Presentation is loading. Please wait.

Presentation is loading. Please wait.

ESS Value Engineering and Cost Reduction Initiative

Similar presentations


Presentation on theme: "ESS Value Engineering and Cost Reduction Initiative"— Presentation transcript:

1 ESS Value Engineering and Cost Reduction Initiative
John Haines Project Manager 1 Feb 2017

2 Outline What are we doing? How are we doing it? Why are we doing it?
Initial Results

3 What we are doing: Value Engineering and Cost Reduction Initiative
Substantial progress has been achieved during the past year on updating the ESS Project plan, budget forecasts, and risks To manage ESS Project within agreed budget constraints, we launched a Value Engineering and Cost Reduction exercise in Nov 2016 Finding solutions that deliver the same or similar scope at a lower cost – Value Engineering Looking into possibilities to defer scope to Initial Operations and Operations including consequences for such deferral Looking at possible scope reductions

4 How we are doing it: Value Engineering and Cost Reduction Process
Systematically review all remaining work scope to identify cost saving and reduction opportunities Include approved budget as well as forecast items In-Kind Contributions are to be considered, but they are complicated … Primary Objective: find cost reductions while Maintaining ultimate capability of 22 world-class instruments in user program with 5 MW machine and high neutron brightness Maximizing scope within construction project This initiative will be a continuous and on-going effort

5 Why we are doing it: Measures are being implemented to manage within funding envelope
Conclusion: “Value Engineering” initiative launched in 2016 to find cost reductions to offset forecast increases and deal with remaining risks

6 Progress on Value Engineering and Cost Reduction Exercise
Potential VE and Cost Reductions (k€) Category CF Accel Target ICS NSS Central Services* Total CR 29,194 2,636 4,630 1,218 - 3,437 41,115 EAC 1,000 33,000 2,300 470 1,751 38,521 EVAL 13,436 60,000 4,140 7,735 6,998 92,309 NO 32,174 13,441 16,877 945 6,078 69,516 75,804 109,077 27,947 10,368 18,264 241,461 * Includes Project Support & Administration, ESH&Q, Communications, DG Services, and Technical Management Services Ready for change in baseline or forecast Evaluating Eliminated Legend CR Process Change Request immediately EAC Implement into Estimate at Completion (EAC) forecast immediately EVAL More evaluation needed NO Do not implement

7 Cost Reduction Measure Estimated Reduction- M€
Summary of Cost Reduction Measures Ready for Implementation in Baseline or Forecast (Items ≥ 1 M€ shown below) Cost Reduction Measure Estimated Reduction- M€ Comment Reduce RF system for HB section (beam power/energy reduced to 3 MW/1.3 GeV) 23 D Straightforward to recover during initial operations Outsource electric grid 17 Reduce forecast need for cost to accelerate some IKCs 10 S Outsource Central Utility Building 7 Preparing to tender Labor and services reductions (streamlining work and converting consultant positions to employee positions) 5.5 Spread across many parts of ESS De-scope Logistics Building 3 Use other areas Defer delivery of Rem Handling transfer casks Need to restore early in initial ops Use cheaper type of stainless steel for monolith shielding 1.6 Use 304 type SS vs. 316 Use cheaper facades for some buildings 1.4 Defer development/deployment of some final aspects of ICS 1.2 Misc. reductions in phone subscription, travel, recruiting, office supplies, … 1.1 Reduced site landscaping 1 Total cost reduction = 80 M€ Savings = 33 M€, Deferrals = 47 M€

8 Cost Reduction Measure Estimated Reduction- M€
Summary of Cost Reduction Measures Still Under Evaluation (Items ≥ 1 M€ shown below) Cost Reduction Measure Estimated Reduction- M€ Comment Deferral of cryomodules, modulators, etc. to reduce power/energy to 3 MW/1.3 GeV ? Disrupts IKC partner's work/contracting; significantly higher cost and delay to restore full capability Reduce initial build-out of Instrument Support Buildings 7 Defer building several floors in the 5 buildings Defer ICS based on other sub-projects 5.2 Remove birds nest roof 4.2 Need approval of revised building permit; potential delay associated with redesigning structures Eliminate on-site solidification of spent ion-exchange column resin 3 Send material to Swedish nuclear waste company (SVAFO) ICS savings from reorganizing work 2.5 Relax or defer surface treatment in rad areas Move guard house to Campus Scope 2.3 Reduce number of MB modulators by 2 to take advantage of lower acceleration gradient 1 Change incoterms from DDP/DAP to FCA for commercial contracts Renegotiate consultant contracts Total cost reduction = 92 M€ Savings = 20 M€, Deferrals = 72 M€

9 Selected Cost Reduction Measures Eliminated from Further Consideration
Estimated Reduction- M€ Comment Defer building 4 of 5 Instrument Support Buildings; concrete slabs only 12.4 Defers/delays essential capabilities needed for early instrument operation and science success Group spoke cavities to better utilize HPRF capability 9 Availability risk; affects IKC package Defer delivery of Active Cell Equipment 6.2 Risk of having to perform installation in contaminated environment Reduce by 1/2 the initial size of the long beam line hall 4.1 Too many early instruments need to be in this hall Defer hydrogen moderator; use dummy water moderator for early ops 4 Schedule delay; no cold neutrons in early operation; will need to commission cold moderator in activated environment Elimination of off-line testing for cryomodules 3.4 Inconsistent with design approach Change monolith internal shielding to carbon steel with protective coating 2 Corrosion risk; contamination issues during maintenance operations Eliminate Stainless Steel liner in Active Cell 1.1 Already contracted, costly maintenance and decontamination during operations Total cost reduction = 69 M€ Savings = 31 M€, Deferrals = 38 M€

10 Budgetary outlook with initial round of VE planned changes
Situation before Value Engineering and Cost Reduction Exercise Conclusion: This is a good start but we need additional cost reductions to deal with risks (some ideas shown in slide 8)

11 Concluding Remarks Value Engineering/Cost Reductions are needed to manage within funding constraints Primary objectives are: Maintaining ultimate capability of 22 world-class instruments in user program with 5 MW machine and high neutron brightness Maximizing scope within construction project


Download ppt "ESS Value Engineering and Cost Reduction Initiative"

Similar presentations


Ads by Google