Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Management © 2008 D. J. Foreman.

Similar presentations


Presentation on theme: "Project Management © 2008 D. J. Foreman."— Presentation transcript:

1 Project Management © 2008 D. J. Foreman

2 Introduction What makes a successful project? All tasks included
Project completed on time Quality maintained Constraints upheld Decision points clearly visible © 2008 D. J. Foreman

3 Graphical Tools Gantt Chart shows dependencies with time relationships
Pert Chart shows dependencies without time relationships © 2008 D. J. Foreman

4 Example – the 'student business' schedule
© 2008 D. J. Foreman

5 Terms -1 Schedule set of tasks and their sequence
Task non-divisible piece of work Current date today's date As-of date separates past and future, (shown as a vertical bar). Allows schedule to 'float' in time and/or be used as a template. Use with "Force future tasks after As-of Date" or an equivalent option. © 2008 D. J. Foreman

6 Terms -2 Link (FF, SS, FS,SF) (sequential) joining of tasks
Status current state of a task Dependency a timing relation between tasks Predecessor task that comes earlier Successor task that comes later Conflicts attempt to simultaneously use exclusive resources © 2008 D. J. Foreman

7 Terms -3 Duration length of a task/project
Completion amount of task finished Critical Path set of consecutive tasks with no delays allowed Milestone task event at a specific date/time has zero duration Span/summary task synopsizes sub-tasks © 2008 D. J. Foreman

8 Terms -4 Resource people, materials, etc
Slack (positive) permissible delay Slack (negative) time that must be recovered to prevent lateness Baseline record of original schedule Future Tasks begin in the future Fixed Tasks specific start/end dates/lengths © 2008 D. J. Foreman

9 Getting Started Load the default schedule from my web page
File / Save as… your name File / Task Info Change start date to specified date Change File/Properties to your name Rename tasks Change any other data as needed © 2008 D. J. Foreman

10 Task Scheduling-1 ASAP Start on 'as-of date', or as soon as possible thereafter Fixed Start/end dates locked-in ALAP Start as late as possible © 2008 D. J. Foreman

11 Task Scheduling-2 Must Start task must begin on this date
Must Finish task must end on this date Critical succeeding tasks cannot start until this task finishes. Required dates may be in trouble. © 2008 D. J. Foreman

12 Types of Links (and delays)
FS FS SS SS FF FF © 2008 D. J. Foreman

13 Gantt View Fields Field Values Status critical path late complete
resource overscheduled delayed (overscheduled resources) scheduled must start (on/after) must finish (on/after) ASAP, ALAP © 2008 D. J. Foreman

14 Gantt View Fields 2 Field Values ID numeric code to identify the task
Slack amount of time before a task is late Duration time to complete a task (date) Effort resource requirement (hours, days, weeks) Dates start, end, late WBS Work Breakdown Structure - identifies tasks based on their position in the schedule OBS Organization Breakdown Structure - identifies tasks by resource group, cost center, or accounting code © 2008 D. J. Foreman

15 Types of tasks Duration Driven Fixed time to complete
Independent of resources Effort Driven Based on resources Time based on applied resources (not used in our projects) Split Assignment Allows for interruptions No effect on duration-driven tasks (same amount of 'work time' involved) Interrupt extends duration for effort- driven tasks © 2008 D. J. Foreman

16 Priorities & Resource Levelling
delaying tasks to resolve conflicts graphical view of resource availability have resource availability data Priorities determine which tasks get shifted during auto-leveling. Resource leveling Histograms Resource calendars Task Priorities © 2008 D. J. Foreman


Download ppt "Project Management © 2008 D. J. Foreman."

Similar presentations


Ads by Google