Presentation is loading. Please wait.

Presentation is loading. Please wait.

Environmental Safeguard Requirement of Project

Similar presentations


Presentation on theme: "Environmental Safeguard Requirement of Project"— Presentation transcript:

1 Environmental Safeguard Requirement of Project
By Rajan Kumar Shrestha Environmental Specialist

2 Organization of Presentation
Why Environmental Safeguard for Projects Project Classification Criteria Environmental Consideration during Project Cycles Environmental Assessment Environmental Consideration During Impact Identification Glimpse of Impact Due to Road Construction Adverse Impacts & Mitigation Measures Environmental Management Plan/Site Specific EMP (Sample) Monitoring Indicators in Implementation Phase Integration of Environmental Safeguard in Project Forestry clearance procedures for Project

3 Why Environmental Safeguard for Project
To fulfill the legal requirements as stipulated in EPA, 2053 and EPR, 2054,GoN Apart from the EPA and EPR, the Forest Act (1993) and Regulation (1995) requires permission from related authorities for any intervention in forest area. To fulfill requirements of Donor (WB/ADB/DFID) Safeguard Policy ADB: Safeguard Policy Statement 2009 WB: Environmental and Social Framework 2018 DFID Policy: Adapted from DFID Environment Guide (2003).

4 Project Classification Criteria
I EPA EPR: The project classification criteria largely depend on the basis of proposal size. The Schedule-1 and Schedule-2 under Rule 3 of EPR categories the proposals requiring IEE and EIA respectively.वातावरण-संरक्षण-नियमावली.pdf II Sensitive Area Criteria: For this purpose, inclusion of the project area within the sensitive area (protected area) will be checked. III. Capital Investment Criteria: Schedule 1 (J) of EPR 1997, states that the operation of any plan, project or programme of any development work, physical activities or change in land use with a cost of Rs.50 millions to Rs. 250 millions require IEE study except the proposal mentioned in Clause (A) to (I)

5 Environmental Consideration during Project Cycles
Consideration of Environmental Safeguards Project identification Pre-feasibility study Environmental screening Decide whether the project need IEE or EIA or none of both Feasibility study Project with IEE study, Undertake preliminary environmental assessment (IEE for ToR) Project with EIA study, Undertake scoping, Prepare ToR for EIA Undertake IEE/EIA study (…… section for steps) Baseline data collection Identification of impacts Propose mitigation measures and estimate cost Prepare monitoring plan and estimate cost Preparation of EMP

6 Detail design/cost estimate/contract package
Field verification and updating of EMP Estimate cost to mitigate the analyzed impacts Include environmental mitigation measures cost in engineering cost estimate Project implementation Integrate environmental activities with engineering activities to ensure EMP implementation Implementation of EMP and measures Undertake monitoring Provide feedbacks to the implementation team Consider feedbacks in implementation Prepare monitoring report Project operation & maintenance Undertake ongoing monitoring Provide feedbacks Consider feedbacks for implementation Carry out auditing Undertake environmental auditing for EIA level projects after two years of project commencement.

7 Level of Environmental Study as Per EPA, EPR in Road Sector
S.N Proposals requiring IEE Proposals requiring EIA 1 New construction of District roads National highways 2 New construction of Urban roads Major feeder roads 3 National highways and feeder roads improvement, rehabilitation and reconstruction Construction of more than 50 km long ropeways 4 Construction of 5 to 50 km long ropeways Construction of more than 5 km long cable car 5 Construction of 1 to 5 km long cable car Clearance of forest area more than 5 Hectares 6 Construction of major bridge Any Projects which is to be constructed within Sensitive Area (Historical, Cultural and Archaeological; Ecologically Sensitive and Wetland Area; National Park, Wildlife Sanctuaries and Conservation Area 7 Constructions of tunnels 8 Improvement, up grading and reconstruction of national highways and feeder roads

8 IEE/EIA Approval Process
Proposal from Proponents (with Baseline Information) Incorporate EMP recommendations into Detail Design/BoQ EIA Required Scoping 15 day notice Prepare TOR Approval of TOR by MOFE EIA Study Including Public Hearing Prepare EIA Report Including EMP Submit EIA Report to Concern ministry for review Submit EIA to MoFE Public Notice for Review of EIA Approval of EIA by MoFE Monitor EMP Compliance during Construction Screening (Based on EPR Schedule) Field Verification (Screening Checklist) IEE Required Prepare TOR by Proponent Approval of ToR by Concern Ministry Prepare IEE Report Including EMP Approval by Concern Ministry IEE/EIA Approval Process 8

9 Environmental Assessment
Project Description Project Activities: Baseline data collection: Physical, biological and socio-economic and cultural environment IEE Field Format_Final.doc Review of literature (reports, maps etc) Walk over/ walk through survey/inspections/observations, Survey format Making measurements, Test Focus group discussion with communities and other stakeholders

10 Environmental Consideration During Impact Identification
Physical Impact Land use patterns Damage to natural landscape Spoils thrown onto water sources, agriculture land, forest area Disturb to natural drainage patterns consequently pouring of surface runoff Air, Noise and Water pollution Operation of quarry/borrow sites Slope instability,landslide, erosion Impact due to establishment and demolition of construction camps Impact due to stockpiling of construction material and locations Crusher plant Bitumen Plant, Batching plant

11 Biological Impact Forest area clearance area
Number of felling of forest trees and vegetation Disturbances to wildlife , habitat, corridor Disturbance to wetlands of bird habitat Felling of protected tree species Disturbance to aquatic ecosystem

12 Socio-economic and Cultural Impact
Loss of private land, standing crops, and farm trees Loss of private structure Loss of community as well as cultural structures (Irrigation canal, water supply, Electric pole, access road, foot trail, Chautara , temple & monument Livelihoods (water mills, employment & income) Public health & safety

13 Glimpse of Impact Due to Road Construction

14 Change in Land Use Pattern

15 Depletion of Forest/Forest resources

16 Loss of Private and Public Properties

17 Spoil Disposal

18 Control of landslide and slope failures

19 Due to surface Water

20

21 Disruption of Irrigation canal

22 Agricultural field and irrigation canal affected by road construction

23 Air Pollution

24 Strip Map Showing Issues of Project

25 Adverse Impacts & Mitigation Measures
Examples of Potential Impacts and Proposed Mitigation Measures.docx

26 Environmental Management Plan
The Environmental Management Plan (EMP) is a guide to help in implementing augmenting beneficial impacts and minimizing adverse impacts. . The EMP : Identification issues on environment (i.e. beneficial and adverse impacts); Selection of realistic mitigation measures; Institutional role and responsibility; Provision of monitoring; Implementation schedule: Cost for implementing the EMP. Integration of EMP into the project’s design,, specifications, cost estimates, bid documents/BoQ, contract/agreement clauses.

27 Site Specific EMP (Sample)
Chainage Location Issues/Significance Likely Potential Impact Suggested Mitigation Measures BoQ/Cost Time of Action Respon-sibility 2+090 Bahun Gaun Scouring: Water from rivulet crosses the road and scours. Induce land slides/ erosion and Gully formation Masonry line drain approx. 50 m length 20 cum /NRs.200,000 During construction Proponent/Contractor 2+400 River Crossing: Risheshwor / Khaire river crosses the road and has started bank cutting. Wash away road and cultivated land. Gabion wall and tree plantation on both sides of road. Client/Contractor

28 Cost of compensatory plantation
Do Forest: The road is narrow. There is community forestry on both sides of road. 25 trees needs to be cut. Permission from MOFE/DFO/CFUG is taken, Tree plantation at a rate of 1:25 along road side between to 4+270 Cost of compensatory plantation During construction DFO/Client 9+480 to 9+500 Land Slide: A landslide 15 m high and 20 m wide is present here. Re-occurrence of landslide will damage the road and house situated on the other side. Gabion wall 4 m high and 20 m long for toe protection, grassing vertically for efficient drainage.

29 Access Trail: There is an access trail to Ramche gaun.
9+560 Ramche Dobato Access Trail: There is an access trail to Ramche gaun. Difficulty in movement. Improvement of access foot trail by stone pitching for 15 m (3 m3) and leveling. During construction 9+880 to Sitapur Low lying area: The area is low lying that could lead to inundation Risk to damage the road, blockage of side drain Hume pipe installation, embankment height 0.5 m lower in this section 10+100 Dadagaun Drinking Water Tap: Water tap with 1 inch GI pipe is installed within 2 m from centre line. 25 HH use this tap for drinking and household water. Damage to the pipe will interrupt water supply for 25 HH Tap will be relocated 20 m towards the road end, where there is a small parcel of barren land.

30 Monitoring Indicators in Implementation Phase
S.N Type of Environment Monitoring Indicator 1. Physical Land degradation (e.g. salinization, acidification, alkalinization, soil pH) Slope instability (e.g no. and size of landslides, slope failure); Scares formation (e.g. damage of aesthetic value in a ropani/kattha land); Loss of agricultural land (e.g. conversion of farmland into infrastructure, such as road, canal in ha); Induced erosion and sedimentation (e.g. rate of soil loss and runoff, erosion mt/ha); Alteration in streams; Erosion on stream banks and valley sides (e.g. slightly, moderately, severely); Damage through spoils (e.g. slightly, moderately, severely, area in ha) Fugitive dust problems (e.g. slightly, moderately, severely);

31 Biological environment
Effect on natural growth (e.g. damage of natural forest); Effect on managed growth (e.g. damage of planted forest); Loss of forest/tree species (e.g. no. of felled trees) Loss of bushes and habitats (e.g. conversion of bushes area in ha.); Poaching of mammals, and birds (e.g. no. of types of mammals and birds poaching); Social, economic, cultural environment Site accidents (e.g no. of minor, medium and major accidients); Members of public (passing routes) (e.g No of pedestrian); HIV (e.g. no. of labour infected); Effect on indigenous people (e.g. effect on manjhi); Labour opportunities (e.g. employment days/year); Economic status (e.g. income Rs/year/hh); Damage to home (e.g. no. of houses damage); Damage to Chautara, Pawti Pauwaa, graveyard, monument, shrine, architectural sculpture; and Damage to temple, shrine, monumental painting, cave or wall.

32 Environmental Monitoring Checklist

33 Disturbance of Biodiversity and Wildlife

34 Mitigation Measures Sample of Overpass Afforestation
Reinstate of Irrigation canal

35 Integration of Environmental Safeguard in Project
Safeguard Screening Integration of Safeguard works in BoQ Bid Invitation Regular Monitoring Grievance handling Implementation of EMP- VCDP-GAP Formation of Committees IEE/EIA&S-EMP Assistance distribution-Deed Transfer Civil Contract Award Field Assessment-Baseline/Impact record Collection of recommendation/consent Site clearance (forest/structures/utilities

36 Forestry clearance procedures for Project
SN Action Responsibility 1 Identification of forest area needed for road project Project 2 Permission from DNPWC/MoFE to conduct EA 3 Preparation of IEE/EIA study 4 Approval of IEE/EIA Concerned Ministry/MoFE 5 Determination of national priority project NPC 6 Request letter to MoFE to forest/ tree cutting, verification report Project through Ministry, DOF/DFO 7 Forestry clearance approval GoN (Cabinet) through MoFE 8 Tree marking, felling and transportation Project with DFO/Warden/CFUG 9 Sale of felled trees DFO/Warden /CFUG 10 Compensatory plantation work Project or DFO/Warden/CFUG 11 Monitoring of compensatory plantation MoFE/concerned Ministry

37 THANK YOU Rajan Kumar Shrestha E-mail: rkshrestha11@gmail.com
Tel: (M)


Download ppt "Environmental Safeguard Requirement of Project"

Similar presentations


Ads by Google