1 European Spallation Source ERIC
Status ESS Anders Sunesson RF group leader European Spallation Source ERIC

2 Welcome! Where are we? What is next?

3 RF Systems RF systems contains two work packages: RF systems provide
Power Converters RF systems provide The RF power to accelerate the particles The power converters to generate the high power RF The power converters for the magnets in the superconducting linac except the raster magnets All major components are designed and in most cases ordered, except high beta modulators, high beta klystrons

4 RF Systems Scope RF systems section: Power Converters section:
RF distribution systems High Power Amplifiers (e.g. klystrons) and auxiliary systems LLRF systems Interlock systems Master Oscillator and Phase reference distribution Power Converters section: HV modulators Spoke RF transmitters Magnet Power Converters

5 FREIA test facility Uppsala University
FREIA infrastructure for CM test Spoke serial CM tests High beta prototype test LLRF tests RF Amplifier Stations

6 High Level Schedule –RF systems
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Global & Project MS First Installations Isrc to DTL1 RBOT Start user program Isrc to DTL4 BOT NC RF systems Test/Commissioning completed Start Phase reference distribution Phase reference tested to dog-leg Start installation Spoke RF Tests completed Start installation Medium/High b RF Start installation Medium b High b

7 ESS schedule and goals Top accelerator goal: Beam through RFQ (MEBT, DTL1) during 2019 A lot to accomplish during 2019 to achieve this goal Beam on dump milestone June 2021 At this time all linac systems, including the complete medium beta LLRF systems, must be ready, installed, and commissioned Target RF group: All RF including Medium beta, installed before end 2020 (this is to allow debugging and commissioning) A lot to accomplish, too.

8 The ESS Project – The Big Picture
Today 2018 2019 2020 2021 2022 2023 2024 2025 ISrc to LEBT ISrc to DTL1 ISrc to DTL4 Beam on Dump (BOD) Accelerator Ready for Beam on Target (RBOT) Beam on Target (BOT) End of Construction Start Of User Program (SOUP)

9 Accelerator Timeline Today 2018 2019 2020 2021 ISrc to LEBT
3/9/2018 ISrc to DTL1 16/12/2019 ISrc to DTL4 17/8/2020 ISrc to Beam Dump (BOD) 14/6/2021 RBOT 13/9/2021 ISrc to LEBT Beam Commissioning 28 wks ISrc to DTL1 Beam Commissioning 13 wks ISrc to DTL4 Beam Commissioning ISrc to DMPL Beam Commissioning

10 ESS Accelerator Installation Overview
Today 2019 2020 2021 2022 ISrc to DTL1 16/12/2019 ISrc to DTL4 17/8/2020 ISrc to Beam Dump (BOD) 14/6/2021 RBOT 13/9/2021 ISrc to DTL1 Beam Commissioning 13 wks ISrc to DTL4 Beam Commissioning ISrc to DMPL Beam Commissioning NCL Installation (RFQ/MEBT/DTL1) NCL Installation (DTLs) NCL RF System Installation SPK CDS Installation SPK CM Installation SPK LWU Installation SPK RF System Installation Elliptical CDS Installation MBL CM Installation MBL LWU Installation MBL RF System Installation HBL CM Installation HBL RF System Installation HEBT/A2T LWU Installation Infrastructure

11 Milestone evolution

12 RF components in tunnel and gallery