnel FEH FY06 Final Design Procurement - Prep Preliminary Design FY07 Procurement Build/Test/Install FY08 Commission FY06 is characterized as the “Design and Thinking” year with the majority of systems being designed and the remaining significantly advanced.

9 XTOD milestones were chosen to lower risks and meet the required commissioning sequence
Higher risk/complexity systems typically have early milestones to ensure adequate development time

10 An aggressive gas attenuator schedule including a prototype sequence is the XTOD critical path
Prototype efforts are intended to minimize development risks and ensure an on time delivery of a system meeting the required performance requirements

11 XTOD is approximately 24% complete and is tracking schedule and performance plans
FY07 is the largest funding year at $12M and includes almost all XTOD procurements

12 Several system documents and reviews have been defined as key schedule milestones
Target XTOD Dates Key Documents Design Reviews WBS Description PRD ESD CDR PDR FDR FEE Mechanical & Vacuum (.01) NEH Mechanical & Vacuum XVTS Mechanical & Vacuum - (.01) FEH Mechanical & Vacuum TBD Fixed Mask 3.3.06 Slit Attenuator FEL Offset Direct Imager Indirect Imager Ion Chamber Total Energy Monitor Spectrometer

13 XTOD work flow will follow ISMS practices for each WBS element
WBS Dictionary LCLS Physics Requirements ICDs IWS (Integrated Work Sheet) is LLNL wide e-form for documenting ISMS for each work package: Scope Hazards Controls Roles (RI…) Responsibilities Training Signoff Hardware Installation Operations Servicing ERDs Designs Eng. Safety Notes Certified Parts Lists

14 Integrated Safety Worksheets will be Developed for Each Task
Current IWS Documents IWS # Title Status Low Current (<1005A) X-Ray Source Operation Active/Approved 12662 r5 LLNL Collaboration at Stanford LCLS: Off-Site Work 12877 LCLS Optics testing at DESY laboratory in Hamburg Germany 12599 r3 Testing of Prototype Gas Attenuator Vacuum System 12920 LCLS X-Ray Tunnel Vacuum Transport System In Review 13253 LCLS Solid Attenuator Draft

15 Summary XTOD schedule reflects an achievable plan Key staff has been assembled to meet the development plan XTOD is tracking the plan The critical path item is being actively scrutinized to ensure success Work flow follows the principle of ISM